Udemy 3 Flashcards
Question 1:
You are reviewing your project where PV=5000 & AC=4000 & EV=3000. What is the project situation?
Project should be terminated as no solution to fix it.
Project is going normal and it will be managed and closed normally.
Project is under budget but ahead of schedule.
Project is going slower than planned.
Project should be terminated as no solution to fix it.
Project is going normal and it will be managed and closed normally.
Project is under budget but ahead of schedule.
Correct answerProject is going slower than planned.
Overall explanationEV< AC&PV , SO the Project is Behind Schedule & Over Budget = Project is going slower than planned
Question 2:
A project is contracted on a Cost-Plus-Fixed-Fee (CPFF) basis with a fee of 10 percent of estimated costs. The estimated cost is US$50,000. If the project comes in at US$60,000 with no changes in project scope, what would be the total cost of the contract?
US$55,000
US$75,000
US$65,000.
US$125,000
US$55,000US$75,000Correct answerUS$65,000.
US$125,000Overall explanationFee is calculated as 10% of 50,000 = (10/100)*50,000 = 5,000, So total cost of the contract is 60,000 + 5,000 = US$65,000.
Question 3:
In your project, SPI is 0.8, CPI 1.2. You analyzed the baseline and decided to return the schedule back to meet customer plan. You will:
Check with team task can be automated and save time
Check option of crashing the project
Check with your sponsor
Check tasks which can be removed from baseline
Check with team task can be automated and save time
Correct answer Check option of crashing the project
Check with your sponsor
Check tasks which can be removed from baseline
Overall explanationSince the CPI is over one and SPI is less than one, it means that the project is currently not over budget, but is behind schedule.so you need to Check option of crashing the project.
Question 4:
You are working on a project with 10 stakeholders. The number of communication channels on this project is:
55
40
61
65
Correct answer55406165Overall explanationN(N-1)/2, You + 10 stakeholders = 11 so 11*10/2 = 55 , This equation is not available anymore in BMBOK Guide 6, but still you may find a question in the real exam based on it.
Question 5:
You are a Project manager in construction Project. If an pessimistic estimate (P) = $12, optimistic estimate for an activity (O) = $8, Most likely (M) =$10. What is the Cost estimate activity?
$ 9.5
$ 9
$ 11
$ 10
$ 9.5$ 9$ 11Correct answer$ 10Overall explanationP+4M+O/6 12+4*10+8/6 =10
Question 6:
The CV= -$2000 and the SV=$1300. How is your project doing?
Behind schedule, under budget
Ahead of schedule, over budget
Behind schedule, over budget
Ahead of schedule, under budget
Behind schedule, under budget
Correct answerAhead of schedule, over budget
Behind schedule, over budget
Ahead of schedule, under budget
Question 7:
As part of earned value management (EVM), The budget at completion for the project is $10,000 and the estimate at completion is $12,000. What is the CPI that he will get?
Zero
Equal 1
CPI less than 1.2
CPI more than 1.2
ZeroEqual 1
Correct answerCPI less than 1.2CPI more than 1.2
Overall explanationEAC= BAC/CPI, CPI=10,000/12,000=0.83 , So the CPI Less than 1.2
Question 8:
A project consists of 5 activities, A, B, C, D and E. B & C can’t start until A has finished, D can’t start until C has finished, and E can’t start until B and D have finished. The duration of A is 5, B is 8, C is 10, D is 19 and E is 15. How many days can activity B be delayed, without delaying the whole project?
21
29
37
35
Correct answer21293735Overall explanation
Question 9:
A project team had planned to accomplish $25,000 worth of work to date. It has spent $23,000 to date, and accomplished $20,000 worth of work. Which of the following statements is true about the project?
The project is $5,000 under budget
The project is $5,000 Over budget
The project is $3,000 Over budget
The project is $2,000 under budget
The project is $5,000 under budget The project is $5,000 Over budget Correct answerThe project is $3,000 Over budget
The project is $2,000 under budget
Overall explanationEV=$20,000 AC=$23,000 CV= EV-AC = -3,000
Question 10:
As part of earned value management (EVM), a project manager is calculating the to- complete performance index (TCPI) based on EAC. The data he has is as follows: The budget at completion for the project is $100,000. The earned value for the project is $25,000. The actual costs to date are $40,000, and the estimate at completion is $115,000. What is the TCPI that he will get?
0
1.1
1
0.9
01.1Correct answer10.9Overall explanationBAC-EV/EAC-AC, 100,000-25,000/115,000-40,000 = 1
Question 11:
Based on the following diagram, what is the total duration of the project?
15
17
22
21
15Correct answer172221Overall explanationPath1) A-B-C-F-H= 14 Days, Path2) A-D-E-F-H= 16 Days, Path3) A-D-E-G-H= 17 Days
Question 12:
As a result of a brainstorming session, your team determines that the most likely Duration of an activity will be 8 days, the optimistic duration is 6 days, and the pessimistic duration is 16 days. What it the expected activity duration by Triangular distribution?
12 days
9 days
11 days
10 days
12 days9 days11 daysCorrect answer10 days
Overall explanationP+M+O/3 = 16+8+6/3 = 10 Days
Question 13:
For the week of July 15, you will report to management that your project has an EV of $7700 and a PV of $9600. What is the status of your project?
Ahead of schedule
Behind schedule
On schedule
Not enough information provided
Ahead of schedule
Correct answerBehind scheduleOn schedule
Not enough information provided
Overall explanationEV
Question 14:
You are working on a project to set up a call centre for your client. The duration of the project is two years. One year has passed, however, only 40% of the work has been completed against the schedule, which says that by now 50% of the work should have been completed. To date, you have spent 60% of the budget. What is the cost performance index of the project?
0.8
0.67
1.5
1.25
0.8Correct answer0.671.51.25Overall explanationIn the question, you have not been provided with the budget, therefore, let us assume that the project budget is “x”. Earned Value = 40% of the budget = 0.4x, Actual Cost = 60% of the budget = 0.6x, We know that the cost performance index = (Earned Value) / (Actual Cost) = 0.4x / 0.6x = 0.67
Question 15:
Your vice president asked you what the Estimate at Completion (EAC) will be for a small project you are working on. You were given a budget of $30,000, and to date you have spent $20,000 but only completed $10,000 worth of work. You are sure the future work will be accomplished at the planned rate. What is the EAC?
$60,000
$10,000
$30,000
$40,000
$60,000 $10,000 $30,000
Correct answer$40,000Overall explanationEAC=AC+BAC-EV =20,000+30,000-10,000 =40,000
Question 16:
You are starting with your team to map the schedule required for each task. You analyzed few tasks where: Task A had 5 days to complete, Task B had 3 days and follow task A Tack C had 2 days and follow task B, Task D had 4 days and follow tasks (A & B), Task E had 3 days and follow tasks (C & D), While having all tasks as FS relation you counted the float for task D which was:
1 Day
0 Days
3 Days
2 Days
1 Day
Correct answer0 Days
3 Days
2 Days
Overall explanationThe float of activity D is Zero, since this activity is on the Critical Path is : A - B - D - E
Question 1:
Halfway through the current iteration, the progress report reveals that the agile project is off track. The project manager didn’t expect that since he carefully sequenced and assigned all project work to meet the iteration goal. What should the project manager have done differently to avoid this issue?
Train the team on how to implement the agile approach
Encourage the team to record their progress using the reporting system
Set up a contingency reserve
Encourage the team to self-organize to ensure their buy-in
Train the team on how to implement the agile approachEncourage the team to record their progress using the reporting system Set up a contingency reserveCorrect answerEncourage the team to self-organize to ensure their buy-inOverall explanationSince he’s leading an agile project, the project manager should have empowered his team to be self-organized through handling iteration tasks selection and prioritization, rather than solely taking care of work sequencing and assignment. This ensures a high level of buy-in from the team. Encouraging the team to self-organize typically results in a highly motivated staff since it allows them to gain the autonomy to choose the most efficient way to accomplish their work (PMBOK 7th edition, page 249).
Question 2:
During a meeting with the sponsor, the project manager gets feedback on the latest prototype and commits to creating a revised version accordingly within three weeks. Which of the following development approaches is the project manager using?
Predictive
Incremental
Agile
Iterative
PredictiveIncrementalAgileCorrect answerIterativeOverall explanationThe iterative approach uses successive prototypes or Proofs of Concept (PoC). Activities are repeated in cycles to produce more information and ideas to improve the product. In this scenario, the project involves a single delivery rather than a series of smaller deliveries. For this reason, incremental and agile development approaches should be eliminated (Agile Practice Guide, page 18).
Question 3:
A PMO is shifting from a predictive to an adaptive approach for delivering the organization’s projects. For this purpose, concerned employees are undergoing agile training. During one of the training sessions, a participant wonders how many people a project team should include. What is the appropriate answer to the participant’s question?
1 to 5
3 to 9
10 to 15
There is no standard number
1 to 5Correct answer3 to 910 to 15There is no standard numberOverall explanationIt’s recommended that an agile team should include 3 to 9 members. Since the level of communication deteriorates as the team size increases, Agile organizations favor smaller teams. For instance, it’s better to have two teams of five people than one team of ten.
Question 4:
No matter what type of project they are managing or what type of challenges they might face, an agile project manager should make sure that the cross-functional team is always focused on:
Delivering frequently
Planning accurately
Improving quality
Delivering value
Delivering frequentlyPlanning accuratelyImproving qualityCorrect answerDelivering valueOverall explanationDelivering value should always be the agile team’s top priority as it represents one of the agile manifesto principles: “working software over comprehensive documentation”. From the client’s perspective, value represents the benefit derived from using a product or a service.
Question 5:
An organization hires an external agile coach as part of its transformation project. In their final report, the agile coach mentions that measures should be taken to enable agile teams to be cross-functional. What does a cross-functional team mean?
Individuals who collectively determine the best way to accomplish the goal of the sprint
Individuals who take part in guiding the product direction
Individuals who possess the necessary skills to produce a functioning product
Individuals who are in charge of authorizing and releasing work assignments
Individuals who collectively determine the best way to accomplish the goal of the sprintIndividuals who take part in guiding the product directionCorrect answerIndividuals who possess the necessary skills to produce a functioning productIndividuals who are in charge of authorizing and releasing work assignmentsOverall explanationA cross-functional team must possess the necessary competencies for creating a product or a service independently, without relying on other members outside of the team. On the other hand, a self-organizing team is when individuals collectively determine the best way to accomplish the sprint goal.
Question 6:
A project manager is leading an Agile project where the team works in a continuous flow rather than using iterations. This approach proved to be less prescriptive and disruptive to the team. Which Agile framework is the project manager using?
Scrum
Adaptive
Incremental
Kanban
ScrumAdaptiveIncrementalCorrect answerKanbanOverall explanationThe Kanban method involves pulling work into the system only when the team is capable of handling it. The Kanban method prioritizes productivity and efficiency through its workflow approach. Unlike the Scrum team, a Kanban team does not have predefined roles.
Question 7:
A project manager is in the stage of selecting a development approach for a new project. Which of the following reasons will encourage the project manager to choose an adaptive approach over a predictive one?
Change requests go through the organization’s change control process
Change requests are used for frequent planning
Change requests are automatically approved
Change requests are implemented as soon as they have been received
Change requests go through the organization’s change control processCorrect answerChange requests are used for frequent planningChange requests are automatically approvedChange requests are implemented as soon as they have been receivedOverall explanationUnlike the predictive approach which requires change requests to go through the organization’s change control process, the adaptive approach welcomes changes and uses them for frequent planning. During each iteration, the team focuses on producing a subset of the product’s features, while continuously refining and reprioritizing the product backlog items to meet new or modified requirements. This means that change requests are not automatically approved; instead, they are discussed with the product owner first, and then they get prioritized in subsequent iterations as per their recommendations.
Question 8:
For their new outdoor fitness park project, the project manager uses an approach that yields frequent smaller deliverables throughout the span of the project. What type of project development approach are they using?
Predictive
Incremental
Iterative
Agile
PredictiveCorrect answerIncrementalIterativeAgileOverall explanationThe incremental approach focuses on the speed of delivery, i.e., fast delivery. In this type of development approach, the project is divided into increments which are successively delivered to avoid waiting for everything to be completed in order to create a solution (PMBOK 7th edition, page 241). In this scenario, the project manager didn’t ask for feedback to adjust deliverables. Hence, the iterative approach can’t be the correct answer. Since Agile = incremental + iterative, then Agile can’t be the right answer either.
Question 9:
By the end of the third iteration, a project manager delivered the website to the customer and signed a maintenance contract to fix any issues that might occur. On the first day of the maintenance contract period, the customer reported an error on the contact page when using a smartphone. After verifying the issue with the project team, the project manager realizes that testing the contact feature on mobile was omitted. What is this defect called?
Primary defect
Escaped defect
Secondary defect
Undetected defect
Primary defectCorrect answerEscaped defectSecondary defectUndetected defectOverall explanationAs the name indicates, an escaped defect is one that was not detected by the project team but rather discovered by the customer or end-user after the product is released. All of the other options are made-up terms.
Question 10:
The following chart was presented during a retrospective meeting. Which of the following statements is true regarding this chart?
This burnup chart shows that there is work left at the end of the sprint
This burnup chart shows that the planned work is completed before the end of the sprint
This burndown chart shows that there is work left at the end of the sprint
This burndown chart shows that the planned work is completed before the end of the sprint
This burnup chart shows that there is work left at the end of the sprintThis burnup chart shows that the planned work is completed before the end of the sprintCorrect answerThis burndown chart shows that there is work left at the end of the sprintThis burndown chart shows that the planned work is completed before the end of the sprintOverall explanationThis chart is a burndown chart that shows that there is work left at the end of the sprint (PMBOK 7th edition, page 108). In fact, 3 story points are left to be completed in order to finalize all the planned work for the exhibited 7-day sprint.
Question 11:
A scrum master works on a project for a pet training mobile app. During the last retrospective meeting, several topics were evoked. Which of the following topics can be discussed in such a meeting?
The feature of tracking a pet’s activities
Which tasks should be prioritized in the next sprint
How to fix the regression of the chat feature
Whether the standup timing is suitable for all team members
The feature of tracking a pet’s activitiesWhich tasks should be prioritized in the next sprintHow to fix the regression of the chat featureCorrect answerWhether the standup timing is suitable for all team membersOverall explanationDuring the sprint retrospective, the scrum master should identify what went well during the sprint and what can be done differently in the next sprint. A possible topic is the timing of the standup. If team members are showing dissatisfaction with the current schedule, then the retrospective meeting is the right event to discuss the issue. Backlog refinement meetings should address topics like the feature of tracking a pet’s activities or how to fix the regression of the chat feature. On the other hand, the sprint planning meeting is the right meeting for discussing which tasks should be prioritized in the next sprint.
Question 12:
This is the first time the project manager adopts the scrum framework for the project execution. One of the team members asks the project manager when a Sprint is considered completed. What should be the project manager’s response?
When all product backlog items are completed
When all the tasks in the sprint are completed
When the sprint’s defined timebox ends
When all product backlog items meet the Definition of Done (DoD)
When all product backlog items are completedWhen all the tasks in the sprint are completedCorrect answerWhen the sprint’s defined timebox endsWhen all product backlog items meet the Definition of Done (DoD)Overall explanationA sprint is considered complete only when it reaches the end of its duration/timebox, which is usually 1 to 4 weeks. In some cases, the sprint ends without finishing all of the assigned tasks, so this can’t be the criteria for sprint completion.
Question 13:
A project manager is facing some challenges because of a key stakeholder. The project manager collaborated with this stakeholder in previous projects where the latter frequently changed her requirements and created trouble whenever those requirements were not met. How should the project manager deal with this issue?
Adopt an Agile approach
Involve the concerned stakeholder right from the start
Ask the concerned stakeholder to mend her ways
Inform management about the issue
Adopt an Agile approachCorrect answerInvolve the concerned stakeholder right from the startAsk the concerned stakeholder to mend her waysInform management about the issueOverall explanationThe project manager should involve the key stakeholder from the very beginning of the project to help reduce and uncover risks, as well as increase her “buy-in.” While implementing an agile approach may benefit the project, it does not address the issue of stakeholder management. If the question were “what’s the appropriate approach for the project?”, then adopting an agile approach would be the right answer taking into consideration the frequently changing requirements.
Question 14:
A team, with no defined roles, uses a board and cards to categorize tasks into “To do”, “Doing”, and “Done”. Without too many restrictions, team members grab a card from the “To do” list and begin to work. What agile framework is being described?
