Understand schedule and resource optimisation Flashcards
what 3 items are required to create a project schedule
- WBS
- effort estimate for each task
- resource list and availability
what are the 7 steps of the schedule development process
- identify the tasks from the WBS
- estimate the duration of each task
- determine the dependencies between tasks
- optimise the schedule and test the logic
- assign resources
- check defined schedule meets success criteria for cost and time
- baseline the schedule and monitor during deployment
what are the 2 types of scheduling technique
- critical path - emphasis on activities - shortest time to complete all activities in a logical order
- critical chain - emphasis on the resources (labour/non-labour)
what are the attributes of critical path
- It is the longest duration through the network.
- It is the shortest time the network can take.
- It is the path of zero total float
- Focuses attention on activities, which if delayed, will affect project duration
- Used to allocate resources and analyse risk (higher impact on CP activities)
- Helps align key milestones
what are the attributes of critical chain
- Focused on resources
- attempts to keep resources at constant utilisation
- uses best case duration estimates
- work completed asap and float becomes the buffer for whole project
- aim for maximum productivity of resources
what is the difference in reporting between critical path and critical chain
critical path - start and finish of activities the focus for reporting
critical chain - rate at which buffer is consumed is reported
what are the main types of resource
Replenishable - raw materials, money - once used no longer available
Re-usable - people, machinery, facilities - still available after tasks completed
when is a Gantt hart created
once the network is understood and critical path identified.
what are key attributes of a Gantt chart
- The bar length indicates duration
- Tasks are positioned at earliest start/finish dates, showing any float at the end
- You choose whether to include logic connections
- It can be rolled up into summary tasks and also show key milestones
- The critical path is often shown in red
- It can show comparison of the current plan to the original plan (baseline)
- It is typically generated using planning software
how are resources allocated in a linear life cycle
In Linear lifecycle resources are allocated per phase or the total project
how are resources allocated in an iterative life cycle
In iterative lifecycle ensure requirements are prioritised/implemented within pre-allocated resources.
Scope and quality will vary within the timeboxed sprint
what is Resource-limited Scheduling – Levelling
- scheduling the activities so that a defined resource limit isn’t exceeded.
- Resources are limited (specialists, limited accommodation)
- Levelling may ultimately delay the project to keep within the resource limits.
what is Time-limited Scheduling – Smoothing
- Smoothing is used when the end date is fixed and resources are to be expended to meet that end date. - - Activities are rescheduled within their available total float to achieve a profile which is as smooth as possible.
how can resource levelling be achieved
- redefine activities to be done by the particular resource
- redefine the specification
- increase task duration
- increase resources on earlier tasks
- move activities not on critical path
how can resource smoothing be achieved
- adding resources to reduce duration
- trying to get smooth usage of resources avoiding peaks and troughs