Understanding Basic Concepts Of Prince2 Flashcards

1
Q

What happens once a project has finished and the final product has been finalised?

A

It goes into BAU - Business as Usual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Prince2 Agile?

A

• Configuration and adaption of Prince2, si Agile is most effective when combining Agile:
- Behaviours
- Concepts
- Frameworks
- Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of work is Prince 2 or Prince2 Agile suitable for?

A

• For projects only
• Not for BAU

(agile can be used for both)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List the characteristics of Project Work?

A

• Temporary
• A specific team is created
• Element of difficulty
• Degree of uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List the characteristics of BAU work?

A

• Ongoing work
• Stable/same team
• Routine understood tasks
• A deflgree of certainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Summarise Business as Usual work.

A

• Repeatable routine tasks by trained people
• No need for PM
• Work on existing products
• Relatively short timescales
• Long list of tasks arriving regularly throughout product lifespan
• An established team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Summarise Project work.

A

• Temporary situation
• Team assembled
• Address specific problems, opportunities, or a difficult change
• Could be a collection of BAU items to be handled collectively
• May need to engage many stakeholders
• Team maybe remotely scattered
• Needs a PM
• Has defined stages prior to delivery
• Layer of PM & Product Direction
• Team disbands after completion
• Finalised product goes into BAU

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define a timebox.

A

• Finite period of time where work is carried out to complete an objective
• Deadline cannot be moved (only prioritisation allowed)
• Low level TB: Sprints
• High level TB: Stage (Collection of low l TBs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What comprises the whole Prince2 framework?

A

• 7 Principles
• 7 Themes
• 7 Processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 3 overall stages throughout the Prince2 project lifecycle?

A

• Pre-project Stage
• Initiation Stage
• Management Stages (Project Delivery Stages)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the 7 Prince2 Processes?

A

• Starting Up a Project (SU)
• Directing a Project (DP)
• Initiating a Project (IP)
• Stage Boundary (SB)
• Controlling a Stage (CS)
• Managing Product Delivery (MPD)
• Closing a Project (CP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In Prince2 what is involved in the “Starting Up a Project” stage?

A

• Executive & PM involvement
• Is the project achievable?
• Creating a Project Brief
• Allows PB to make a decision to go ahead or require further investment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In Prince2 how does the project move from starting up a project stage to Initiating a Project Stage ?

A

• Project Brief submitted to the PB via a STAGE BOUNDARY
(aka Managing a Stage Boundary, turnstile, milestone, go no)
• Also to include Stage Plan for next stage
• Once submitted to PB, the PB deliberates whether to go ahead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who are 3 Prince2 Project Stakeholders?

A

• Business Executive (Business Interests)
• Senior User (User Interests)
• Senior Supplier (Creator Interests)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In Prince2 what is involved in “Initating a Project?

A

• Planning the project
• A high level plan (No. Of Stages/Project Plan)
• Creation of Product Initation Documents (PID)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In Prince2 what is the purpose of Product Initiation Documentation?

A

• Define the project
• Define rules (Approach, Risk, Quality, Communication, Benefits)
• Also include a Next Stage Plan by the PM
• In summary gives direction and scope & forms a contract between PM & PB
• Needs updating after each MS

Uses:
1. Ensure a sound basis prior to PB commitment
2. Act as a base document for PB/PM to assess progress, issues and on-going viability
3. A reference for the project for people joining the project

17
Q

In Prince2 what is the composition of the “Product Initiation Documentation”?

A

• PROJECT DEFINITION (Achieve: background, obj & outcomes l, scope & exclusions, constraints/assumptions, user/interested parties, interfaces)
• PROJECT APPROACH (Choice of solution & delivery approach)
• BUSINESS CASE (Justification based on costs/risks/benefits)
• PROJECT MANAGEMENT TEAM STRUCTURE (Who involved)
• ROLE DESCRIPTIONS
• QUALITY MANAGEMENT APPROACH
• CHANGE CONTROL APPROACH
• RISK MANAGEMENT APPROACH
• COMMUNICATION MANAGEMENT APPROACH
• PROJECT PLAN (how obj achieved, provide a baseline for progress via each MS)
• PROJECT CONTROLS (MS, tolerances, monitoring & reporting)
• TAILORING OF PRINCE2

18
Q

In Prince2 how does the project go from “Initiating a Project” to the “Controlling a Stage”?

A

• Creation of next stage plan
• Submission of Stage Boundary to the board
- Review of current stage
- Next Stage Plan
• PB to deliberate

19
Q

In Prince2 what is “Controlling a Stage”?

A

• Next Stage on from IP
• PM To oversee the work done by the teams
• Keep PB informed of progress
- Highlight Report

20
Q

How does a PM update the PB on “Controlling a Stage” management stages?

A
  • Via a Highlight Report
21
Q

What does a Team Manager do?

A

• Manage the product delivery team through multiple work packages.
• Ensuring work package completion
• Updating PM on progress
- via checkpoint report

22
Q

When are Work Packages created?

A

• During the Initiating a Project Stage
• Discussion between the PM and TM

23
Q

In Prince2 how are the Product Delivery stages (Controlling a Stage) moved forward to the next ones?

A

• Towards end, PM submits a Stage Boundary to PB
- Current stage review (End Stage Assessment)
- Next Stage Plan
• Deliverated by PB to approve

24
Q

In Prince2 summarise the ending of a Project

A

• Towards the end of last Delivery stage, PM checks off last WPs
• Once finished it’s closed
• PPD has been given to customer
• The PB closes the project!
• PB closes and workers go back to BAU
• Post Project Assessment

25
Q

What are the 6 Prince2 Tolerances?

A

• Cost
• Time
• Quality
• Scope
• Benefits
• Risk

26
Q

What does the Team Manager have to raise to the PM for Work Package Tolerance change?

A
  • Issue report

(PM cannot authorise outside stage tolerance)

27
Q

What does the PM raise to the PB for tolerance changes outside stage level tolerance?

A

• Exception

28
Q

What does the PB need to check when receiving an “Exeption” from the PM?

A

Continued Business Justification

29
Q

Where do the three levels of tolerance sit within the Prince2 “Processes”?

A

Project Level Tolerance [Directing a Project]

Stage Level Tolerance [Controlling a Stage]

Work Package Tolerance [Managing Product Delivery]

30
Q

What does the PB need to check at the end of each stage/ Stage Boundary within a Prince2 project?

A

Continued Business Justification

31
Q

What is the role called who is ultimately responsible for representing the high-level customer view?

A
  • Super Product Owner
  • Senior Product Owner
  • Product Manager
32
Q

What are the main differences between Customer Representatives and Customer Subject Matter Experts?

A
  • A Customer Representative’s involvement is significantly less than a CSME, not part of a one particular team and may want to contribute both at high-level and detailed-level.
  • A CSME is assigned to a particular team, more involvement than CR. Can be part-time or full-time
33
Q

In terms of availability, what is the main difference between CSME & SSME?

A

SSMEs tend to be only full-time, unlike CSMEs