Scrum
Kanban
Lean
Kaizen
ScrumCorrect answerKanbanLeanKaizenOverall explanationKanban is an agile method that employs a pull-based work system where tasks are assigned only when resources are available. Unlike Scrum, the Kanban team has no formal roles. Additionally, Kanban practice has fewer restrictions than Scrum. Lean is not an agile framework. In contrast, agile and kanban are subsets of lean (Agile Practice Guide, page 11). Kaizen is a quality and resource management philosophy of applying continuous small improvements to increase productivity and reduce costs.
Question 15:
A project manager is leading a rebranding project using a predictive approach for the planning phase and an Agile approach for work execution. The project manager receives an email from a key stakeholder requesting an estimation of the project completion date. In order to estimate the completion date, the project manager takes into consideration the team’s average velocity, which is 20 story points, and the fact that the project still has 205 remaining user story points to complete. How many iterations will it take to finish the project work?
10 iterations
11 iterations
12 iterations
Cannot be determined
10 iterationsCorrect answer11 iterations12 iterationsCannot be determinedOverall explanationIf the team maintains an average velocity of 20 story points per iteration, it would take 11 iterations to complete the remaining 205 story points. (205 story points / 20 story points = 10.25 iterations). Since the timebox of an iteration should not be changed, the project team will need 11 iterations to complete the rest of the work.
Question 16:
A project manager is managing a software development project. In order to ensure that the project’s agile team is cross-functional, the project manager hires an experienced designer. A few days later, the designer informs the project manager that he’s unable to do his work properly because the subscription plan of the design application he’s using doesn’t include all of the functionalities he needs. Therefore, the designer asks for an upgraded subscription plan. What should the project manager do next?
Ask the designer to raise the issue during the next retrospective meeting
Tell the designer to be self-reliant by dealing with the situation and finding turnarounds
Explain to the designer that his current subscription plan is sufficient for fulfilling his assigned tasks
Reach out to the appropriate stakeholder to upgrade the designer’s subscription plan
Ask the designer to raise the issue during the next retrospective meetingTell the designer to be self-reliant by dealing with the situation and finding turnaroundsExplain to the designer that his current subscription plan is sufficient for fulfilling his assigned tasksCorrect answerReach out to the appropriate stakeholder to upgrade the designer’s subscription planOverall explanationAs a servant leader, the project manager should reach out to the appropriate stakeholder in order to upgrade the designer’s subscription plan. In an agile work environment, the project manager should listen to the impediments faced by their team members and act to solve them. If the designer’s subscription plan cannot be upgraded, then the project manager should explain this, asking the designer to try finding turnarounds, such as using other complementary applications that offer the functionalities that he needs to perform his work. Agile teams are self-organized, i.e they decide how they should perform their work. Thus, forcing the designer to use a limited subscription plan is inappropriate. Furthermore, since the designer is experienced, he’s able to clearly identify his needs, therefore the scrum master or the project manager should cater to the designer’s job requirements rather than argue with the latter. Retrospective meetings are set up to improve processes and not to remove impediments.
Question 17:
Using an Agile approach, where should product requirements be documented?
In the requirements log
In the product backlog
In the team charter
In the WBS
In the requirements logCorrect answerIn the product backlogIn the team charterIn the WBSOverall explanationProduct requirements are documented under the backlog as user stories. The backlog user stories are then continuously prioritized and refined. The WBS is only used in the predictive approach.
Question 18:
At a trade show, a prospect stops at the stand of a company that specializes in selling and installing network security appliances. The prospect asks the representative if their company can provide and set up 10 firewall hardware devices in 5 weeks, recommending an incremental approach to deliver 2 firewalls per week. The prospect adds that an external security expert will be conducting a penetration test, and that final acceptance will be granted only after all performed cyber attacks are detected and prevented. What is the prospect defining in the above scenario? (Select two)
Definition of Done
Quality Assurance
Technical Requirements
Quality Control
Correct selectionDefinition of DoneQuality AssuranceTechnical RequirementsCorrect selectionQuality ControlOverall explanationA Definition of Done (DoD) is a checklist of the required criteria for considering a product ready for delivery (PMBOK 7th edition, page 81). The prospect is also describing the quality control process that will be focusing on defect identification. Quality assurance, on the other hand, focuses on defect prevention. Technical requirements cover the product requirements, such as WiFi support, storage, number of LANs, etc.
Question 19:
To guide the development team on what they intend to achieve, a product owner of an HR solution shares the following table depicting the key deliverables of each quarter of the 9-month project. What agile artifact does this table represent?
Product vision statement
Product wireframe
Product roadmap
Product backlog
Product vision statementProduct wireframeCorrect answerProduct roadmapProduct backlogOverall explanationThe product roadmap is built by the product owner to demonstrate the anticipated sequence of deliverables over the project duration (Agile Practice Guide, page 52). As an Agile artifact, the product roadmap sets the product’s strategic view, indicating where the product is headed in both the short and long terms. In agile organizations, the product roadmap serves as a guide rather than a project plan. The product roadmap is different from the product backlog in that the product roadmap provides the big picture while the product backlog tackles the practical and feasible steps required to tangibly create the product. The Product wireframe is a mockup or a sketch of the user interface, high-level functionality, page layout, etc. A product vision statement outlines what a product would look like to ultimately achieve its vision and give purpose to its existence. A vision statement should be short, simple, and specific.
Question 20:
An experienced scrum master is often asked “How long should a sprint be?” to which they always respond by saying “It depends, you should initially find a balance that works for the team, but typically an agile scrum sprint is ____________ long.”
3-5 days
1 week
2-4 weeks
5-8 weeks
3-5 days1 weekCorrect answer2-4 weeks5-8 weeksOverall explanationA Sprint has to be long enough for the team to finish all included stories. As per a Scrum rule, a Sprint should never exceed one month. The duration of a sprint depends on the project size and complexity as well as the team’s capacities. It takes 2 to 4 weeks on average to complete a sprint with a team of 3-9 members working on a single project.
Question 21:
A project manager is leading a project of gaming equipment development. The project team holds a monthly status review meeting with the product owner to review post-iteration deliverables. What’s the best communication type to use in a status review meeting?
Push
Pull
Interactive
Formal
PushPullCorrect answerInteractiveFormalOverall explanationWhen an immediate response is required and the information you’re communicating is sensitive and could be misinterpreted, you should use interactive communication. It involves one or more people sharing thoughts and ideas, with participants responding in real time. Interactive communication can take place through teleconferences or face-to-face contact. When using communication media such as emails, the project manager can’t pick up on stakeholders’ facial expressions and body language.
Question 22:
During the standup meeting, a team member invokes an impediment they’re facing. In order to address this impediment, the project manager suggests that two other members sit with the team member facing the issue and collaborate to find the appropriate solution. What technique is the project manager suggesting? (Select two)
Pairing
Swarming
Mobbing
Brainstorming
PairingCorrect selectionSwarmingCorrect selectionMobbingBrainstormingOverall explanationSwarming and mobbing imply that multiple team members or the entire team focus collectively on resolving a specific impediment. Although pairing, swarming, and mobbing all represent collaboration techniques used by the Agile team (Agile Practice Guide, page 39), the situation doesn’t describe pairing since this technique requires only two team members to work together to resolve an issue. Brainstorming, on the other hand, is used to generate ideas, rather than to resolve issues.
Question 23:
All of the following are either Agile or Lean frameworks except:
Scrumban
eXtreme Programming
Waterfall
Crystal Methods
ScrumbaneXtreme ProgrammingCorrect answerWaterfallCrystal MethodsOverall explanationWaterfall is a predictive methodology that was deemed too rigid to handle the changing requirements brought on by new technology or a demanding client. Even though there are numerous Agile and Lean frameworks, the Agile Practice Guide only addresses Scrum, Kanban Method, Scrumban, eXtreme Programming (XP), Crystal Methods, Dynamic Systems Development Method (DSDM), Feature-Driven Development (FDD), and Agile Unified Process.
Question 24:
The Agile scrum framework simplifies the project management process by decomposing it into cycles, aka Sprints. With the increase of the Agile approach adoption, more terminologies, tools, and techniques are introduced and used. For instance, the term “Zero Sprint” refers to:
The preparation step for the first sprint
The first sprint of a project
A sprint that doesn’t have any user stories
A sprint where none of the tasks is completed
Correct answerThe preparation step for the first sprintThe first sprint of a projectA sprint that doesn’t have any user storiesA sprint where none of the tasks is completedOverall explanationThe term “Zero sprint” refers to a step in the process of preparing the initial sprint. Before initiating a project, various activities must be completed, which are all referred to as the Zero sprint. Doing preliminary research, deciding on technical choices, and preparing for backlogs are all examples of activities performed prior to project launch. Mike Cohn illustrated the usage of Sprint 0 in his book “Succeeding with Agile Software Development Using Scrum” (Page 152).
Question 25:
A project manager got assigned to lead a new project. Wondering about the project completion date, the product owner asks the project manager: “How many story points do you expect to complete per sprint?”. In order to provide the product owner with an accurate response, the project manager should:
Estimate the sprint velocity based on the team members’ input
Complete multiple sprints in order to be able to answer the product owner’s question
Rely on their own judgment as an experienced project manager to estimate the team velocity
Engage the team in estimating their velocity based on their previous agile projects
Estimate the sprint velocity based on the team members’ inputComplete multiple sprints in order to be able to answer the product owner’s questionRely on their own judgment as an experienced project manager to estimate the team velocityCorrect answerEngage the team in estimating their velocity based on their previous agile projectsOverall explanationTypically, the project manager should rely on the available historical data of their team velocity in order to set a reasonable and achievable number of story points per sprint, depending entirely on your team’s capacities and how much they can accomplish. When a new team has no historical data, the sprint forecast can be done based on your experience with similar projects along with collaborative estimations from the entire team, to determine how many story points they can potentially deliver in the first sprint.
Question 26:
Throughout his long career, a project manager has always followed a servant leadership style, particularly with agile teams. What does servant leadership imply?
One individual in charge of directing and guiding the team
Carrying out work through iterations, with one prominent leader
Naming a team leader, while team members serve as followers
Understanding and addressing the needs of team members
One individual in charge of directing and guiding the teamCarrying out work through iterations, with one prominent leaderNaming a team leader, while team members serve as followersCorrect answerUnderstanding and addressing the needs of team membersOverall explanationAccording to the Agile Practice Guide, servant leadership implies leading your team by focusing on understanding and addressing their needs to yield the best performance possible (PMBOK 7th edition, page 17).
Question 27:
In order to handle high levels of change and ensure the active participation of all interested parties, a project manager adopts a change-driven project development approach, which is also known as:
Adaptive approach
Predictive approach
Waterfall approach
Hybrid approach
Correct answerAdaptive approachPredictive approachWaterfall approachHybrid approachOverall explanationA change-driven approach is also referred to as an adaptive, Agile, flexible, or change-focused approach. This development approach is characterized by the ability to react and adapt to high levels of change as well as the constant involvement and participation of different parties. On the other hand, a waterfall or predictive approach is sequential and rigid. Hybrid is a combination of predictive and adaptive approaches.
Question 28:
In projects following the Scrum framework, which of the following questions won’t be asked to team members during daily stand-ups?
What have you completed since the last stand-up?
What will you complete until the next stand-up?
What do we need to finish as a team?
Are there any impediments?
What have you completed since the last stand-up?What will you complete until the next stand-up?Correct answerWhat do we need to finish as a team?Are there any impediments?Overall explanationIn contrast with flow-based Agile which focuses on the team’s throughput, iteration-based Agile focuses on accountability through three standard questions: - What was completed yesterday? - What will be completed today? - Are there any blockers or impediments?
Question 29:
A project manager realized that her team’s velocity is fluctuating when she reviewed their burn-up chart. While searching for the root cause, the project manager notices that a certain team member has a very slow performance compared to the other members, which is negatively impacting the whole team’s performance. How should the project manager address this issue?
Plan training sessions for the concerned team member
Acquire a more competent resource
Mentor the concerned team member
Reassign the concerned team member to another project
Plan training sessions for the concerned team memberAcquire a more competent resourceCorrect answerMentor the concerned team memberReassign the concerned team member to another projectOverall explanationWhen a team member’s performance is negatively impacting the overall progress of the project, the project manager should immediately interfere. Since training the team member would take time, mentoring them would be a more suitable option for this urgent issue. Mentoring can help the team member enhance their performance. It’s among the project manager’s responsibilities to serve as a guide in identifying and assisting her team members with their learning needs to ensure better productivity and performance (PMBOK 7th edition, page 18). By offering enough support and attention, the team member will respond positively by working harder, which will naturally result in better performance. A mentor should however continue to observe the team member’s performance and provide feedback to help them refine and improve their work.
Question 30:
An agile team is working on the project of an e-commerce website. After a slow start and a lot of disputes, team members are starting to get along and support each other’s needs. In which area of the Tuckman ladder does this team currently exist?
Area A
Area B
Area C
Area D
Area A Area BCorrect answerArea CArea DOverall explanationGetting over the storming stage (area B) means that the team has managed to resolve their conflicts and that a sense of unity is starting to shape. During the norming phase (area C), a sense of cohesion and unity emerges, a common consensus is developed, and personal differences start to diminish. Team performance is improved at this point as members get more goal-oriented (PMBOK 7th edition, page 166). However, if disagreements resurface, the team can slide back into the storming phase. Please note that on the real PMP exam you may be asked to answer this type of question by clicking on the correct area in the image.
Question 31:
In an Agile software development project involving the creation of a mobile application for a ride-sharing service, the project manager has implemented a practice where team members take turns facilitating daily stand-up meetings to promote collaboration and ownership. Each team member is assigned a rotating role to facilitate the stand-up meeting for a designated period, typically one week. However, one team member consistently fails to properly facilitate stand-up meetings, acting flustered, failing to engage other team members, and doing most of the talking.
What should the project manager do next?
Assign the responsibility of facilitating stand-up meetings to another more reliable team member.
Provide immediate feedback at the end of each stand-up meeting so all team members can learn from their colleague’s mistakes.
Organize coaching sessions with the team member to discuss the importance of their role in facilitating stand-up meetings and provide guidance on how to improve.
Remove the team member from the project team as their failure to facilitate meetings is hindering progress.
Assign the responsibility of facilitating stand-up meetings to another more reliable team member.Provide immediate feedback at the end of each stand-up meeting so all team members can learn from their colleague’s mistakes.Correct answerOrganize coaching sessions with the team member to discuss the importance of their role in facilitating stand-up meetings and provide guidance on how to improve.Remove the team member from the project team as their failure to facilitate meetings is hindering progress.Overall explanationOrganizing coaching sessions with the team member is the most appropriate course of action. Coaching allows the project manager to provide support, guidance, and feedback to help the team member overcome any hardships they’re having playing the role of a facilitator. Servant leaders should support the team through mentoring, encouragement, and support. Sometimes team members may not have knowledge or experience in roles or functions. Servant leaders who may have more exposure or training in techniques can support the team by providing training (Agile Practice Guide, page 37). The coaching session should focus on identifying any obstacles or challenges the team member is facing and collaboratively developing strategies to overcome them. Assigning the responsibility of facilitating stand-up meetings to another team member does not address the root cause of the problem. It could also lead to resentment among team members and disrupt team dynamics. Providing immediate feedback at the end of each stand-up meeting so all team members can learn from their colleague’s mistakes can create tension and negatively impact the team member’s morale. Removing the team member from the project team is extreme for the described issue and could disrupt project continuity and negatively impact the team.
Question 32:
During the sprint planning meeting, the product owner and the cross-functional team members agreed on which backlog items would be executed in the next sprint. Who commits to delivering a potentially shippable increment by the end of the sprint?
The cross-functional team
The scrum master
The product owner
The entire Scrum team
Correct answerThe cross-functional teamThe scrum masterThe product ownerThe entire Scrum teamOverall explanationWhen the sprint planning is complete, the cross-functional team members acknowledge their commitment to the business value that will be delivered by the end of the sprint. The sprint goal and the sprint backlog embody this commitment (Essential Scrum by Rubin, Kenneth S, page 346). The product owner doesn’t deliver business value by the end of the sprint but rather owns the product backlog; the product owner manages, maintains, and prioritizes the product backlog items. Keep in mind that the Product backlog represents work that needs to be done to create the entire product, while the Sprint backlog is a subset that represents the work that needs to be executed in the current sprint. The scrum master helps in maintaining the scrum processes and intervenes neither in the selection nor the execution of the sprint backlog items.
Question 33:
A project manager has been assigned to an agile project that is already mid-execution. Which of the following should the project manager check to examine the high-level description of the project scope?
Project charter
User stories
Epics
Work breakdown structure
Correct answerProject charterUser storiesEpicsWork breakdown structureOverall explanationThe project manager should refer to the project charter to find the ‘high-level description‘ of the project. The project charter is a formal document that describes the project in its entirety, including its objectives, work processes, and stakeholders. This project planning document can be used throughout the whole project lifecycle (PMBOK 7th edition, page 184). User stories and epics only represent the detailed requirements, not the entire high-level description of the project scope. The Work Breakdown Structure (WBS) also outlines the detailed requirements of projects that follow a predictive approach.
