Week 10 (PROJECT RISK MANAGEMENT) Flashcards

1
Q

Risk and uncertainty continuum

A
  • High Risk – Low Risk
  • Project Work – Production Line
  • High Change – Little Change
  • Control High – Control Low
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Objectives

A

The project’s objectives are defined by the project charter, the project plan and the individual plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Risk Identification (Why Projects Fail)

A

Risk identification identifies areas of risk, uncertainty and constraints, which might impact on the project and limit or prevent the project from achieving its stated objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Risk Quantification (Impact/Frequency)

A

Quantifying risks evaluates the risks, prioritizes the level of risk and uncertainty, quantifies the frequency of the risks occurring and the level of impact on the stated objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Risk Response

A

Response development defines how the project will respond to the identified risks, which could be a combination of elimination, mitigation, deflection or acceptance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk Control

A

The risk control function implements the risk management plan. This might involve in-house training and communication to the other stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Business Case

A

Outlines a course of action to address corporate requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project Charter

A

Translates the business plan into requirements at the project level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project Plan

A

Integrates all the individual plans to produce an optimum baseline plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Management System

A

Some objective do not relate directly to a deliverable but how the project is managed through the PM system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project Sponsor

A

There is no project sponsor linking the project to the company’s strategic need therefore, the company runs the risk of making a project that is not able to realize benefits for the company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project Organization

A

There is no project organisation structure therefore, the company runs the risk of functional manager prioritizing the allocation of resources for the depts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project Manager

A

There is no project manager with the single point of responsibility, therefore, the company runs the risk of no one coordinating the work as the project moves from one dept to another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project Team

A

There is no project manager or team leader managing and leading the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Office

A

There is no project office or central point to being all the project participants together

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Too Much Innovation

A

In practice, a project with too many untried and tested components runs the risk of teething problems.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Too Little Innovation

A

Market opportunities not considered resulting in too little design
therefore, there’s a risk of producing a project that is obsolete.

18
Q

Operators

A

The users are not involved in the design process therefore, the
company runs a risk of the company building a facility that is
difficult to operate.

19
Q

Stakeholders

A

Are not identified resulting in their needs and expectations not
being considered

20
Q

Configuration

A

The configuration between the components (deliverables) and
existing facilities are not considered

21
Q

Prototypes

A

The project is built before a functioning prototype or model is fully tested therefore, it runs a risk of expensive reworks and retrofitting.

22
Q

Build-Method

A

Not fully developed before the execution phase, therefore, it runs the risk of working becoming boxed-in resulting in expensive rework and delays.

23
Q

Scope Definition

A

If the scope is not defined the company runs a risk of the PM being unsure and confused as to what needs to be included or excluded.

24
Q

Scope Change

A

If there is no scope change control system, the company runs the risk of uncontrolled scope creep.

25
Q

Cost

A

The project budget is not clearly defined there is a risk of
uncontrolled expenses.

26
Q

Cash Flow

A

If cashflows are not forecasted there are risks of negative cashflows.

27
Q

Time (Critical path)

A

If the time (critical path) is not established there is a risk of
performing non-critical work.

28
Q

Procurement

A

Project procurement requirements are not planned there is a
risk of long lead times not being identified.

29
Q

Resources

A

A resource histogram of resource loadings are not produced,
the company runs the risk of not having sufficient resources to
complete the project as per the schedule.

30
Q

Project Control

A

If there is no project control being carried out the PM will have
to rely on intuition to know where best to allocate the resources.

31
Q

Quality

A

There is a risk when the quality requirements are not adhered to

32
Q

Communication

A

There is a risk if no communication management requirements are not adhered to.

33
Q

Document Control

A

There is a risk when the document control requirements are not considered.

34
Q

Project Meetings

A

Should the project meetings not be considered the company runs a risk as there will be no minutes.

35
Q

Quantitative Risk Assessment

A

Using various statistical techniques to evaluate risks.

36
Q

Qualitative Risk Assessment

A

Using educated opinions and expert judgements.

37
Q

Frequency of Risk

A

The frequency and likelihood of a risk occurring needs to be considered.

38
Q

Priority

A

To prioritize the risks which could possibly threaten a project’s completion or deadlines.

39
Q

RISK RESPONSE

A

Eliminate Risk= Looks at avoiding risks completely.
Mitigate Risk= Reducing the risk’s probabilities.
Deflect Risk= Deflecting the risk in full or in part to another party.
Accept Risk (with Contingency)= Accepting risk with a contingency plan.
Turn Risk into Opportunity= Identify opportunities from risks identified

40
Q

RISK CONTROL

A
  • Set Up Risk Control Sheet
  • Progress Meetings
  • Identify Risk
  • Agree Response
  • Monitor
  • Lessons Learned