1
Q

In Prince2 what are the 3 types of management product?

A

• Baseline
• Record
• Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In Prince2 list the Baseline Management Products

A

• Benefits Management Approach
• Business Case
• Change Control Approach
• Communication Management Approach
• Plan (Project, Stage & Team)
• Product Description
• Project Brief
• Product Initiation Documentation
• Project Product Description
• Quality Management Approach
• Risk Management Approach
• Work Package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In Prince2Agile list the Management Record Products to be tailored.

A

• Configuration Item Record
• Daily Log
• Issue Register
• Lessons Log
• Quality Register
• Risk Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In Prince2Agile list the Management Report Products to be tailored.

A

• Checkpoint Report
• End Project Report
• End Stage Report
• Exception Report
• Highlight Report
• Issue Report
• Lessons Report
• Project Status Account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is the baseline management product “Benefits Management Approach” tailored for P2Agile,?

A

• Emphasis on how frequent release planning enables benefits
- May lead to early customer benefits
- Impact on on-going project viability
- Many benefits may be planned to be in effect before end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is the baseline management product “Business Case” tailored for P2Agile,?

A

• Expressed in a way to allow Flexing on amount of deliverables
• MVP identified to allow raising of an exception if forecasted to be delivered late

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is the baseline management product “Change Control Approach” tailored for P2Agile,?

A

• Nature of Agile means many versions of products created
- Therefore needs to embraced and supported
- Use of frequent releases and associated tools defined

• Consider project/management changes may affect baseline. But detailed changes may not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is the baseline management product “Communication Management Approach” tailored for P2Agile,?

A

• Vital that Agile methods understood
(Informal interactions, daily stand-ups, prototyping, workshops etc)
• Appicable to all project levels
• Define approaches like how a sprint review takes place, and delivery team/PM communication via checkpoint reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is the baseline management product “Plan” tailored for P2Agile,?

A

• Agile plans more informal/low tech
• Although more formality higher up in project levels of planning
• Possibly a creation of release plans
• Agile plans likely to show product features in order, their order, their dependencies for delivery team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is the baseline management product “Product Description” tailored for P2Agile,?

A

• Used interchangeably with User Stories/EPICs.
- Although Prod Des may contain more info.
• Can be product backlog items
- Describing who/what/why?
• Format could be an index card/document

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is the baseline management product “Project Brief” tailored for P2Agile,?

A
  • Informal format
  • Project definition is more outcome- based than solution-based
  • Outline areas of scope and quality criteria that have flexibility for prioritisation
  • Describe use of Agile and its benefit
  • Detail Agile delivery roles
  • Impact on incremental delivery on operations and maintenance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How is the baseline management product “Product Initiation Document” tailored for P2Agile,?

A
  • Should be created with the view of “ enough and no more”. Concise and at appropriate level of detail
  • May exist on an information radiator
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How is the baseline management product “Project Product Description” be tailored for P2Agile,?

A
  • Focus on defining the Product with a close link to a desired outcome
  • As part of a workshop
  • Purpose clearly visible to all
  • Defines ultimate output and outcome
  • The composition will contain highest level of Product descriptions and respective priorities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is the baseline management product “Quality Management Approach” tailored for P2Agile,?

A
  • Agile needs to be incorporated into the strategy to ensure quality
  • De-scoping is not a reduction in quality
  • The quality may start out to be low due to the work uncertainty
    • Early adopters would be the intended audience more interested in utlilizing the product than deficiencies.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is the baseline management product “Risk Management Approach” tailored for P2Agile,?

A

-An Agile risk assessment is used. Emphasis on Agile behaviour risks
- Everyone looks out for risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is the baseline management product “Work Package” tailored for P2Agile,?

A
  • Interface carried out in an collaborative way
  • Negotiated between the PM, TM and possibly the delivery team as well
  • 1+ maybe collaboratively defined as the output from a sprint planning meeting
  • CSME may help with prioritising
  • May include 1+ releases & sprints
17
Q

How is the Record management product “Configuration Item Record” tailored for P2Agile,?

A
  • Cater for high levels of change as common with Agile
  • Operational stakeholders may want to be involved
18
Q

How is the Record management product “Daily Log” tailored for P2Agile,?

A
  • PM to use this to store information especially informal communications (face-to-face)
19
Q

How is the Record management product “Issue Register” tailored for P2Agile,?

A
  • May be informal/low tech
20
Q

How is the Record management product “Lessons Log” tailored for P2Agile,?

A
  • As continual improvement is important to Agile, this may be displayed in a very visible way
  • Can be used to create quick working agreements
  • Can be used in a retrospective
21
Q

How is the Record management product “Quality Register” tailored for P2Agile,?

A
  • Maybe more low tech
22
Q

How is the Record management product “Risk Register” tailored for P2Agile,?

A
  • Maybe more informal/low tech
  • Include risks identified during the Agile Risk Assessment
23
Q

How is the Report management product “Checkpoint Report” tailored for P2Agile,?

A
  • Typically in the form of an information radiator and/or burn chart
  • Could be replaced by a daily stand-up/scrum meeting with agreement of delivery team
    > However it must be avoided to be seen as a “reporting” mechanism
  • If info is transparent, it can be pulled” by the PM when needed
24
Q

How is the Report management product “End Project Report” tailored for P2Agile .
.

A
  • Agile useage assessment included (referencing Agilometer)
25
Q

How is the Report management product “End Stage Report” tailored for P2Agile . .

A
  • Could be built incrementally throughout a stage depending on frequency of timeboxes/releases
  • May be part of a release review
26
Q

How is the Report management product “Exception Report” tailored for P2Agile

A
  • Most likely to occur when the expected amount to be delivered exceeds tolerances
  • Could be triggered by a burn chart showing how progress has gone outside tolerance
  • May further result in a meeting where options are discussed before raising it with PB
27
Q

How is the Report management product “Highlight Report” tailored for P2Agile?

A
  • May contain additional information about releases (what’s been released and benefits enabled)
  • Could be delivered verbally
  • Could be in the form of an information radiator and/or burn chart
    >if info is transparent, it can be “pulled” by the PB
28
Q

How is the Report management product “Issue Report” tailored for P2Agile?

A
  • More low tech
  • Produced/updated during a sprint/release review
29
Q

How is the Report management product “Lessons Report” tailored for P2Agile?

A
  • Maybe low tech
  • Handed to Project Support informally
30
Q

How is the Report management product “Product Status Account” tailored for P2Agile

A
  • Cater for high levels of change to iterative development/delivery