Question 34:
A project manager works in an organization that uses Agile practices. In order to evaluate their project performance, the project manager uses (Select two):
Cost performance index
Value-based measurements
Empirical measurements
Schedule performance index
Cost performance indexCorrect selectionValue-based measurementsCorrect selectionEmpirical measurementsSchedule performance indexOverall explanationAgile favors empirical and value-based measurements instead of predictive measurements (Agile Practice Guide, page 61). Agile teams focus on measuring value and implementing an empirical process in which progress is based on observations of reality, facts, experiences, and evidence. The Agile approach consists of a fixed cost and schedule, hence the project manager can’t use the Cost Performance Index (CPI) & the Schedule Performance Index (SPI) couldn’t be used.
Question 35:
A project manager is leading a web project using an adaptive approach. The project consists of creating an automatic notification system that alerts users when their cloud expenses exceed a predefined threshold. The project manager and the project team are currently preparing and updating user stories for the next iterations. What activity does this depict?
Backlog refinement
Schedule management
Project management
Sprint Review
Correct answerBacklog refinementSchedule managementProject managementSprint ReviewOverall explanationBacklog refinement involves preparing the next iteration’s stories. In order to make sure the backlog contains the right items for the next iteration, the project manager, along with the team, should review and prioritize backlog items, ensuring that top items are ready to be delivered (PMBOK 7th edition, page 235). This activity can take place as a formal planned meeting or as a regular ongoing task.
Question 36:
A project manager is assigned to an organic skincare branding project. After checking the sprint performance, the project manager is not satisfied with the current progress. During a meeting with the team to discuss the matter, the project manager learns that some issues were not accurately estimated due to missing key information during the sprint planning. Knowing that the team uses story points to estimate issues and user stories, how should the project manager address this problem?
Re-estimate all of the sprint’s issues and user stories
Re-estimate the velocity of the sprint
Do nothing and raise the problem in the sprint retrospective
Collaborate with the team to review the remaining issues in the sprint backlog
Re-estimate all of the sprint’s issues and user storiesRe-estimate the velocity of the sprintDo nothing and raise the problem in the sprint retrospectiveCorrect answerCollaborate with the team to review the remaining issues in the sprint backlogOverall explanationA team should ideally prepare all of the sprint issues and user stories before it starts. However, this is not always the case for a number of reasons. Inaccurate estimations of user stories can result in unsatisfying progress and unfinished tasks in the Sprint Backlog. In this case, the project manager should collaborate with the team to review and complete the remaining Sprint issues. The project manager should first identify the issues that the team didn’t finish, document them, and determine the needed effort for completing them. In a second step, the project manager should redefine priorities, re-estimate issues, and reflect on what happened in the sprint retrospective.
Question 37:
The role of the product owner in an Agile project is:
Coordinating the work of the sprint and running the team
Having a vested interest in the project and its outcomes and interfacing with stakeholders
Representing the business unit, customer, or end-user
Completing the backlog items and signing up tasks based on established priorities
Coordinating the work of the sprint and running the teamHaving a vested interest in the project and its outcomes and interfacing with stakeholdersCorrect answerRepresenting the business unit, customer, or end-userCompleting the backlog items and signing up tasks based on established prioritiesOverall explanationThe product owner represents the business unit, customer, or end-user as they’re regarded as the voice of the customer. The Product Owner is responsible for maximizing the value produced by the team and ensuring that the stories meet the user’s needs and comply with the Definition of Done (DoD) (PMBOK 7th edition, page 245). Apart from the project team, the product owner has significant relationships and obligations, including working with upper management, end-users, and other stakeholders.
Question 38:
For their new project, a project manager decided to create a Work Breakdown Structure (WBS), define and sequence all activities, and then execute tasks in month-long cycles. The sponsor can change 30% of the subsequent cycle’s scope of work with no need for a change request. Which of the following approaches is being adopted?
Adaptive
Hybrid
Predictive
Iterative
AdaptiveCorrect answerHybridPredictiveIterativeOverall explanationA hybrid approach incorporates different components from various approaches (PMBOK 7th edition, page 36). In the described scenario, the project manager is combining the characteristics and practices of predictive (planning everything at the beginning of the project), iterative (executing work in cycles), and adaptive approaches (by allowing a 30% change without going through a formal process).
Question 39:
Among the challenges that an organization faces when shifting to Agile, is the need to build teams made of “T-shaped” members. A “T” shaped team member is:
A generalist who is able to tackle any task within the backlog, regardless of the required skills
A person who had freshly started their career and needs coaching by the scrum master
An individual who specializes in a single field and rarely contributes to another field
An individual who supplements their competence in one area with less-developed skills in associated areas and has an aptitude for collaboration
A generalist who is able to tackle any task within the backlog, regardless of the required skillsA person who had freshly started their career and needs coaching by the scrum masterAn individual who specializes in a single field and rarely contributes to another fieldCorrect answerAn individual who supplements their competence in one area with less-developed skills in associated areas and has an aptitude for collaborationOverall explanationA “T” shaped team member typically has encompassing expertise in one field with supporting but less-developed skills in related areas. T-shaped people also have an aptitude for collaboration. “I” shaped people, on the other hand, have a profound specialization in one domain and only seldom participate in work outside of that domain (Agile Practice Guide, Page 42).
Question 40:
A medium-sized IT company that has been using the predictive approach assigns an agile consultant to assist in their transition to the Agile approach. Which of the following aspects should the Agile consultant take into consideration when assisting in this transition?
The organization’s familiarity with the predictive approach
The organization’s culture
The existence of a Scrum master
The organization’s size
The organization’s familiarity with the predictive approachCorrect answerThe organization’s cultureThe existence of a Scrum masterThe organization’s size Overall explanationAn organization’s culture influences the type of project management approaches adopted by project teams. The familiarity with the existing approaches, the size of the organization, and the competency of the team are all factors that contribute to the culture.
Question 41:
A project manager works for a company that is undergoing a reorganization. During a staff meeting, the project manager learns that management has decided to shift technology to use the cloud. The project manager uses an Agile approach to lead their project, and since they know that this shift will have a direct impact on the project, they decide to:
Assess the impact of the shift with the sponsor before moving forward with the change management procedure
Assess the impact of this shift with the team and refine the backlog
Close the project and start over to properly adapt to the new technological transition
Send a formal request to the sponsor asking for an exception from using the cloud
Assess the impact of the shift with the sponsor before moving forward with the change management procedureCorrect answerAssess the impact of this shift with the team and refine the backlogClose the project and start over to properly adapt to the new technological transitionSend a formal request to the sponsor asking for an exception from using the cloudOverall explanationAgile practices provide the ability to quickly adapt to new conditions. In this case, shifting to a new technology imposes assessing and refining the backlog with the team’s assistance.
Question 42:
A project manager uses the scrum framework to manage a graphic design project. Which of the following events will not be used by the project team?
Sprint planning
Weekly scrum
Sprint review
Sprint retrospective
Sprint planningCorrect answerWeekly scrumSprint reviewSprint retrospectiveOverall explanationScrum teams use four main events: sprint planning, daily scrum, sprint review, and sprint retrospective.
Question 43:
A project manager is using the Agile approach to manage a software development project. During a meeting with the team, the project manager presents the _____________ to showcase how much work still needs to be done during the current iteration.
Schedule
Burnup chart
Milestone chart
Burndown chart
ScheduleBurnup chartMilestone chartCorrect answerBurndown chartOverall explanationUnlike the burnup chart which shows the completed work, a burndown chart is a graphical depiction of the work that still needs to be completed (PMBOK 7th edition, pages 108).
Question 44:
Which of the below statements represents the most accurate definition of backlog refinement? (Select three)
The process of creating the initial list of product requirements, formerly known as backlog grooming.
When the product owner or team members review the backlog to make sure it has the proper items
The continuous elaboration of project requirements to satisfy the stakeholders’ needs
The continuous activity of writing, updating, and prioritizing requirements
The process of creating the initial list of product requirements, formerly known as backlog grooming.Correct selectionWhen the product owner or team members review the backlog to make sure it has the proper itemsCorrect selectionThe continuous elaboration of project requirements to satisfy the stakeholders’ needsCorrect selectionThe continuous activity of writing, updating, and prioritizing requirementsOverall explanationBacklog refinement (formerly referred to as backlog grooming) occurs when the product owner along with some, or all of the team members checks the backlog to make sure it contains the proper items, that these items are prioritized, and that the ones at the top are ready to be delivered (PMBOK 7th edition, page 235). This activity is carried out regularly and can be either an officially scheduled meeting or an ongoing activity. The process of developing the initial list of product requirements represents backlog elaboration or creation.
Question 45:
A project manager is leading an internal accounting software development project. During a sprint planning meeting, the project manager tackles a task that involves setting an automatic email as a reminder when an unpaid invoice misses its due date. The Agile team agrees to assign the task a total of 8 Story Points, based on the developers’ estimate of 5 story points and the testers’ estimate of 3 points. Which of the following statements is correct regarding this situation?
The project manager should be the one estimating the task, not the team
The task should be estimated as a whole and not per segment
Story points should never be estimated, they should be calculated
The team should involve relevant stakeholders in the task estimate
The project manager should be the one estimating the task, not the teamCorrect answerThe task should be estimated as a whole and not per segmentStory points should never be estimated, they should be calculatedThe team should involve relevant stakeholders in the task estimateOverall explanationStory points are assigned to each user story to estimate the total effort needed to bring a feature or functionality to life. Thus, they shouldn’t be assigned partially. The team has to carefully consider how much work and effort each story requires in order to ensure that they can deliver the work they’ve committed to.
Question 46:
A project manager is managing a two-year project that involves a high level of uncertainty and unforeseen complexity. The team expects adjustments as the scope of work gradually becomes more clear over time. To manage stakeholder expectations, what should the project manager clear up concerning their choice of using an iterative approach to manage the project?
That work will be subject to short feedback loops with the backlog being reprioritized in each iteration
That work will be developed progressively based on monthly feedback loops
That all tasks will be prioritized up front, and that work will be gradually decomposed
That the team will start executing the backlog work from the bottom up
Correct answerThat work will be subject to short feedback loops with the backlog being reprioritized in each iterationThat work will be developed progressively based on monthly feedback loopsThat all tasks will be prioritized up front, and that work will be gradually decomposedThat the team will start executing the backlog work from the bottom upOverall explanationShort feedback loops and backlog reprioritization are common in projects that use an iterative approach. Frequent delivery and feedback allow the team to prioritize work and respond to changes more efficiently. The duration of the iteration should be determined according to the project’s characteristics. For example, a monthly feedback loop could not be appropriate for a two-month-long project. Weekly or fortnightly feedback would be more convenient in this case.
Question 47:
A project manager needs to choose the suitable project management approach for the project they’re leading. There are a variety of approaches to choose from, each ideally suited for a specific project type. Agile and Scrum are two of the most common and often conflated terms. Given their similarities, they can get confusing sometimes, but they are, in fact, two distinct concepts. What is the primary distinction between Scrum and Agile?
Agile is a set of values and principles, while Scrum only presents a set of values.
Agile is a set of values, principles, and practices, while Scrum only involves a set of values and principles.
Agile is a set of values and principles, while Scrum represents a set of values, principles, and practices.
Agile is a framework, while Scrum is a philosophy.
Agile is a set of values and principles, while Scrum only presents a set of values.Agile is a set of values, principles, and practices, while Scrum only involves a set of values and principles.Correct answerAgile is a set of values and principles, while Scrum represents a set of values, principles, and practices.Agile is a framework, while Scrum is a philosophy.Overall explanationOn the surface, Agile and Scrum look similar as they both rely on an iterative process, frequent client interaction, and collaborative decision-making. The primary distinction between Agile and Scrum is that Agile is a project management philosophy that utilizes a core set of values or principles, while Scrum is a specific Agile practice used to facilitate a project. Although Scrum is an approach within Agile, Agile does not necessarily imply Scrum since Agile encompasses a wide range of approaches. Scrum is based on a small set of core values, principles, and practices (collectively forming the Scrum framework). References: Agile Alliance & Essential Scrum by Rubin, Kenneth S (Preface).
Question 48:
The traditional format of a daily stand-up meeting consists of gathering in a circle near a task board where each member takes their turn to answer a number of questions. Which of the following statements best describes the daily stand-up in agile?
It is a meeting during which the upcoming work schedule is discussed
It is a meeting during which the team is asked about what they did on the previous day and their plan for the current day along with any problems they might have faced during the execution of their tasks
It is a daily brainstorming session
It is a daily lessons-learned session
It is a meeting during which the upcoming work schedule is discussedCorrect answerIt is a meeting during which the team is asked about what they did on the previous day and their plan for the current day along with any problems they might have faced during the execution of their tasksIt is a daily brainstorming sessionIt is a daily lessons-learned sessionOverall explanationThe daily standup is a meeting held by members of the project team. This meeting brings the team together for a status update, to ensure that everyone is on the same page and has insight into what is going on, whether it’s good or bad. Such a meeting usually takes up to 15 minutes during which every team member is asked three questions: What did you do yesterday that helped your team meet the Sprint goal? What will you do today to help your team meet the Sprint goal? And, Did you face any impediments that prevented you or your team from meeting the Sprint goal? (PMBOK 7th edition, page 179)
Question 49:
Agile is not fit for all projects, despite all the advantages it can bring forth. Therefore, it’s important to understand the drawbacks of this approach. Which of the options below represent the disadvantages of the Agile approach? (Select three)
Poor resource planning
Limited documentation
Self-organized teams
Fragmented output
Correct selectionPoor resource planningCorrect selectionLimited documentationSelf-organized teamsCorrect selectionFragmented outputOverall explanationPoor resource planning, limited documentation, and fragmented output are three key downsides of the agile approach. Since Agile is built on the fact that teams don’t know what their final result will look like earlier in the project, it’s difficult to anticipate project costs, time, and resources at the start, and this difficulty becomes more pronounced as projects become larger and more complex. Moreover, in Agile, documentation occurs during the project, and it is often done “just in time”, rather than at the beginning of the project. As a consequence, documentation becomes less informative. Additionally, while incremental delivery can help launch goods faster, it’s often regarded as one of the Agile approach’s major disadvantages: when teams work on each component at different time periods, the end result often becomes fragmented instead of being one coherent deliverable. On the other hand, Agile teams are self-organizing which is proven to contribute to a higher velocity, increased quality, and less need for team management.
Question 50:
The Sprint goals were not met by the Scrum team. A key team member took two days off at the start of the four-week Sprint due to a family emergency. What is the most likely reason for the team’s failure to achieve the Sprint goals?
The project manager didn’t assign a replacement for the OOTO (Out Of The Office) member
The team is inexperienced
The team did not plan the sprint effectively
The team is overworked
The project manager didn’t assign a replacement for the OOTO (Out Of The Office) memberThe team is inexperiencedCorrect answerThe team did not plan the sprint effectivelyThe team is overworkedOverall explanationWhen a team struggles to achieve the sprint goals, it’s mainly due to poor sprint planning. A team that fails to reach its sprint target is a team that can’t properly plan its work, does not have a clear understanding of its own capabilities, or does not have a good sense of how to forecast stories and/or tasks. A team member’s two days off should not be an excuse for missing the sprint goals.
Question 51:
An associate project manager is working for a digital design agency specializing in branding and packaging. In their current project, the project manager uses an approach that implies sharing partially completed work with the client in order to obtain early feedback and modify the product accordingly. The project manager is using a(n)____________ approach.
Incremental
Predictive
Agile
Iterative
IncrementalPredictiveAgileCorrect answerIterativeOverall explanationThe iterative development approach focuses on developing the product through a series of repeated cycles that successively improve or add functionalities to the product by incorporating stakeholders’ feedback. The iterative approach differs from the incremental approach in that change is expected. In fact, change is a necessary part of the iterative approach. (Source: Effective Project Management Traditional, Agile, Extreme, Hybrid by Robert K. Wysocki, page 49). An adaptive or agile approach is also change-driven like the iterative approach. Yet, it requires ongoing stakeholder/client engagement and the use of backlogs (including product requirements and user stories) to reflect their current needs.
Question 52:
A project manager depends on time-boxing to help team members avoid wasting time on shallow work and stay focused on the main deliverables. Which of the following statements best describes time-boxing?
Duration of intense activity within a specific release
A time frame for executing specific activities
Tight planning to reduce the time required for an activity completion
Setting a deadline for product delivery
Duration of intense activity within a specific releaseCorrect answerA time frame for executing specific activitiesTight planning to reduce the time required for an activity completionSetting a deadline for product deliveryOverall explanationA timebox is a fixed period of time in which work has to be completed. The timebox duration could be a few hours, days, or weeks depending on the work complexity or size (PMBOK 7th edition, page 181).
