Understand schedule and resource optimisation Flashcards

1
Q

what 3 items are required to create a project schedule

A
  • WBS
  • effort estimate for each task
  • resource list and availability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what are the 7 steps of the schedule development process

A
  1. identify the tasks from the WBS
  2. estimate the duration of each task
  3. determine the dependencies between tasks
  4. optimise the schedule and test the logic
  5. assign resources
  6. check defined schedule meets success criteria for cost and time
  7. baseline the schedule and monitor during deployment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what are the 2 types of scheduling technique

A
  • critical path - emphasis on activities - shortest time to complete all activities in a logical order
  • critical chain - emphasis on the resources (labour/non-labour)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what are the attributes of critical path

A
  • It is the longest duration through the network.
  • It is the shortest time the network can take.
  • It is the path of zero total float
  • Focuses attention on activities, which if delayed, will affect project duration
  • Used to allocate resources and analyse risk (higher impact on CP activities)
  • Helps align key milestones
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what are the attributes of critical chain

A
  • Focused on resources
  • attempts to keep resources at constant utilisation
  • uses best case duration estimates
  • work completed asap and float becomes the buffer for whole project
  • aim for maximum productivity of resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is the difference in reporting between critical path and critical chain

A

critical path - start and finish of activities the focus for reporting

critical chain - rate at which buffer is consumed is reported

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are the main types of resource

A

Replenishable - raw materials, money - once used no longer available

Re-usable - people, machinery, facilities - still available after tasks completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

when is a Gantt hart created

A

once the network is understood and critical path identified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what are key attributes of a Gantt chart

A
  • The bar length indicates duration
  • Tasks are positioned at earliest start/finish dates, showing any float at the end
  • You choose whether to include logic connections
  • It can be rolled up into summary tasks and also show key milestones
  • The critical path is often shown in red
  • It can show comparison of the current plan to the original plan (baseline)
  • It is typically generated using planning software
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

how are resources allocated in a linear life cycle

A

In Linear lifecycle resources are allocated per phase or the total project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

how are resources allocated in an iterative life cycle

A

In iterative lifecycle ensure requirements are prioritised/implemented within pre-allocated resources.

Scope and quality will vary within the timeboxed sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is Resource-limited Scheduling – Levelling

A
  • scheduling the activities so that a defined resource limit isn’t exceeded.
  • Resources are limited (specialists, limited accommodation)
  • Levelling may ultimately delay the project to keep within the resource limits.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what is Time-limited Scheduling – Smoothing

A
  • Smoothing is used when the end date is fixed and resources are to be expended to meet that end date. - - Activities are rescheduled within their available total float to achieve a profile which is as smooth as possible.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

how can resource levelling be achieved

A
  • redefine activities to be done by the particular resource
  • redefine the specification
  • increase task duration
  • increase resources on earlier tasks
  • move activities not on critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

how can resource smoothing be achieved

A
  • adding resources to reduce duration

- trying to get smooth usage of resources avoiding peaks and troughs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what is cost planning

A

understanding where costs fall in the project schedule to be able to manage resource demand, supplier payments and funding requests

17
Q

what are the 4 main cost categories

A
  • Direct costs - exclusive to the project and include the costs of resources directly involved in delivering and managing the work
  • Indirect costs - Cannot be directly associated with a specific work element and include overheads and other charges that may be shared across multiple activities.
  • Fixed (or non-recurring) costs - Happen once in a project life and contribute a single cost. Examples include the purchase of plant or machinery.
  • Variable (or recurring) costs - Occur periodically as an event in a project and contribute multiple costs with a cumulative effect, and include salaries and materials
18
Q

what is the likely periodicity of funding released in a linear lifecycle

A

linear life cycle funds may only be released at decision gates, when the costs spent to date are understood and costs forecasted for the future are approved through the updated business case.

19
Q

what is the likely periodicity of funding released in an iterative lifecycle

A
  • the release of funds may be more frequent due to the close interaction with the sponsor as work is completed in short intervals.
  • most structured for iterations nearest in time
  • cost planning is fixed and scope will vary to deliver within costs