1
Q

What engine is responsible for setting up the fill site?

A

Typically the fifth engine

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who becomes the Fill Site Unit Leader?

A

OIC of the fill site engine

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

While a minimum of two lines will be stretched off of the fill site engine how many units can be filled at once?

A

Only fill one unit at a time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the tanker flow calculation?

A

Total capacity of tanker minus 20% divided by the round trip time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Fire Flow Formula for Rapid Fire Control

A

(LxW)/3 x # of floors + 25% for each exposure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Dump tanks on tankers must equate to what?

A

Total size of dump tanks must at least equal capacity of tankers tank

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How many companies should get your preplan for non-hydrant areas?

A

The first 6 engine companies and tanker stations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Tanker Task Force?

A

One engine, three tankers, one command officer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does the second Chief do on rural water supply assignment?

A

Water Supply Group Supervisor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

First Engine on Rural Water Supply Assignment

A
  • lay out supply line from driveway to incident, this should be done from where the supply pumper and dump tanks are to located
  • assign 5th engine to fill site
  • lay out from 1st engine should include a siamese on the supply line
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

First Tanker on Rural Water

A
  • Pump water to first engine through siamese
  • Drop dump tanks, hard sleeves, low level strainer
  • Drop additional siamese and hose for the dump site engine
  • once a draft is established by dump site engine, dump water into dump tank and become part of shuttle ops
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Second Engine Rural Water

A
  • Engine driver sets up to supply water to first engine from dump site by hooking a line to the siamese
  • positions at dump tank and establishes draft
  • crew proceeds up for back up line
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Third Engine

A
  • Officer and crew assume control of the dump site
  • Officer assumes Dump Site Unit Leader
  • The DSUL will head up water supply ops until arrival of second chief
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fifth Engine Rural Water

A
  • Fill site
  • Officer becomes Fill Site Unit Leader
  • At least two lines off engine for filling incoming units
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How far can relay ops be conducted with 4” hose?

A

Over 1 mile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How often should dry hydrants be back flushed and tested?

A

Every 6 months

17
Q

How often should water storage tanks be checked by FD?

A

Every 6 months

18
Q

Nurse Tanker

A

-A tanker that proceeds with the initial attack engine to the incident scene and provides water as needed for the initial attack. This is used in a combination operation scenario where the initial layout of hose is over 1000’

19
Q

Whom does the Water Supply Group Supervisor oversee?

A

Fill Site Unit Leader and the Dump Site Unit Leader