Question 53:
A project manager works for a mobile app development company. One of his latest projects involves the creation of an exercise app that syncs with another nutrition app to combine and analyze the data. As a result of a recent regulatory change, the project team is working on refining the backlog. The process of backlog refinement involves:
The identification of the work items to be accomplished during the next sprint
A board to keep track of the product and sprint backlogs
A prioritized list of product requirements which is maintained by the project team
The gradual development of product specifications to meet the needs of the product owner
The identification of the work items to be accomplished during the next sprintA board to keep track of the product and sprint backlogsA prioritized list of product requirements which is maintained by the project teamCorrect answerThe gradual development of product specifications to meet the needs of the product ownerOverall explanationBacklog refinement refers to the progressive elaboration of project requirements where the Agile team collaboratively integrates reviews and updates with the sole purpose of satisfying the customer and product owner’s needs (PMBOK 7th edition, page 235). The identification of the work items to be accomplished during the next sprint is carried out during the sprint planning. The backlog is a prioritized list of product requirements that is maintained by the team. An information radiator or a Kanban board helps to keep track of the product and sprint backlogs.
Question 54:
Velocity generally enables project managers to make predictions that are accurate, but not totally precise, concerning project planning. The term “Velocity” in scrum refers to?
A team’s sprint-by-sprint progress rate
Project execution speed
Team members’ average capacity
All of the above
A team’s sprint-by-sprint progress rateProject execution speedCorrect answerTeam members’ average capacityAll of the aboveOverall explanationVelocity refers to a Scrum development team’s rate of delivering business value. An agile team’s velocity is calculated by simply adding up the estimates or story points of all the features, user stories, requirements, or tasks successfully delivered by all team members during an iteration.
Question 55:
“Impediments” are usually evoked during daily standups, and in some cases, they are thoroughly discussed during the sprint retrospective. “Impediments” refer to:
Issues that hinder the Agile team’s project completion
Change requests
External risks
Problems caused by the product owner
Correct answerIssues that hinder the Agile team’s project completionChange requestsExternal risksProblems caused by the product ownerOverall explanationThe term “impediment” refers to problems and issues that stop the project team’s progress. Impediments should be constantly and regularly identified as they can hinder a project’s completion. Identifying, tracking, and helping remove impediments is one of the main responsibilities of the Project Manager or Scrum Master. Often, team members are able to remove their own impediments, as in the case of technical issues or risks. However, some impediments involving external issues or risks can be beyond the team’s ability to remove them. In this case, opting for support from outside of the Team is needed to overcome impediments.
Question 56:
8 tasks of an Agile project release have the following story points: 3, 2, 5, 5, 8, 1, 3, 5. Given that the team’s velocity is 10, how many iterations will they need to complete all of the 8 tasks?
3
4
5
7
3Correct answer457Overall explanationThe sum of all tasks is 32 story points. Therefore, after calculation, you’ll find that it will take 3.2 iterations for the team to complete the tasks of the given release: (32 story points / 10 story points = 3.2 iterations). However, since the timebox of an iteration should not be changed, 4 iterations are needed to complete the release tasks.
Question 57:
In order to explain to the client the meaning of a story point in the agile methodology, a project manager states that a story point can be defined as:
The equivalence of WBS in the predictive approach
An estimate of project duration
An estimate of the required efforts to complete a particular task
A score that is given to measure the clarity of a particular task
The equivalence of WBS in the predictive approachAn estimate of project durationCorrect answerAn estimate of the required efforts to complete a particular taskA score that is given to measure the clarity of a particular taskOverall explanationA story point is a metric used to estimate the difficulty of carrying out a given user story in an agile project. In other words, it is an abstract measure of the effort required to implement a user story. A story point is simply a number that indicates the difficulty level of the story. The difficulty varies depending on the complexities, risks, and efforts involved (PMBOK 7th edition, page 178).
Question 58:
A Scrum Master attends or facilitates the different Scrum events including the Sprint, Sprint planning, Daily standup, Sprint review, and Sprint retrospective. Which of the following options describes the sprint retrospective meeting?
A meeting for refining product backlog items
A meeting for discussing the negative and positive aspects of a sprint as well as any possible improvements
A meeting for defining and evaluating the work of the next sprint
A meeting held at the end of the project’s last sprint
A meeting for refining product backlog itemsCorrect answerA meeting for discussing the negative and positive aspects of a sprint as well as any possible improvementsA meeting for defining and evaluating the work of the next sprintA meeting held at the end of the project’s last sprintOverall explanationDuring the sprint retrospective meeting, all the good and bad aspects of the sprint are discussed. The retrospective meeting is considered a meeting for improvements, as it is mainly held to find the proper ways and means of identifying potential pitfalls and past errors, and to seek out new ways to avoid those mistakes. This meeting isn’t held at the end of the project’s last sprint; it recurrently takes place after the Sprint Review and before the following Sprint Planning. A backlog refinement meeting is used to refine product backlog items. The sprint planning meeting is used to define and evaluate the work of the next sprint.
Question 59:
A project manager is leading a project using an adaptive development approach. How should the project manager plan the project activities?
Plan all of the iterations work before the start of the project
Progressively elaborate the scope based on continuous feedback
Develop a high-level plan as the project progresses
Execute the project activities described in the Statement Of Work (SOW)
Plan all of the iterations work before the start of the projectCorrect answerProgressively elaborate the scope based on continuous feedbackDevelop a high-level plan as the project progressesExecute the project activities described in the Statement Of Work (SOW)Overall explanationPlanning activities in an adaptive approach entails progressively elaborating the work scope based on the stakeholders’ continuous feedback. The project is split into iterations, and at the end of each iteration, the customer reviews the accomplished work on the product. Then, the customer’s feedback is used to define the detailed scope of the next iteration. Defining all iterations’ work before the start of the project depicts an iterative development approach while implementing activities described in the statement of work depicts a predictive development approach.
Question 60:
After discussing the matter with stakeholders, the project manager decided to go with a hybrid approach for the new project in order to take full advantage of both predictive and adaptive approaches. When the project manager documented and estimated all activities, one of the stakeholders complained that the project seemed to follow the predictive approach instead. What should the project manager do next in order to demonstrate that they are actually following a hybrid approach?
Sequence activities
Develop schedule
Plan iterations
Estimate costs
Sequence activitiesDevelop scheduleCorrect answerPlan iterationsEstimate costsOverall explanationThe project manager can demonstrate that they are following the hybrid approach by adopting iterative practices along with predictive methods. All of the other options represent processes within the predictive approach, therefore they will not demonstrate to the stakeholder that the project manager is following a hybrid approach.
Question 61:
An organization selected a pilot project to experiment with the Agile approach. They hired an agile coach to help the project manager since they have been only using the predictive method in the past. During the fourth sprint retrospective, the project team complained that many organizational processes are hindering their work progress, resulting in project delays and rework. What should the project manager do?
Start dedicating part of daily standup meetings to resolving impediments
Conduct a root cause analysis in the following sprint retrospective
Identify the organizational processes that are causing issues and work on removing, changing, or alleviating them
Encourage the project team to be self-organizing by dealing with any problem that gets in their way
Start dedicating part of daily standup meetings to resolving impedimentsConduct a root cause analysis in the following sprint retrospectiveCorrect answerIdentify the organizational processes that are causing issues and work on removing, changing, or alleviating themEncourage the project team to be self-organizing by dealing with any problem that gets in their wayOverall explanationTransitioning to Agile does not mean that the approach with all its components will work for the organization, project, or team. Therefore, when issues with the new processes arise, the best practice would be customizing, tailoring, and adapting them to the team’s needs for optimum efficiency. This involves removing any processes that don’t seem to bring any value to the way the team is conducting work, changing to other more suitable processes, or altering the existing processes to fix any issues and make them more compatible with requirements. Daily standups are meant for learning the current progress of each team member’s work as well as detecting impediments rather than dedicating part of the meeting to resolving them, which is neither convenient nor practical since the meeting duration is time-boxed to 15 minutes. Besides, the impediments were already detected by the development team, which means that the project manager should work on removing them as their role entails, beyond the standup meetings.
Question 62:
At the time they joined the organization, the scrum master was leading a team of 6 members. But, the number has doubled since then, making collaboration complicated. Plus, team members expressed their discontent with standups lately, as they tend to repetitively exceed their allotted time. What could the scrum master do to deal with this situation?
Be more vigilant to standups’ duration so they do not exceed 15 minutes
Increase the standup meeting timebox to 20 minutes
Split the team into two Scrum teams and apply the Scrum of Scrums technique to facilitate coordination between them
Switch to a predictive approach since scrum is not suitable for teams counting more than 9 members
Be more vigilant to standups’ duration so they do not exceed 15 minutesIncrease the standup meeting timebox to 20 minutesCorrect answerSplit the team into two Scrum teams and apply the Scrum of Scrums technique to facilitate coordination between themSwitch to a predictive approach since scrum is not suitable for teams counting more than 9 membersOverall explanationScrum of Scrums (SoS), aka meta Scrum, is used to coordinate the work of two or more Scrum teams (Agile Practice Guide, page 111). The main aim of implementing the Scrum of Scrums approach is to create smaller, more coordinated independent teams. Since your team exceeds the maximum number of 9 team members per Scrum team, the logical alternative is to split the team in order to benefit from the efficiency of Scrum processes. The consequences of increasing resources should not be tackled by switching to a predictive approach. Instead, Scrum can evolve to “Scrum of Scrums” or even “Scrum of Scrum of Scrums” in such a case. Monitoring the standup duration, on the other hand, will not fix the problem since a very large team naturally results in longer standup meetings. Deciding to increase the meeting duration is not right either since it goes against Scrum principles.
Question 63:
The figure below presents the Agile triangle of constraints. Which terms correspond to A, B, C, and D respectively?
Flexible, Fixed, Cost, Scope
Flexible, Fixed, Scope, Cost
Fixed, Flexible, Cost, Scope
Fixed, Flexible, Scope, Cost
Flexible, Fixed, Cost, ScopeFlexible, Fixed, Scope, CostCorrect answerFixed, Flexible, Cost, ScopeFixed, Flexible, Scope, CostOverall explanationUnlike predictive approaches, projects that follow adaptive approaches have a fixed cost and schedule and flexible scope. A. Fixed, B. Flexible, C. Cost, and D. Scope.
Question 64:
An organization decided to use the agile approach for its new project. What should they get at the end of the first sprint?
A plan for the subsequent sprint
A potentially releasable product increment
A Minimum Viable Product (MVP)
A Work Breakdown Structure (WBS)
A plan for the subsequent sprintCorrect answerA potentially releasable product incrementA Minimum Viable Product (MVP)A Work Breakdown Structure (WBS)Overall explanationAgile uses iterations, also known as sprints, in each, a potentially shippable increment of the product is produced (Agile Practice Guide, page 101). The plan for the subsequent sprint is the output of the sprint planning event. A Minimum Viable Product (MVP) is a primary version of the product with just the basic functionalities with the purpose of collecting feedback or validating the product idea. It could take several sprints for the product to reach the MVP stage. Finally, a WBS is a planning technique used in the predictive approach.
Question 65:
An organization is making a progressive transition from the predictive to the adaptive approach. What can the project manager do to prepare their team for the transition? (Select two)
Provide training for the team on agile values and practices
Apply the “learning-by-doing” philosophy by immediately switching to agile approaches
Plan a gradual transition by introducing a few iterative or incremental techniques to their current project
Suggest a full transition since agile practices cannot be combined with predictive ones
Correct selectionProvide training for the team on agile values and practicesApply the “learning-by-doing” philosophy by immediately switching to agile approachesCorrect selectionPlan a gradual transition by introducing a few iterative or incremental techniques to their current projectSuggest a full transition since agile practices cannot be combined with predictive onesOverall explanationThe project manager should provide their team with relevant training in order to enable them to adopt the new agile practices with more confidence. They should also gradually introduce certain iterative or incremental techniques to make the transition smoother. This will improve the team learning process and accelerate delivering value to sponsors. Many teams can’t make a full immediate switch to the agile approach. It is preferable and even recommended to make a gradual transition by combining adaptive and predictive practices, which is known as a hybrid approach (Agile Practice Guide, page 30).
Question 66:
An organization intends to launch a project where team members are going to employ a pull system while aiming to limit work in progress. The pull system functions as follows: when a work item is done, it triggers a pull to bring in the next item on the to-do list. Which Agile framework does this describe?
Scrum
Kanban
Pull
Lean
ScrumCorrect answerKanbanPullLeanOverall explanationKanban is a workflow project management approach that uses a board to display and manage work items in columns, e.g., To do, In progress, Testing, and Done. Kanban is built around four key principles: Visualizing workflow, Limiting work in progress (WIP), Focusing on flow, and Continuous improvement. Scrum doesn’t rely on a pull work system, it relies on sprints to execute a selection of predetermined work items. Lean is not an Agile Framework, it’s rather a philosophy that promotes removing waste within work processes. Pull is a made-up term.
Question 67:
A project manager was assigned to a large project that has unclear requirements and deliverables. After choosing an agile approach to deal with the situation, what should the project manager do next?
Acquire an agile coach to clarify the project scope
Facilitate the identification and prioritization of current work items, then ensure their execution in an iterative and incremental way
Set up a cross-functional team to help define all the needed iterations for completing the project
Have a meeting with the product owner or sponsor to discuss project baselines
Acquire an agile coach to clarify the project scopeCorrect answerFacilitate the identification and prioritization of current work items, then ensure their execution in an iterative and incremental waySet up a cross-functional team to help define all the needed iterations for completing the projectHave a meeting with the product owner or sponsor to discuss project baselinesOverall explanationThe project manager should start by facilitating the identification and prioritization of evident requirements, hence helping with the elaboration of the product backlog. Next, and since the project is following an agile approach, the project manager should execute work iteratively and incrementally. Since the project is large and deliverables are vague, it might not be possible to make the project scope clearer and remove ambiguity before starting implementation. In that case, the predictive approach would be more suitable than agile. Needless to say that the agile coach’s role does not involve clarifying the scope of work, it rather entails helping the project team embrace an agile mindset. Defining all of the iterations needed for completing the project refers to predictive planning. Likewise, project baselines are only specified in predictive projects.
Question 68:
In the graph below, what concepts or approaches correspond respectively to positions A, B, C, and D?
Agile, Scrum, Kanban, Lean
Agile, Scrum, Lean, Kanban
Lean, Scrum, Agile, Kanban
Lean, Kanban, Agile, Scrum
Agile, Scrum, Kanban, LeanAgile, Scrum, Lean, KanbanLean, Scrum, Agile, KanbanCorrect answerLean, Kanban, Agile, ScrumOverall explanationA. Lean: a set of concepts that includes eliminating waste, amplifying learning, and delivering as fast as possible.
B. Kanban: a subset of lean which also refers to a framework within agile.
C. Agile: a subset of lean and an umbrella for several frameworks.
D. Scrum: one of the agile frameworks.
Please note that in the real exam such a question usually comes in the form of “drag & drop”.
Question 69:
In a meeting with the product owner, the agile project manager has been informed that many other functionalities should be added to the product, without the possibility of extending the project’s deadline. What should the project manager do?
Use the smoothing technique and allude that delays are possible in such cases
Inform the product owner that lower priority work items will have to be dropped from the project
Create a separate backlog for the new functionalities and work on it when time allows
Inform the product owner that the new functionalities should be first authorized through an official change request
Use the smoothing technique and allude that delays are possible in such casesCorrect answerInform the product owner that lower priority work items will have to be dropped from the projectCreate a separate backlog for the new functionalities and work on it when time allowsInform the product owner that the new functionalities should be first authorized through an official change requestOverall explanationThe agile project manager should inform the product owner that, consequently, they have to drop lower priority work items from the project. Unlike the predictive approach, agile projects do not require formal change requests to change the scope. However, when new functionalities with higher priority are added, lower priority functionalities might have to be dropped in case the project timeframe can’t be extended. The project manager should not have a pretext for delays. Plus, they should discuss what’s in their mind directly with the product owner without any implicit hints. On the other hand, it’s not appropriate to have two backlogs. The new requirements should be prioritized within the existing backlog. The new functionalities’ priority is high, thus they should not be tackled “when time allows”.
Question 70:
An organization assigned a Product Owner to a new agile project and asked them to work on creating value and generating Return on Investment (ROI) as early as possible. How can the product owner achieve the organization’s demands?
Share these priorities with the project team
Support and serve the project team
Prioritize product backlog items
Improve work processes
Share these priorities with the project teamSupport and serve the project teamCorrect answerPrioritize product backlog itemsImprove work processesOverall explanationIn order to get the most value as early as possible, the product owner should focus on prioritizing product backlog items. Sharing the organization’s priorities with the project team is important to help them understand the product owner’s choices. Still, the product owner is the one responsible for the product, not the project team. Improving work processes and supporting and serving the project team are the main focus of the scrum master rather than the product owner.
Question 1:
Network diagrams are a visual display of project work as they show the connection between work activities and how they progress from the project’s start to its completion. The longest path in a network diagram is known as:
Critical Path
Critical Chain
Float
Free Float
Correct answerCritical PathCritical ChainFloatFree FloatOverall explanationIn a network diagram, the critical path is the path with the longest series of tasks (PMBOK 7th edition, page 238). Activities that are not on the critical path have some float (also called slack) that allows some margin for delay without causing the delay or change of the project end date. Free float is the amount of time an activity can be delayed without delaying the early start of the immediate subsequent activity. The critical chain is also the longest path in the network diagram, but unlike the critical path, it takes into consideration resource availability in addition to technical dependencies.
Question 2:
In an interior design project for a library, the client asks the team to increase the number of bookshelves beyond what was agreed on. Since the project is on schedule and adding additional shelves will make no difference, the project manager consents to the client’s request. This is an example of:
Gold Plating
Customer Obsession
Scope Creep
Successful Project
Gold PlatingCustomer ObsessionCorrect answerScope CreepSuccessful ProjectOverall explanationScope creep (also known as “feature creep” or “requirement creep”) refers to the uncontrolled expansion of the project’s scope (PMBOK 7th edition, page 249). Customer obsession consists of an excessive focus on providing a better customer experience by meeting and even exceeding your client’s needs. However, customer obsession shouldn’t mean delivering beyond scope since the latter can increase the project schedule and cost, thus decreasing the success rate of the project. The tackled situation is not considered gold plating since the client is the one who brought up the change request; it was neither the project manager nor team members who added changes without the client’s approval, as gold plating implies.
Question 3:
A project manager is managing a software development project using the predictive approach. A day prior to the release deadline, a quality engineer on their team discovers a bug that may result in a one-week delay. What should the project manager do next?
Inform the stakeholders that there is a bug that requires 2 to 3 days to fix and put more pressure on the engineers to fix it on time
Meet with stakeholders and inform them about the situation and that it may take a week to resolve the bug
Update the lessons learned and add them to the organizational process assets
Create and send a change request document to the change control board
Inform the stakeholders that there is a bug that requires 2 to 3 days to fix and put more pressure on the engineers to fix it on timeCorrect answerMeet with stakeholders and inform them about the situation and that it may take a week to resolve the bugUpdate the lessons learned and add them to the organizational process assetsCreate and send a change request document to the change control boardOverall explanationAs soon as it becomes obvious that the project will be delayed, the project manager should notify the client and present them with new alternatives. They should be honest and transparent about delays. The question includes the term “next”, so the first thing that the project manager should do before creating a change request or updating lessons learned is meet with stakeholders to inform them about the situation. Under the RESPONSIBILITY section of the PMI’s Code of Ethics and Professional Conduct, page 3: When the project manager discovers errors or omissions caused by others, they should communicate them to the appropriate body as soon as they are discovered. Under the HONESTY section, page 6: the project manager should provide accurate information in a timely manner.
Question 4:
A project manager works for Massive Fun, a company specializing in eco-friendly kids’ toys. Two months into the project, they launch the second phase consisting in developing biodegradable playing dough. Hence, the project manager meets with the sponsor to check if any potential players were left out in the first phase and to discuss these new stakeholders’ influence. The activity that the project manager is carrying out with the sponsor can be identified as:
Planning stakeholder engagement
Identifying stakeholders
Planning resource management
Identifying risks
Planning stakeholder engagementCorrect answerIdentifying stakeholdersPlanning resource managementIdentifying risksOverall explanationThe project manager is identifying stakeholders and analyzing their level of influence. Although the project has been active for two months, it is recommended to perform this activity on a regular basis, especially when the project gets into a new phase.
Question 5:
A project manager is leading a project to implement a new ERP system for a local customer. The project manager guides the team to define the project requirements in detail before moving to execution. The project will be delivered after 4 months, but the customer will pay the organization in monthly installments. Which of the following project development approaches is the project manager adopting?
Predictive
Adaptive
Iterative
Incremental
Correct answerPredictiveAdaptiveIterativeIncrementalOverall explanationSince requirements are fixed and deliverables will only be shipped at the end of the project, then the project manager is using a predictive approach. The iterative approach is also characterized by a single delivery (Agile Practice Guide, page 18), but it has dynamic requirements. Adaptive and incremental approaches involve frequent small deliveries. In the described scenario, payment installments are not linked to deliverables or iterations; it’s just a payment option that has no influence or connection to the project development approach.
Question 6:
A project manager is assigned to a 12-month project that has a $100,000 budget. Six months have passed and $60,000 has been spent. On closer inspection, the project manager finds out that so far, only 40% of the work has been completed. The value of the completed 40% work is referred to as:
Planned value
Earned value
Actual cost
Cost variance
Planned valueCorrect answerEarned valueActual costCost varianceOverall explanationEarned Value refers to the value of the work accomplished to date (PMBOK 7th edition, page 239). If the project gets terminated at this point, Earned Value will show you the value that the project has produced. In this case, the project’s Earned Value (EV) is $40,000 = 40% of the value of total work. The amount of $60,000 represents the Actual Cost (AC). The planned value is $50,000 (50% of the budget), while the cost variance is -$20,000 (EV - AC).
Question 7:
A project manager is carrying out the initial planning activities for a gas pipeline construction project using a predictive approach. When estimating the pipeline installation activity, one team member states that they ran the same length of pipes in 14 hours on a previous similar project. Another team member claims that they can run 100 meters of gas pipes per hour. The team will need to run a total of 1000 meters of pipes. Using the analogous estimating technique, how many hours will it take the team to run the gas pipeline?
10
11
12
14
101112Correct answer14Overall explanationUnlike parametric estimating, the analogous estimating technique uses expert judgment by comparing a particular activity to a similarly completed one on a previous project in order to determine its duration or cost. This means that the project manager should rely on expert feedback, i.e., completing a similar task in 14 hours.
Question 8:
During project execution, a team member reaches out to the project manager to inquire about the work they need to accomplish in this phase of the project. Which of these documents comprises thorough descriptions of work packages?
WBS
WBS Dictionary
Activity List
Scope management plan
WBSCorrect answerWBS DictionaryActivity ListScope management planOverall explanationThe planned work is included in the lowest level of the WBS components, known as work packages. Detailed information on work packages, such as descriptions, owners, prerequisites, successors, due dates, etc. is included in the Work Breakdown Structure Dictionary (PMBOK 7th edition, page 253).
Question 9:
An activity has an Early Start (ES) of day 5, a Late Start (LS) of day 12, an Early Finish (EF) of day 10, and a Late Finish (LF) of day 17. Which of the following statements are correct regarding this activity? (Select two)
The activity is on the critical path
The activity is not on the critical path
The activity has a float
The activity has a lag
The activity is on the critical pathCorrect selectionThe activity is not on the critical pathCorrect selectionThe activity has a floatThe activity has a lagOverall explanationSince it has a 7-day float, this activity is not on the critical path. The float of this activity can be calculated by subtracting the Early Start (day 5) from the Late Start (day 12) or by subtracting the Early Finish (day 10) from the Late Finish (day 17). Since the float of the activity is greater than zero, then it’s not on the critical path. Remember that critical path activities have zero float.
Question 10:
A project manager is leading a construction project. Throughout its execution, the project was influenced by Organizational Process Assets (OPAs). Which of the following statements are considered as OPAs? (Select two)
Construction work requires a building permit from City council
Workers who don’t obey safety rules will be penalized
Only authorized personnel are allowed on site
Workers have expertise in infrastructure construction
Construction work requires a building permit from City councilCorrect selectionWorkers who don’t obey safety rules will be penalizedCorrect selectionOnly authorized personnel are allowed on siteWorkers have expertise in infrastructure constructionOverall explanation“Workers who don’t obey safety rules will be penalized” and “only authorized personnel are allowed on site” are considered Organizational Process Assets (OPAs) since they represent the organization’s internal procedures. “Workers have expertise in infrastructure construction” is an internal Enterprise Environmental Factor, while “Construction work requires a building permit from the City council” is an external Enterprise Environmental Factor.
Question 11:
The project team cannot plan for risks that are believed to be difficult to find or imagine. Therefore, a(n) ___________ reserve should be set for threats that were not identified in advance.
Management
Buffer
Contingency
Additional
Correct answerManagementBufferContingencyAdditionalOverall explanationThe Management Reserve is a budget under “management control” that is dedicated and used for risks that were not identified during risk analysis, aka unknown-unknowns (unknown = unidentified, unknowns = risks). On the other hand, a contingency reserve is used for identified risks with predetermined risk response strategies, aka known-unknowns (known = identified, Unknowns = risks) (PMBOK 7th edition, page 127). Additional reserve and buffer reserve are made-up terms.
Question 12:
In a predictive approach, which of the following statements are true about project deliverables? (Select two)
Project deliverables should be identified throughout the project lifecycle
Project deliverables can be products, services, or any other type of outcome
Once project deliverables have been identified, they should not be changed anymore
The acceptance criteria for deliverables should be described in the project agreement
Project deliverables should be identified throughout the project lifecycleCorrect selectionProject deliverables can be products, services, or any other type of outcomeOnce project deliverables have been identified, they should not be changed anymoreCorrect selectionThe acceptance criteria for deliverables should be described in the project agreementOverall explanationProject deliverables can be products, services, or any other type of outcome. In a predictive approach, project deliverables should be determined, described, and agreed upon as early as possible in the project, to avoid any costly changes later on. Acceptance criteria should also be described and agreed upon. The change is possible and should follow the change request process.
Question 13:
For a museum construction project, concrete is poured after the completion of rebar and formwork. Now, workers must wait 14 days before removing the formwork, as the concrete must be strong enough for this operation. The 14-day period is an example of:
A Lead
A Lag
Crashing
Fast-tracking
A LeadCorrect answerA LagCrashingFast-trackingOverall explanationLag Time is when a delay is purposely made between activities. Lead time, on the other hand, is the time saved by starting an activity before its predecessor is completed. Crashing and fast-tracking are two schedule compression techniques.
Question 14:
A project task is 90% complete. It cannot, however, be finished until another task is completed. What type of dependency is this? (Select two)
Finish-to-start (FS)
Finish-to-finish (FF)
Mandatory dependency
Discretionary dependency
Finish-to-start (FS)Correct selectionFinish-to-finish (FF)Correct selectionMandatory dependencyDiscretionary dependencyOverall explanationThis is an example of finish-to-finish mandatory dependency. Two tasks may in fact run concurrently in the case of a finish-to-finish dependency. However, the second task can be entirely completed only after the first task is 100% done. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work (PMBOK 7th edition, page 60).
Question 15:
A project manager of a dating mobile app received an urgent change request from the client. After checking the change request, the project manager realized that implementing it could be very costly. What is the best course of action for the project manager to take in this case?
Discussing the cost impact with the client
Implementing the change request straight away
Rejecting it due to its cost impact
Not allowing any change requests regardless of their cost
Correct answerDiscussing the cost impact with the clientImplementing the change request straight awayRejecting it due to its cost impactNot allowing any change requests regardless of their costOverall explanationThe project manager must discuss the impact of the change request on the project cost with the client. They cannot process the change request unless the client understands and accepts its impact.
Question 16:
Which of the following options represents the characteristics of the predictive project management approach? (Select two)
Scope, time, and cost are determined in the early phases of the project life cycle
Change is limited as much as possible during project execution
The scope is determined early in the project life cycle, but time and cost are routinely modified
After one iteration, deliverables have enough functionality to be considered complete
Correct selectionScope, time, and cost are determined in the early phases of the project life cycleCorrect selectionChange is limited as much as possible during project executionThe scope is determined early in the project life cycle, but time and cost are routinely modifiedAfter one iteration, deliverables have enough functionality to be considered completeOverall explanationPredictive methods focus on thoroughly analyzing and planning the future while taking into account known risks. The scope, time, and cost are all predetermined early in the project life cycle. Predictive teams often establish a Change Control Board (CCB) to ensure that only valuable changes are considered for implementation.
Question 17:
A project manager is using a predictive approach to lead his project. Team members have been allocated to this project with 50% availability. However, the project manager recently discovered that the team has been spending less than 50% of their time working on the project. The project schedule is about to become heavily delayed, putting deadlines in jeopardy. What should the project manager do?
Discuss getting additional resources with the project sponsor
Negotiate clear and written assignments with reliable scheduling priorities with functional managers
Adjust the schedule and negotiate new deadlines due to unexpectedly slow work progress
Crash the project in order to complete it on time
Discuss getting additional resources with the project sponsorCorrect answerNegotiate clear and written assignments with reliable scheduling priorities with functional managersAdjust the schedule and negotiate new deadlines due to unexpectedly slow work progressCrash the project in order to complete it on timeOverall explanationSince the project manager didn’t assign the team members himself, then the organization must be functional. In this case, it is best to talk with functional managers and negotiate clear and written assignments with reliable scheduling priorities. It is the responsibility of functional managers, not the project sponsor, to manage staff assignments. The project manager, on the other hand, should provide a resource calendar to make sure that functional managers are aware of when and what resources he needs for his project. Adjusting or crashing the schedule without tackling the source of the problem is not the right course of action. Besides, crashing the project requires adding more resources, which is beyond the project manager’s authority in a functional organization.
Question 18:
Upon request, a project manager presents to his superiors the order of magnitude estimations for the hostel construction project he’s leading. The level of accuracy of the order of magnitude estimation is:
-25% to +75%
-25% to +50%
-10% to +25%
-5% to +10%
Correct answer-25% to +75%-25% to +50%-10% to +25%-5% to +10%Overall explanationA Rough Order of Magnitude Estimate (ROM estimate) is an estimation of the needed effort and cost to complete a project. A ROM estimate is performed very early in a project’s life cycle; during the project selection and approval period and prior to project initiation in most cases. The order of magnitude during the initiation phase has an accuracy range of -25% to 75% (PMBOK 6th edition, page 241).
Question 19:
Within the predictive approach, which of the following terms is used for both costs and schedules to establish what you’ll measure against later in the monitoring and controlling phase?
Variance
Expected value
Baseline
Estimates
VarianceExpected valueCorrect answerBaselineEstimatesOverall explanationCost and schedule baselines are used to assess performance in the monitoring and controlling phases.
Question 20:
The project team includes one carpenter who is only available to work part-time. Since her work is on the critical path, the project’s planned completion date had to be pushed back to align with her availability. The adjustment of the project schedule to handle resource constraints is referred to as:
Load Balancing
Resource Loading
Resource Leveling
Resource Smoothing
Load BalancingResource LoadingCorrect answerResource LevelingResource SmoothingOverall explanationResource leveling is used to optimize resource allocation by adjusting the activities’ start and finish dates. This often results in changing the original critical path, as was the case in the described scenario; the carpenter is a scarce resource for the project and her availability is constrained, which led to extending the project schedule to manage this limitation. Resource smoothing, on the other hand, is performed to achieve a more consistent resource utilization over a period of time. Resource loading is the total assigned hours of work divided by the number of hours you have to do the work. Load balancing is common in computing and it refers to the process of distributing a set of tasks over a number of resources with the aim of speeding up the overall data processing.
Question 21:
The following diagram represents the decomposition of the project deliverables into smaller tasks. What is this diagram called?
Affinity diagram
Product breakdown
Product roadmap
Work breakdown structure
Affinity diagramProduct breakdownProduct roadmapCorrect answerWork breakdown structureOverall explanationThe WBS is a hierarchical decomposition of the total scope of work to create the required deliverables (PMBOK 7th edition, page 81). The planned work is included in the lowest level of the WBS components, which are called work packages. Product breakdown is a product analysis technique (PMBOK 6th edition, page 153). The product roadmap demonstrates the anticipated sequence of deliverables throughout the project duration. Affinity diagrams classify a large number of ideas into groups for analysis and review.
Question 22:
A project manager is leading a new virtual reality game development project. The project is scheduled to last 10 months with a budget of $100,000. One month into the project, the team completed 10% of the total work. What is the project’s current Schedule Performance Index (SPI)?
0.1
1
1.1
10
0.1Correct answer11.1 10Overall explanationThe schedule performance index (SPI) is a measure of the conformance of actual progress (earned value) to the planned progress: SPI = EV / PV (PMBOK 7th edition, page 249). A value of 1.0 indicates that the project performance is on target. When CPI or SPI is greater than 1.0, it indicates better-than-planned project performance, while a CPI or SPI that is less than 1.0 indicates poorer-than-planned project performance.
