Week 2: Cost Estimating & Scheduling Flashcards

1
Q

What ways are there to estimate?

A

Parametric estimating, first divide a project into units of
work. Then, determine the cost per unit, and then multiply the number of units by the cost per unit to estimate the
total cost.

First Principles is the process of building-up prices, or rates, for an item or piece of work considering all the parts and activities needed to put it together

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

First Principles Estimating factors.

A
  • Waste
  • Labour
  • Productivity
  • Financials
  • Overheads
  • Contingencies
  • Risk
  • Profit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Equation for labour cost related.

A

■ Total cost of labour = Σ total work hour (i) * wage rate (i)

■ Total work hours = Σ quantity of work (i) / productivity rate (i)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Direct vs. Indirect Costs

A

■ Direct Costs:
Material
Labour
Equipment
Subcontracted items

■ Indirect Costs:
Project Field Office
Laydown yard
Project Management
Accounting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contingencies

A

■ Contingency is that amount of money added to an estimate to cover the unforeseen needs of the project, construction difficulties, or estimating accuracy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

8 Project Phases

A

1.Project Establishment
2.Concept Design
3.PreIiminary Design
4.Developed Design
5.Detailed Design
6.Procurement
7.Construction Admin
8.Post Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

WBS stands for…

A

Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Equation needed for float calculation

A

■ Total Float (TF) = LF - ES - dur
■ Start Float (SF) = LS - ES
■ Finish Float (FNF) = LF - EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cause of Unbalanced Bidding

A

■ Mathematically unbalanced:
◦ Bid containing lump sum or unit bid items which do not reflect reasonable actual costs
■ front loading
◦ Get more money at the beginning of the project by
overpricing the work done early in the project
■ Maximise Profit
■Material unbalance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly