Week 8: Earned Value Analysis Flashcards
Earned Value Analysis (EVA) allows the PM to answer the following 3 questions:
- Where have we been? (How much work done, how much $ spent)
- Where are we now? (Under/overbudget? Behind/ahead of schedule?)
- Where are we going? (Anticipated total cost, money required to complete project)
What is the Weighted Attributes procurement method?
why is it not that good?
Assess attributes and price with varying weightings to determine preffered bidder for cost and quality optimisation. Lacks transparency because of tradeoffs between price & non-price components leading to unexpected outcomes.
What is the Target Price (Purchaser Nominated Price) procurement method?
- Client sets budget in Request for Proposal. Specifies desired outcomes.
- Suppliers describe proposed solutions based on weighted evaluation criteria.
- Bids are scored. Winner is determined using weighted attributes method.
Useful when issuing request for proposal where client defines desired outcome but relies on suppliers to prepare best approach. Ensures optimal value within set budget.
What is the Price Quality procurement method?
Transparent version of Weighted Attributes method. Clients can see weightings. Increased transparency and sensitivity. Ideal for complex/high risk procurements where attribute weightings impact value for money.
‘reality check’ for clients
What is the Quality-based selection (Brook’s Law) procurement method?
Once the best supplier is chosen, client and suppliers collaborate to establish a ‘Target Outturn Cost’ (TOC).
Pain-share/gain-share mechanism to incentivise exceptional performance during project execution.
Ideal for uncertain project scope, challenging estimate price/ alliance
What is the Schedule of Values?
what is total SOV?
Detailed allocation of the contract sum into individual components of work.
-Basis for determining earned value for progress payments. What has been accomplished or earned.
- Total of SOV = contract price + contractor’s profit
What are Baseline Values?
Planned values:
- time
- dollars earned.
What is the Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV)?
The value of work planned or scheduled to be accomplished within a specific time period as illustrated in the schedule.
What is the Budgeted Cost for Work Performed (BCWP) or Earned Value (EV)?
The value of work completed measured in terms of planned value of work.
What is the Actual Cost of Work Performed (ACWP) or Actual Cost (AC)?
The actual cost incurred in the performance of the work for a given time period.
What is the Schedule Variance (SV)?
SV = EV - PV = BCWP - BCWS
What is Schedule Performance Index (SPI)?
SPI = EV/PV = BCWP/BCWS
What is Cost Variance (CV)?
CV = EV - AC = BCWP - ACWP
What is Cost Performance Index (CPI)?
CPI = EV/AC = BCWP/ACWP
What are the steps to drawing an Expense S-Curve (Planned Value)?
- Draw an ES Gantt chart for the project.
- Assign values linearly per day.
- Add cost values vertically to get daily totals.
- Accumulate daily values from left to right to get total.
- Plot accumulated figures on graph of cost against time. (S-Curve)
demonstrates progress for a variety of tasks as a whole
What is a SPI chart?
Plot Reporting Period (X) against SPI values (Y).
Graphically express estimated schedule performance.
What is a CPI chart?
Plot Reporting Period (X) against CPI values (Y).
Graphically express estimated cost performance.
What are the four main forecasts?
Estimate at Completion (EAC)
Estimate to Completion (ETC)
Variance at Completion (VAC)
To-Complete Performance Index (TCPI)