Question 23:
Adopting a predictive approach to plan an agriculture project, a project manager chooses the ___________ method to estimate the cost by using work breakdown.
Analogous
Parametric
Top-down
Bottom-up
AnalogousParametricTop-downCorrect answerBottom-upOverall explanationThe bottom-up method can be used as an estimation technique for the project’s overall cost by estimating the approximate value of smaller components and using the total sum of these values to find the overall cost. This type of estimation is used to create the project schedule or budget. The project work is typically subdivided into smaller parts and each component is given a duration and cost estimate. The individual duration estimates are aggregated to determine the schedule, while the individual cost estimates are aggregated to determine the budget.
Question 24:
A project manager is assigned to an industrial project that follows a predictive approach. During the risk planning phase, the project manager decided to create a contingency reserve for:
Passive risk acceptance
Active risk acceptance
Workaround
Unidentified risks
Passive risk acceptanceCorrect answerActive risk acceptanceWorkaroundUnidentified risksOverall explanationRisk acceptance acknowledges the existence of a threat, but no proactive action is taken (PMBOK 7th edition, page 248). The most common active acceptance strategy is to establish a contingency reserve, including time, money, or resources to handle the threat if it occurs. Passive acceptance involves no proactive action apart from a periodic review of the threat to ensure that it does not change significantly (PMBOK 6th edition, page 443). A workaround is an unplanned response to deal with unidentified risks and risks that are passively accepted.
Question 25:
A project manager is leading a construction project. Work on light spots is pending since ceiling tiles are still being installed, which may cause some delays within the project. What should the project manager refer to in order to check the electricity team’s availability in the next two weeks to resolve this dependency?
Resource Calendars
Responsibility Assignment Matrix (RAM )
RACI Matrix
Organigram
Correct answerResource CalendarsResponsibility Assignment Matrix (RAM)RACI MatrixOrganigramOverall explanationA resource calendar is a calendar for planning, managing, and monitoring resources, including both employees and equipment. It gives project managers an overview of how resources are being utilized, which resources are available, and when. On the other hand, the Responsibility Assignment Matrix (RAM) describes the involvement of different parties and their roles in completing tasks or deliverables in a project. It’s used to clarify roles and responsibilities within a team, project, or process. RACI is an acronym for Responsible Accountable Consult and Inform and it’s used to assign roles and responsibilities for each task in a given process. An organigram, also called an organizational chart, organogram, or organizational breakdown structure (OBS), is a diagram that depicts the organization’s structure and the relationships and ranks of its different positions.
Question 26:
A project manager created the following high-level hierarchical list of human and physical resources of a project that consists in creating a bulk SMS platform for marketing campaigns. What does this visual illustration represent?
Resource calendar
Organization breakdown structure
Resource breakdown structure
RACI chart
Resource calendarOrganization breakdown structureCorrect answerResource breakdown structureRACI chartOverall explanationA resource breakdown structure is a hierarchical list of team and physical resources related by category and resource type that is used for project planning, management, and control (PMBOK 7th edition, page 187). Each descending level corresponds to a more detailed description of the resource. A resource calendar, on the other hand, is a calendar for planning, managing, and monitoring resources. Organizational Breakdown Structure (OBS), also known as Organization Chart, is used for representing the project organization. RACI is an acronym for Responsible Accountable Consult and Inform and it’s used to assign the roles and responsibilities of the individuals involved in a project or a process.
Question 27:
A project manager is leading a project that has a fixed fee of $5,000 and an estimated cost of $50,000. Knowing that the actual cost of the project reached $60,000, what is the total cost of the Cost Plus Fixed Fee contract?
$50,000
$55,000
$60,000
$65,000
$50,000$55,000$60,000Correct answer$65,000Overall explanationThe total cost of the Cost Plus Fixed Fee (CPFF) contract is the sum of the Actual cost and the Fixed fee; $60,000 + $5,000 = $65,000.
Question 28:
A project manager is assigned to lead a construction project for the first time. Three months in, the project manager notices that the running cost is higher than expected. So, they decide to assess the project’s financial status by calculating the difference between Earned Value (EV) and Actual Cost (AC). What is the project manager calculating?
Cost Performance Index
Cost Variance
Planned Value
To-Complete Performance Index
Cost Performance IndexCorrect answerCost VariancePlanned ValueTo-Complete Performance IndexOverall explanationThe amount of budget deficit or surplus at a given point in time expressed as the difference between Earned Value(EV) and the Actual Cost (AC), is known as Cost Variance (PMBOK 7th edition, page 238).
Question 29:
A predefined budget allocation is a project ___________________.
Budget
Assumption
Risk
Constraint
BudgetAssumptionRiskCorrect answerConstraintOverall explanationProject constraints are limiting factors for your project that can impact delivery, quality, and overall project success. An imposed delivery date or a predefined budget are considered project constraints (PMBOK 7th edition, page 72).
Question 30:
A project manager is in charge of an ergonomic chair design project. Upon the identification of some technical risks, the project manager decides it’s best to create a prototype. This is an example of risk:
Acceptance
Avoidance
Transfer
Mitigation
AcceptanceAvoidanceTransferCorrect answerMitigationOverall explanationRisk mitigation can imply prototype development in order to prevent the risk from scaling up. Creating a prototype will support the testing and through testing, you can generate the necessary data to probably even close the risk. To keep costs low, you can opt for partial prototypes for the specific portions of the process that involve the risk.
Question 31:
A project manager working at Smart Tools, a smart kitchen appliances company, has recently completed the design phase of a product. Therefore, the project manager is currently arranging a phase review with the steering committee, which will be facilitated by the company’s PMO. Phase reviews are also called:
Kill point
Endpoint
PMO review
Project review
Correct answerKill pointEndpointPMO reviewProject reviewOverall explanationPhase reviews, aka phase gates, phase exits, phase entrances, kill points, and stage gates, is a formal review of the project to evaluate its status. The results are documented and presented to the concerned stakeholders or the sponsor in order to get their approval to proceed to the next phase in the project lifecycle. It’s called “Kill point” because when your board determines that your project hasn’t achieved its objectives to date, they may decide to stop it (PMBOK 7th edition, page 244).
Question 32:
A project manager is in charge of a project for creating a next-generation vehicle. Before the assembly of the vehicle can be performed, the wheels have to be designed and built. Which type of dependency does this situation depict?
External
Discretionary
Soft Logic
Mandatory
ExternalDiscretionarySoft LogicCorrect answerMandatoryOverall explanationA mandatory dependency is also called a hard dependency or hard logic. For example, consider 2 activities A and B, if B has a mandatory dependency on A, it means action on B cannot be performed until action on A has been completed. A discretionary or soft logic dependency, on the other hand, is an optional or preferred dependency. External dependencies involve a relationship between project activities and non-project activities (PMBOK 7th edition, page 60).
Question 33:
After being assigned by management to lead a new project, the project manager is immediately asked to develop the project charter in order to launch the project as soon as possible. To develop the project charter, the project manager will need the following documents: (Select three)
Strategic plan
Business case
Agreements
Project plan
Correct selectionStrategic planCorrect selectionBusiness caseCorrect selectionAgreementsProject planOverall explanationTo develop the Project Charter, the project manager needs business documents such as the project’s business case, benefits/strategic plan, and agreements. The project plan is developed once the project charter is signed.
Question 34:
Midway through the execution phase of a construction project, a key team member requests a two-month leave for personal reasons. What should the project manager do first before taking their decision about the team member’s leave request?
Find a replacement
Evaluate the impact of the team member’s leave on the project
Persuade the team member to take several short leaves over the remaining project duration instead
Ask the team member to postpone their leave
Find a replacementCorrect answerEvaluate the impact of the team member’s leave on the projectPersuade the team member to take several short leaves over the remaining project duration insteadAsk the team member to postpone their leaveOverall explanationThe first thing the project manager should do in this situation is to understand what impact this leave will have on the project. For instance, a two-month leave may not have a big impact on a 3-year project, but it will have a significant impact on a 6-month project, especially if this team member is a key player. After evaluating the impact, the project manager can ask the team member to postpone their leave or split it into shorter leaves over the project duration. If the impact of the team member’s leave is still significant, even with these two solutions, then the project manager may need to seek a replacement.
Question 35:
Using a predictive approach, the project manager was able to finish the project six weeks ahead of schedule, despite the $75,000 increase in project costs. This situation depicts:
Resource leveling
Resource smoothing
Crashing
Fast-tracking
Resource levelingResource smoothingCorrect answerCrashingFast-trackingOverall explanationProject crashing implies reducing the time one or more tasks take in order to minimize the overall duration of the project. Crashing consists of increasing the project resources to help finish tasks in less time than planned. However, this leads to an increase in project costs. Such measures cannot be implemented without the approval of the sponsor or key stakeholders. Fast-tracking is also a schedule compression technique, but it involves performing tasks simultaneously without adding more resources or increasing costs (PMBOK 7th edition, page 59). Resource leveling and resource smoothing are two resource optimization techniques, which are used to respond to resource limitations. These two techniques can only extend the project schedule.
Question 36:
A project manager is leading a software development project worth $100,000. Referring to the project status report, the project manager finds out that they have spent $30,000, with 25% of the work completed. The project is:
Under budget
Over budget
Ahead of schedule
Behind schedule
Under budgetCorrect answerOver budgetAhead of scheduleBehind scheduleOverall explanationThe project manager can determine the financial status of their project by calculating the Cost Performance Index (CPI = EV / AC) or the Cost Variance (CV = EV - AC). Since AC = $30,000, then they need to calculate the Earned Value (EV = % completed work x budget). Considering the described scenario, EV= 25% x $100,000 = $25,000.
Consequently, CPI = $25,000 / $30,000 = 0.833 which is less than 1, meaning that the project is over budget. CV = $25,000 - $30,000 = - $5,000 which is less than 0, which confirms that the project is over budget.
Question 37:
The procurement manager who is assigned to a construction project meets with the project manager to assess the final performance of the project’s primary vendor. This involved discussing the multiple issues that they experienced with this vendor, including late delivery and budget overruns. The procurement manager and the project manager also analyzed what they could have done differently and what they did well when it comes to addressing the vendor issues when they occurred. What activity are the procurement manager and the project manager engaged in?
Collaborating on an open claim with the vendor
Generating a work performance report
Confirming the formal acceptance of the vendor’s work
Capturing lessons learned
Collaborating on an open claim with the vendorGenerating a work performance reportConfirming the formal acceptance of the vendor’s workCorrect answerCapturing lessons learnedOverall explanationThe procurement manager and the project manager are discussing lessons learned in engaging with this particular vendor and also in activities associated with managing the vendor’s performance. This includes identifying what went well and what could have been done differently, which will benefit future projects.
Question 38:
A project manager is managing a telecommunication project following the predictive approach. While controlling the project execution, she uncovers scope creep caused by a key project stakeholder who happens to be her close friend. What should the project manager do?
Nothing, since the scope creep was caused by a prominent stakeholder and a close friend
Reverse the scope changes since she didn’t approve them
Take the scope creep to the change control board
Nothing, since the scope creep could have a positive impact on the project
Nothing, since the scope creep was caused by a prominent stakeholder and a close friendReverse the scope changes since she didn’t approve themCorrect answerTake the scope creep to the change control boardNothing, since the scope creep could have a positive impact on the projectOverall explanationThe scope creep should be brought to the project team’s attention and treated as an unapproved change. This will also need to go through the formal channel by reporting it to the change control board and decide with them on the appropriate course of action (PMBOK 7th edition, page 87). Undoing the changes without referring to the CCB means the project manager is going to perform additional work that is not part of the scope, resulting in further scope creep; That’s why they need approval from CCB. As the project manager, she should avoid favoritism and any situations of conflict of interest by maintaining impartiality in her decisions.
Question 39:
A project manager leads a project to build a water distillation machine. After internally verifying that the product properly extracts essential oils, the product was shipped to the client site. After receiving the machine, the client sent an email to the project manager asking whether it met the requirements or not. What should the project manager do next?
Send an engineer to the client’s site to double-check the product
Perform the control quality process and use the contingency reserve to fix any unidentified issues
Collaborate with the client to get their signature approving that the product complies with requirements
Confirm that the product was internally tested and formally close the project
Send an engineer to the client’s site to double-check the productPerform the control quality process and use the contingency reserve to fix any unidentified issuesCorrect answerCollaborate with the client to get their signature approving that the product complies with requirementsConfirm that the product was internally tested and formally close the projectOverall explanationAt this stage, the project manager should work with the client to get their signature as approval that the product complies with requirements. Confirming that the product has been internally tested on your part is not sufficient since the client must validate that the product does meet their requirements. The control quality process is supposed to be performed before the product is shipped. In this situation, the client just asked whether the product meets the requirements or not and didn’t report any problems. Thus, the proper next step is to go over all of the product specifications with the client to formally validate them and get their signature approving that the product complies with requirements in order to finally close the project.
Question 40:
The team of a predictive project discovers that many implemented features are different from the outlined scope in the scope statement. Which of the following documents should the project manager refer to in order to deal with this matter?
WBS
WBS dictionary
Requirements traceability matrix
Project charter
WBS WBS dictionaryCorrect answerRequirements traceability matrixProject charterOverall explanationThe traceability Matrix is a document that maps requirements as well as other aspects of the project. It’s used as evidence to confirm that requirements have been fulfilled, as it typically documents those requirements along with issues and test results (PMBOK 7th edition, page 189).
Question 41:
A project manager is assigned to a project consisting of four phases. Which of the following meetings should the project manager hold at each phase to ensure the continuous commitment of project stakeholders?
kickoff meeting
Retrospective meeting
Risk review meeting
Stage gate meeting
kickoff meetingRetrospective meetingRisk review meetingCorrect answerStage gate meetingOverall explanationStage-gate or phase review meetings represent an opportunity for project stakeholders to review project progress along with planned future actions. In these meetings, project stakeholders can assess whether or not the project is on track to meet the organization’s expectations (PMBOK 7th edition, page 42). You should schedule gate meetings at key milestones throughout your project to not only ensure it is on track but also demonstrate to the project stakeholders that you are staying on course.
Question 42:
Prior to a meeting with the sponsor to update them on the project status, a project manager is going through the project status report which shows that the SPI is 0.8, while the CPI is 1.1. What should be more concerning to the project manager?
Nothing, the project is performing well
Cost
Schedule
Risk
Nothing, the project is performing wellCostCorrect answerScheduleRiskOverall explanationSince the Schedule Performance Index (SPI) is less than 1.0, then the project is behind schedule. Consequently, the project manager should be concerned about the project schedule. Since CPI is 1.1, then the project is under budget. Thus, the project is on track cost-wise. There is no indication in the question that the project manager should be concerned about risks.
Question 43:
A project manager is planning a cryptocurrency conference. The Ministry of Finance, which is the conference sponsor, limited the number of attendees to forty. One day prior to the event, the project manager got a call from the ministry office informing them that they wanted to add two other subject matter experts to the conference attendees list. Luckily, the conference room has a seating capacity of fifty people. However, the project manager needs to rearrange lodging, catering, coffee breaks, gift packages, etc. accordingly. What should the project manager do first?
Issue a change request to address the ministry’s request
Accept the ministry’s request and increase the number of attendees since the conference didn’t start yet
Accept the ministry’s request and increase the number of attendees since the request is issued by the sponsor
Refuse to increase the number of attendees since the event is only one day away
Correct answerIssue a change request to address the ministry’s requestAccept the ministry’s request and increase the number of attendees since the conference didn’t start yetAccept the ministry’s request and increase the number of attendees since the request is issued by the sponsorRefuse to increase the number of attendees since the event is only one day awayOverall explanationWhen a critical key stakeholder requests a change, the project manager should treat it with high priority and issue a change request to the Change Control Board (CCB) in order to add their request to the scope (PMBOK 7th edition, page 77). In the described situation, the project manager is able to address the stakeholder request. So, it’s not appropriate to decline the change request under the pretext that the conference date is only one day away. On the other hand, the project manager should not immediately increase the number of attendees because this will be considered scope creep. Even though the conference hasn’t started yet, project execution has already begun since the project team has contacted suppliers, reserved attendees’ accommodations, booked the conference room, etc.
Question 44:
A project manager calculates the early & late start and finish dates of his project activities. One of the activities has the following representation. What is this activity’s float?
16
8
12
24
16Correct answer81224Overall explanationFloat, Total float, Slack, or activity float represents how long an activity can be delayed without causing a delay in the project completion date. On a critical path, the total float is zero. You can calculate an activity float by subtracting the Early Start date of the activity from its Late Start date: (12 - 4 = 8 days), or by subtracting the Early Finish date of the activity from its Late Finish date (28 - 20 = 8 days).
Question 45:
The ______________ is a project forecasting tool that represents the cost estimate of a project if it keeps the same cost performance.
Estimate to Complete (ETC)
Variance at Completion (VAC)
Estimate at Completion (EAC)
Budget at Completion (BAC)
Estimate to Complete (ETC)Variance at Completion (VAC)Correct answerEstimate at Completion (EAC)Budget at Completion (BAC)Overall explanationEstimate at Completion (EAC) is defined as the sum of the completed work cost plus the cost required to finish the remaining work. Estimate at Completion (EAC) may differ from the Budget At Completion (BAC) based on the project performance (PMBOK 7th edition, page 104). If it becomes obvious that the BAC is no longer viable, the project manager should consider the forecasted EAC instead.
Question 46:
A project manager is managing an eCommerce project using a predictive approach. The customer reached out to the project manager asking him to add a new feature to allow users to rate the products they purchased. Knowing that this feature may involve some security risks, what should the project manager do next? (Select two)
Inform the customer of the potential risks to convince them to change their mind
Ask the customer to submit a change request
Protect the team from distractions by asking the customer to put off the change until they finish the project
Evaluate the change and its associated risks with the team
Inform the customer of the potential risks to convince them to change their mindCorrect selectionAsk the customer to submit a change requestProtect the team from distractions by asking the customer to put off the change until they finish the projectCorrect selectionEvaluate the change and its associated risks with the teamOverall explanationSince the project manager is adopting a predictive approach, he should ask the customer to submit a change request that will be evaluated by him and his team. The change request evaluation should cover analyzing its associated risks and implications. After gathering all information, the Change Control Board (CCB) will decide to either accept the change or reject it. The project manager is usually a member of the CCB. In this case, the project manager may influence the decision based on the conducted analysis. But, he cannot do this without assessing the change with his team first (PMBOK 7th edition, page 77). The customer may not accept postponing the change. The concept of protecting the team from distraction or external interference doesn’t exist in the predictive approach; it’s rather common in the Scrum framework, more specifically during sprint execution.
Question 47:
A project manager is managing a highway paving project. Four months into project execution, the project manager notices that the performance is deteriorating. What did the project manager examine to make such a realization?
Status Report
Risk Report
Forecasting Report
Trend Report
Status ReportRisk ReportForecasting ReportCorrect answerTrend ReportOverall explanationA trend Report is used to check the performance status; whether the project performance is on track, improving, or deteriorating over a time period. This report shows a comparison between the project’s current performance in a specific duration against its previous performance during a similar time duration (comparing monthly performances for example). Performance could be compared monthly, quarterly, semesterly, or annually.
Question 48:
While managing an industrial project, a project manager notices that two stakeholders are always debating which may have a negative impact on the project. Which of the following options is used to document and monitor this type of situation?
Dispute log
Problem log
Change log
Issue log
Dispute logProblem logChange logCorrect answerIssue logOverall explanationThe issue log, also called an issue register, is a project document that records and tracks all issues that have a negative impact on the project (PMBOK 7th edition, page 185). Once created, it’ll be the project manager’s tool to monitor and communicate all that is going on in the project. Such issues may involve resources leaving the project, conflicting teams, or even individuals with low morale. A change log is used to document all change requests. Problem log and dispute log are both made-up terms.
Question 49:
Before announcing the completion of the project execution, the project manager of a construction project reviews deliverables and performs a site walkthrough. What is the project manager performing in this scenario?
An inspection
A handing over
An audit
A scope validation
Correct answerAn inspectionA handing overAn auditA scope validationOverall explanationDuring an inspection, the project manager reviews deliverables and performs a site walkthrough if applicable. Audits, on the other hand, are carried out to determine if project activities comply with organizational and project policies, processes, and procedures (PMBOK 6th edition, page 294). In other words, audits are performed on processes while inspections are performed on products. The project manager here is neither validating the scope with the customer nor handing over deliverables to them.
Question 50:
The most recent project of Kitchen Plus Inc. involves the creation of an automatic dicer with industry-exclusive characteristics. Based on the information provided by the project team, the current Schedule Performance Index (SPI) is 1.10, while the Cost Performance Index (CPI) is 0.80. What should the project manager do to balance out the performance of both the schedule and budget?
Crash the schedule by adding more resources to critical activities
Fast-track the longest activities that fall on the critical path
Level out resource usage to further spread out costs over time
Nothing, since the project is performing as expected
Crash the schedule by adding more resources to critical activitiesFast-track the longest activities that fall on the critical pathCorrect answerLevel out resource usage to further spread out costs over timeNothing, since the project is performing as expectedOverall explanationBased on the performance indexes provided, the project is 10% ahead of schedule while being over budget. Leveling out resource usage is a strategy used to spread out costs over time. This helps reduce unexpected spikes of spending, albeit it may lead to lengthening the schedule. Crashing or fast-tracking are two schedule compression techniques. So, it’s pointless to use them in the described situation since the project is ahead of schedule.
Question 51:
A project manager is managing a project with a distributed team, fixed budget, and tight deadlines. Knowing that they’re adopting a predictive approach, what should the project manager do to avoid any scope creep and keep their team focused on delivering a product that meets requirements?
Ask the project team to skip small requirements so that they can only focus on big and important ones
Ensure that all alterations to the scope are authorized through a formal process
Prevent stakeholders from directly interacting with the project team
Scope creep cannot be avoided in a predictive project, therefore the project manager should adopt an agile approach instead
Ask the project team to skip small requirements so that they can only focus on big and important onesCorrect answerEnsure that all alterations to the scope are authorized through a formal processPrevent stakeholders from directly interacting with the project teamScope creep cannot be avoided in a predictive project, therefore the project manager should adopt an agile approach insteadOverall explanationThe project manager can avoid scope creep by adhering to the agreed-upon change management process. Change management processes have to be set up front and should be very straightforward. Essentially, when a change is suggested, it should be reviewed, approved or rejected, and then incorporated into the project plan if it’s approved (PMBOK 7th edition, page 87). Requirements shouldn’t be skipped, small or big. Often, it’s not appropriate to prevent the stakeholders from communicating with the project team. Not all projects are fit for the agile approach, therefore it’s not appropriate to change the project’s development approach just to prevent scope creep.
Question 52:
One year into managing a predictive project, and during the completion and closure process, the project manager faces a key stakeholder’s refusal to sign off the deliverables due to non-compliance claims. What can the project manager do to ensure stakeholder acceptance?
Issue a change request
Conduct a sprint retrospective
Change the SOW
Conduct a variance analysis
Issue a change requestConduct a sprint retrospectiveChange the SOWCorrect answerConduct a variance analysisOverall explanationVariance analysis is a technique used at the end of a project or phase in order to identify any deviation in deliverables or difference between actual and planned behaviors. This method is used to determine the cause and magnitude of the difference between baseline and actual performance, as well as retain control over the project (PMBOK 7th edition, page 177).
Question 53:
Due to high levels of uncertainty, the project manager opts for the rolling wave method for the project planning. How is this method useful in this case?
It will help the project manager determine which activities are more important to prioritize
It will help the project manager organize the project’s activities and tasks
It will help the project manager determine the sequencing of a large number of activities
It will help the project manager reach the proper level of detail in each work package at the right time
It will help the project manager determine which activities are more important to prioritizeIt will help the project manager organize the project’s activities and tasksIt will help the project manager determine the sequencing of a large number of activitiesCorrect answerIt will help the project manager reach the proper level of detail in each work package at the right timeOverall explanationRolling wave is a project planning method that consists of a gradual elaboration of details to the Work Breakdown Structure (WBS) over time. Near-term deliverables are decomposed into individual components (work packages) that are broken down to the greatest degree of detail. Long-term deliverables, on the other hand, are identified more broadly. In this way, rolling wave planning allows work to progress on current and near-term deliverables while the planning for potential work packages continues. The Rolling wave method is used to address uncertainty rather than prioritizing, organizing, or sequencing activities (PMBOK 7th edition, page 249).
Question 54:
Within a predictive approach, the _________________ is the basis for cost estimation.
Scope management plan
WBS
Resource management plan
Cost baseline
Scope management planCorrect answerWBSResource management planCost baselineOverall explanationSince it includes all of the project deliverables as well as the control accounts associated with work package elements, the Work Breakdown Structure (WBS) acts as the foundation for cost estimates.
Question 55:
A project manager was informed by the project sponsor that they need to complete the project one week sooner than the originally agreed-upon schedule. Knowing that the project follows a predictive approach, what should the project manager do first in order to implement the sponsor’s request?
Crash the schedule
Fast-track the schedule
Add duration buffers
Level out resources
Crash the scheduleCorrect answerFast-track the scheduleAdd duration buffersLevel out resourcesOverall explanationIn this scenario, one of two schedule compression techniques must be used: crashing or fast-tracking. Crashing the schedule involves compressing it by adding more resources to the project. However, fast-tracking implies performing originally sequential activities in a simultaneous way instead (PMBOK 7th edition, page 59). When possible, select the least costly option first, which would be fast-tracking.
Question 56:
Before taking a long leave, a project manager informed the person filling in for them that they should regularly calculate the project’s Earned Value (EV). Among the following options, what is the right description of an Earned Value?
The difference between the budgeted cost of the performed work and its actual cost
The cost of labor spent to date
The method of determining how much of the budget should have been spent based on the amount of work accomplished to date
The amount of money that has been spent so far on the project
The difference between the budgeted cost of the performed work and its actual costThe cost of labor spent to dateCorrect answerThe method of determining how much of the budget should have been spent based on the amount of work accomplished to dateThe amount of money that has been spent so far on the projectOverall explanationEarned Value (EV) is the method used to measure how much of the allocated budget should have been spent in view of the work realized to date (PMBOK 7th edition, page 239). This technique allows the project manager to calculate the Cost Variance (CV), which is the difference between the budgeted cost of the performed work (EV) and its actual cost, to eventually find out whether the project is under or over budget. The amount of money that has been spent so far represents the Actual Cost (AC).
Question 57:
When the dimensions of the dug canals for the new dam project were compared to the plan, a huge variance was revealed. Therefore, the project manager had to call for a meeting with the team to decide what to do next. In which of the following process groups does the project manager’s activity take part?
Executing
Closing
Monitoring and Controlling
Inspecting
ExecutingClosingCorrect answerMonitoring and ControllingInspectingOverall explanationReviewing the project performance in comparison to plans is part of the monitoring and controlling process group. These processes are meant for tracking, adjusting, and reporting on the project performance, as well as implementing corrective actions when needed to ensure the project is on track, budget and time-wise. Inspecting is not a process group, it’s rather a risk identification activity.
Question 58:
A project manager is assigned to a farm fencing project of 300 ft. Since they have already managed two similar projects in another region, the project manager knows that a chain-link fence costs $10 per foot for materials, and between $10 and $15 per linear foot for labor, depending on the workers’ experience and common rates in the region. What is the best way to estimate the labor cost per linear foot?
Three-point estimation
Parametric estimating
Bottom-up estimating
Analogous estimating
Correct answerThree-point estimationParametric estimatingBottom-up estimatingAnalogous estimatingOverall explanationThe three-point estimating is the triangular distribution of pessimistic, optimistic, and most likely estimates. This technique is used when there is insufficient historical data or when there is only judgmental data. Since the two similar projects were performed in another region, the project manager can’t precisely define the labor cost using analogous estimating. Parametric estimating can be used to estimate the cost of the 300 ft fence after figuring out the labor cost per linear foot, but since the PM needs to estimate the labor cost per linear foot, this technique can not be applied. Plus, bottom-up estimating can’t be used in this situation since the labor cost depends on the workers’ experience and the applied rates in the region, not on the volume and decomposition of the required work.
Question 59:
After creating the network diagram, the project manager identified three critical paths. What should the project manager do next?
Approve the network diagram and closely monitor all three critical paths
Approve the network diagram and closely monitor the longest path among the three
Re-examine the network diagram since it’s supposed to only have one critical path
Re-examine the network diagram since it’s not supposed to have more than two critical paths
Correct answerApprove the network diagram and closely monitor all three critical pathsApprove the network diagram and closely monitor the longest path among the threeRe-examine the network diagram since it’s supposed to only have one critical pathRe-examine the network diagram since it’s not supposed to have more than two critical pathsOverall explanationThe project manager should approve the network diagram and closely monitor all three critical paths. Theoretically, there is no limit on how many critical paths a network diagram could have. If a project has more than one critical path, then all critical paths must have exactly the same length.
Question 60:
After completing the creation of the scope statement, a project manager wanted to make sure that all of the project deliverables were identified and could be managed effectively. So, they opted for the _____________________ method to develop the WBS in order to capture all of the project’s details.
Scope decomposition
Bottom-up estimating
Rolling wave planning
Checklist analysis
Correct answerScope decompositionBottom-up estimatingRolling wave planningChecklist analysisOverall explanationScope decomposition is a planning method used to decompose and subdivide the project and scope deliverables into more manageable, small work units. The decomposition level depends on the complexity and size of the project (PMBOK 7th edition, page 84).
Question 61:
During the project execution phase, the Change Control Board (CCB) approved a change request that no one on the project team knew how to implement. What should the project manager do to deal with this issue? (Select two)
Document the issue in the issue log
Hire a subject matter expert
Formally request the CCB to revoke their decision
Ask the team to do more research on how to implement the approved change request
Document the issue in the issue logCorrect selectionHire a subject matter expertFormally request the CCB to revoke their decisionCorrect selectionAsk the team to do more research on how to implement the approved change requestOverall explanationHiring a subject matter expert and conducting more research will help your team implement the change request. This is considered a problem-solving approach since it entails finding solutions to the encountered issues or challenges. Uncertainty can be reduced by collecting more information through conducting research, engaging experts, or performing a market analysis (PMBOK 7th edition, page 229). Neither documenting the issue in the issue log nor asking the CCB to revoke their decision could help resolve the issue.
Question 62:
A newly assigned interim project manager got a call from one of the project vendors claiming that they had already completed 50% of the agreed-upon work and asked for payment. What should the project manager refer to in order to check whether they need to pay the vendor or not and how much should they get paid?
Request for proposal
Contract
Response to bid
Procurement management plan
Request for proposalCorrect answerContractResponse to bidProcurement management planOverall explanationThe contract is the document the project manager should refer to in order to verify the payment procedure. A contract is a mutually binding agreement that obligates the seller to provide the required services and the buyer to pay a predetermined amount on an agreed-upon date or schedule (PMBOK 7th edition, page 191).
Question 63:
During a construction project, the construction team finds out that the designed model for the swimming pool requires some raw material that is no longer available in the local market. However, there is an alternative with the same price and probably a better quality. What should the project manager do next?
Update the resource management plan to replace the old material with the new one
Submit a change request in order to get formal approval for using the new material
Order a sample of the new material and check its compliance with the quality management plan
Use the new material right away since it has the same price and probably a better quality
Update the resource management plan to replace the old material with the new oneCorrect answerSubmit a change request in order to get formal approval for using the new materialOrder a sample of the new material and check its compliance with the quality management planUse the new material right away since it has the same price and probably a better qualityOverall explanationThe project manager should submit a change request to the Change Control Board (CCB) according to the procedures described in the change management plan. The project manager should not use the new material unless the CCB approves the change request. The CCB may decide to further investigate the new material, import the old material from another country, or even change the swimming pool design. In the case of using a new material, the resource management plan should be updated.
Question 64:
After multiple negotiation sessions, all terms and details were agreed upon and the seller finally got the 18-month building project contract for $715,500. What type of contract is used in this scenario?
Time and Material
Fixed Price
Cost Reimbursable
Cost Plus Incentive
Time and MaterialCorrect answerFixed PriceCost ReimbursableCost Plus IncentiveOverall explanationFixed price contracts are used for projects with clear requirements where a price is fixed in return for the seller’s services and/or products. Time and Material (T&M) contracts set a quote for an hourly rate plus the cost of materials instead of quoting a fixed price for the entire project. Cost Reimbursable contracts, on the other hand, reimburse the contractor for the actual costs they incur to provide their services and/or product, plus an additional fee. A Cost Plus Incentive contract, for instance, is a cost-reimbursable contract that incentivizes the contractor to bring their best performance by completing the project under budget or before deadlines.
Question 65:
During the execution of a construction project, the supplier informed the project manager that delivering the new order of steel bars may have a 3-day delay. What should the project manager do next?
Negotiate the delay with the vendor to get it reduced
Look for another vendor
Evaluate the impact of the delay
Update the project schedule
Negotiate the delay with the vendor to get it reducedLook for another vendorCorrect answerEvaluate the impact of the delayUpdate the project scheduleOverall explanationThe project manager should evaluate the impact of the delay before making any decision. A delayed activity doesn’t necessarily result in the whole project delay. For instance, if the activity is not on the critical path and it has a lag of more than three days, then the delay won’t probably have any impact on the project. Therefore, there is no need for negotiating the delay or looking for a new vendor to get the order delivered on time.
Question 66:
After baselining the scope and during project execution, a key stakeholder, who is a member of the Change Control Board (CCB), requested a new service. Taking into consideration that the project manager is convinced that this new service can add value to the project, what should they do?
Implement the change request since the key stakeholder is a member of the CCB
Implement the change request since it will add value to the project
Submit a change request according to the change control system
Record the change request in the change log
Implement the change request since the key stakeholder is a member of the CCBImplement the change request since it will add value to the projectCorrect answerSubmit a change request according to the change control systemRecord the change request in the change logOverall explanationRegardless of the fact that the change was requested by a member of the CCB, the project manager should submit a change request according to the procedures defined in the change control system. This system describes how modifications to project deliverables should be undertaken (PMBOK 7th edition, page 332). The change request is not submitted yet to the CCB, so it should not be recorded in the change log. After submitting it, the change log should be updated to track the status of the change. The project manager should not implement the change without getting the CCB’s formal approval. Being convinced of the change’s value or having the consent of one member of the CCB is not sufficient to move forward with the implementation.
Question 67:
A solar-powered car project is almost finished when the project manager receives an approved change request to replace a defective component of the car batteries. What should the project manager do?
Record the problem in the issue log
Meet with the change control board to discuss the matter
Repair the defective component
Replace the defective component
Record the problem in the issue logMeet with the change control board to discuss the matterRepair the defective componentCorrect answerReplace the defective componentOverall explanationSince the project manager has received an approved change request, they should ensure its appropriate implementation. Since the change request specifically entails the replacement of the defective component, the project manager shouldn’t repair it instead.
Question 68:
A project manager is wrapping up a one-year project. Which of the following activities should be prioritized?
Updating the change log
Releasing the project resources
Completing the knowledge transfer activities
Celebrating the project completion
Updating the change logReleasing the project resourcesCorrect answerCompleting the knowledge transfer activitiesCelebrating the project completionOverall explanationBecause projects are temporary endeavors, most of the acquired knowledge is lost once the project is completed. The project manager should be attentive to knowledge documentation and transfer to allow the organization to gain and retain the knowledge and experience obtained through running projects (PMBOK 7th edition, page 78). Once this activity is completed, a celebration could take place and resources can be released. On the other hand, the change log should be updated to monitor the change requests’ status.
Question 69:
A project manager closed all contracts related to their construction project, except one that concerns setting up security cameras. The only thing left for this contract is to go through a quick inspection by an expert in order to check out wireless connection, night vision, cloud storage, etc. Knowing that the security cameras are working fine and that the project needs to be closed as soon as possible, what should the project manager do?
Close the contract and the project with no inspection
Close the contract, but keep the project open
Close the project, but keep the contract open
Keep the contract and the project open
Close the contract and the project with no inspectionClose the contract, but keep the project openClose the project, but keep the contract openCorrect answerKeep the contract and the project openOverall explanationThe project manager should keep both the contract and the project open until the seller performs the inspection. Closing a project entails conducting several processes and steps including closing out all contracts. Closing a contract in return requires verifying that the seller has delivered their work as predetermined in the contract.
Question 70:
During project execution, the sponsor informed the project manager that the produced water-proof watches should be tested in real underwater conditions in order to fulfill the acceptance criteria. When the sponsor’s advice was applied, 10% of the already produced watches did not pass the test. What should the project manager do next?
Consider this as an internal failure and correct defects without submitting a change request
Consider this as an internal failure and submit a change request to fix the defective products
Consider this as an external failure and correct defects without submitting a change request
Consider this as an external failure and submit a change request to fix the defective products
Consider this as an internal failure and correct defects without submitting a change requestCorrect answerConsider this as an internal failure and submit a change request to fix the defective productsConsider this as an external failure and correct defects without submitting a change requestConsider this as an external failure and submit a change request to fix the defective productsOverall explanationWhen the product quality is tested by the project team and it reveals certain defects, the defective products are considered an internal failure. Therefore, all defects must be addressed and fixed internally before delivering the final product to the customer (PMBOK 7th edition, page 184). A change request must be issued in order to make any sort of change on the project whether it’s a corrective action, preventive action, or a defect repair.
Question 1:
A project manager is facing some struggles after joining a new company; her superiors noticed that during a kick-off meeting, she had difficulty answering questions about how the project fits in with the organization’s objectives. What critical skill is the project manager lacking?
Business acumen
Ways of working
Communication skills
Power skills
Correct answerBusiness acumenWays of workingCommunication skillsPower skillsOverall explanationThe PMI Talent Triangle is made up of three types of skill sets: Ways of Working, Power Skills, and Business Acumen. A project manager possessing business acumen skills should be able to explain the business value of their project and how it aligns with the organization’s goals.
Question 2:
A project manager is assigned to an eco-friendly packaging project. In order to manage involved stakeholders, the project manager starts by analyzing their power, urgency, and legitimacy. Which analysis method is the project manager applying?
Stakeholder cube
Salience model
Power/interest grid
Power/influence grid
Stakeholder cubeCorrect answerSalience modelPower/interest gridPower/influence gridOverall explanationThe salience model is a method used to classify stakeholders and decide who matters more by assessing their power, legitimacy, and urgency. The model allows the project manager to decide the relative salience of a given stakeholder (PMBOK 7th edition, page 171).
Question 3:
A project manager notices that his colleague, who is a fellow project manager, shows up at the office with new high-tech gadgets every day. This raises his suspicions that his colleague might be accepting gifts from hardware vendors who will be bidding on one of their company’s upcoming multimillion-dollar contracts. Which of the following should the project manager do?
Warn the concerned colleague that such gifts aren’t appropriate and leave it at that
Convince his colleague to return the items and stop accepting any gifts from vendors
Directly ask his colleague whether these items were gifts from vendors or he purchased them himself
Report his colleague to the organization so that a conflict-of-interest investigation can take place
Warn the concerned colleague that such gifts aren’t appropriate and leave it at thatConvince his colleague to return the items and stop accepting any gifts from vendorsCorrect answerDirectly ask his colleague whether these items were gifts from vendors or he purchased them himselfReport his colleague to the organization so that a conflict-of-interest investigation can take placeOverall explanationThe best way to act in this situation is to verify facts before taking any action. A violation based only on suspicion should not be reported. The project manager can get the facts right by telling his colleague that he is concerned about how things might appear and simply inquire about the source of the items. As a project manager, you should never jump to conclusions. You should always double-check facts before reporting a conflict-of-interest situation.
Question 4:
A project manager is working on a contract. Now that they completed their contract and closed the project, the project manager is out of work. What type of organizational structure does the project manager work in?
Strong matrix
Projectized
Functional
Weak matrix
Strong matrixCorrect answerProjectizedFunctionalWeak matrixOverall explanationA Project-oriented organization, or a projectized organization, is one in which a considerable part of its processes and activities take place in the form of projects. There is no defined hierarchy; resources are brought together specifically for the purpose of a project. When a project is complete, they either get transitioned to another project or released.
Question 5:
After deciding to invest more in the project management capabilities of the organization, the CEO of Men In, a Men luxury lifestyle gadgets company, established a PMO to ensure compliance with a set of project management standards. What type of PMO is the CEO implementing?
Supportive
Controlling
Directive
Agile
SupportiveCorrect answerControllingDirectiveAgileOverall explanationA controlling PMO focuses on two key areas: Supporting the organization in applying project management practices and Requiring compliance with those practices.
Question 6:
A project manager gets hired to lead the marketing department of a financial institution. The project manager first meets with the project management team in order to review the project portfolio. Next, they focus on learning about the governance framework in place, which is considered to be:
Organizational process assets
Project management framework
Enterprise environmental factors
Agile Manifesto principles
Organizational process assetsProject management frameworkCorrect answerEnterprise environmental factorsAgile Manifesto principlesOverall explanationAn organization’s culture, structure, and governance, are all Enterprise Environmental Factors that can influence a project’s success.
Question 7:
A project manager works for a construction company, which has recently gone through major organizational changes. The organization’s new manager seems to be closely monitoring when employees arrive and leave work. The project manager overhears her saying that she is concerned about the team’s lack of motivation. What type of management style does the new manager exhibit?
Theory X
Theory Y
Theory Z
Theory XY
Correct answerTheory XTheory YTheory ZTheory XYOverall explanationDouglas McGregor defined two models of worker behavior: Theory X and Theory Y. The new manager exhibits the traits of Theory X managers, who believe that the majority of people dislike work, lack motivation, and are in constant need of supervision. Theory X managers adopt an authoritarian style to make their teams work (PMBOK 7th edition, page 160).
Question 8:
The risk manager is collaborating with the project manager to perform a risk analysis. To determine the most likely project completion date based on known risks, they conduct a simulation using the _________________tool to go through thousands of possible scenarios.
Monte Carlo analysis
Decision-tree analysis
Sensitivity analysis
Influence diagrams
Correct answerMonte Carlo analysisDecision-tree analysisSensitivity analysisInfluence diagramsOverall explanationThe project manager and the risk manager are using the Monte Carlo analysis to assess the possible impact of individual project risks and other sources of uncertainty on project goals. For example, if a particular risk arises, what impact will it have on the project schedule and cost? Monte Carlo provides a variety of potential outcomes and probabilities, allowing you to consider the likelihood of different scenarios (PMBOK 7th edition, page 177).
Question 9:
A project manager who follows the servant leadership style is onboarding a new team member who they believe can help fill skill-level gaps in the current project team. The project manager provides the new team member with a copy of the project charter and commits to sending them a copy of ________________, which addresses team values, ground rules, and working agreements.
The employment contract
The resource management plan
The communication management plan
The team charter
The employment contractThe resource management planThe communication management planCorrect answerThe team charterOverall explanationA team charter is a document that is developed in a group setting to clarify team direction while also establishing boundaries. It is created at the team’s forming phase in order to encourage understanding and buy-in. A team charter aligns the team with ground rules, team values, meeting guidelines, working agreements, as well as other group norms (PMBOK 7th edition, page 192).
Question 10:
A project manager is leading a project that has become so large (multiple teams, long duration, and huge budget) that the sponsor has been replaced by a steering committee. What should the project manager do to accommodate this new change?
Acknowledge that the stakeholders’ structure has changed and tailor communication accordingly
Work according to the original plan while keeping in mind that the project may now include additional stakeholders
Hold a meeting with the new steering committee and continue working on the project
Share an updated status report with the new steering committee
Correct answerAcknowledge that the stakeholders’ structure has changed and tailor communication accordinglyWork according to the original plan while keeping in mind that the project may now include additional stakeholdersHold a meeting with the new steering committee and continue working on the projectShare an updated status report with the new steering committeeOverall explanationOn large projects, one sponsor might not be enough. A Steering Committee is established when a large project involves multiple business units, organizations, or individuals who all have a substantial stake in the project’s success and outcomes. The project manager needs to be proactive and respond to this change. The initial communication plan for a single sponsor may not work for a steering committee. In order to ensure effective communication with the committee, the project manager must understand their communication requirements and preferences.
Question 11:
A company must select one of two projects that have the same budget, but different returns and risk levels. Which tool or technique should be used in order to make the right decision?
Decision tree
Tornado diagram
SWOT Analysis
Sensitivity analysis
Correct answerDecision treeTornado diagramSWOT AnalysisSensitivity analysisOverall explanationThe decision tree analysis is used to support the identification and selection of the best course of action among several alternatives. Each of these alternative paths can have associated costs and risks, including both threats and opportunities. The decision tree reveals the expected monetary value of each branch, allowing the determination and selection of the optimal path (PMBOK 7th edition, page 175).
Question 12:
A government contractor wants to keep the costs of the new project they are working on under control while putting the risk on the vendor’s side. Moreover, the contractor wants to ensure that the seller is legally obliged to complete the contract, otherwise, they may face financial liabilities. Which type of contract best conforms to the contractor’s needs and represents the least risk for them as a buyer?
Fixed-price
Time & Materials (T&M)
Cost Plus Incentive Fee (CPIF)
Cost-reimbursable
Correct answerFixed-priceTime & Materials (T&M)Cost Plus Incentive Fee (CPIF)Cost-reimbursableOverall explanationFixed price contracts present the least risk for the buyer. A fixed-price contract is one in which the payment does not depend on the spent time or used resources. It involves setting a fixed price for the service, product, or result defined in the contract (PMBOK 7th edition, page 191).
Question 13:
A project manager is leading a small team of developers using project management software that includes a Kanban board. After receiving many questions from team members on how to create, review, and validate tasks or issues, the project manager decides to create the following chart. This chart is called:
Pareto chart
Flowchart
Context diagram
Scatter diagram
Pareto chartCorrect answerFlowchartContext diagramScatter diagramOverall explanationA flowchart (also referred to as a process map, progress flow, and progress flow diagram) graphically displays the logical order of a process (PMBOK 7th edition, page 189). A Pareto chart is displayed as a histogram, representing the most serious causes of an error, while a scatter diagram is used to determine the correlation between two variables. Both diagrams don’t show a task or issue’s management process flow. Context diagrams, on the other hand, are used to visually demonstrate how a business process, other systems, and people, all interact. Context diagrams can include a business process as one of its components, but they can’t provide insight into a particular process flow.
Question 14:
A project manager is assigned to a 3D home design project. After setting the time of daily standup meetings, the project manager faces some issues since not all of the remote team members find the meeting time convenient. Which conflict resolution technique should the project manager use to handle time zone differences?
Avoid
Accommodate
Compromise
Withdrawal
AvoidAccommodateCorrect answerCompromiseWithdrawalOverall explanationSince the time zone difference is beyond anyone’s control, a compromise should be made to bring some degree of satisfaction to all parties. Working towards a compromise is perceived as the best outcome, even if no one is completely happy with the final resolution (PMBOK 7th edition, page 168).
Question 15:
When conducting remote resource hiring, what is the best way to quickly collect data from candidates to analyze and compare?
Video recordings
Workshops
Questionnaires and surveys
Live interviews
Video recordingsWorkshopsCorrect answerQuestionnaires and surveysLive interviewsOverall explanationSurveys and questionnaires are written sets of questions designed to quickly gather data from a large number of respondents who are usually geographically dispersed.
Question 16:
A project manager that works at Tunitalent, an innovative design, web, and marketing agency, suggests creating a dropshipping e-commerce project since it was a trendy and profitable project. However, her manager refuses since Tunitalent lacks experience in this field. Being excited to go through such a new experience and confident in her ability to successfully manage the project, what should the project manager do to persuade her manager to select the project?
Conduct a what-if analysis
Calculate the Return On Investment (ROI)
Calculate the Net Present Value (NPV)
Conduct a cost-benefit analysis of the business case
Conduct a what-if analysisCalculate the Return On Investment (ROI)Calculate the Net Present Value (NPV)Correct answerConduct a cost-benefit analysis of the business caseOverall explanationTo persuade an organization to select your project, the business case should be subjected to a cost-benefit analysis in order to illustrate the benefits of implementing the project by determining its anticipated financial gains and profitability. The Cost-Benefit Analysis is more comprehensive than the Net Present Value (NPV) and the Return On Investment (ROI), as it attempts to quantify both tangible and intangible costs and benefits (PMBOK 7th edition, page 175).
Question 17:
A project manager is running a project with remote and local resources. The remote team complains that they are not getting enough information about what’s going on with the project, which has caused them to do some rework. The project manager schedules a conference call with the two teams, and he decides to switch to a sophisticated enterprise chat platform to optimize communication. Which conflict resolution technique did the project manager use?
Collaborate
Compromise
Force
Smooth
Correct answerCollaborateCompromiseForceSmoothOverall explanationThe Collaboration/problem-solving conflict resolution technique is based on incorporating multiple viewpoints and insights from differing perspectives. It necessitates a collaborative mindset and open communication to achieve consensus and commitment to an agreement. This approach aims to reach a win-win situation for all involved parties (PMBOK 7th edition, page 22).
Question 18:
To better understand how the project’s system flows, depicting the scope in abstraction, and enabling stakeholders to communicate about it, and what lies beyond its boundaries, a project manager uses a visual representation of how people and other systems interact with a new system. Which of the following tools does the project manager use?
Affinity Diagram
Flowchart
Context diagram
Influence diagram
Affinity DiagramFlowchartCorrect answerContext diagramInfluence diagramOverall explanationContext diagrams are visual depictions of the product scope, displaying the business system and how it connects and interacts with other systems. It presents the inputs and outputs of the system, as well as its main players, including organizations, other business systems, end-users, etc.
Question 19:
Realizing that her project is not going according to estimations, a project manager suspects that it might be due to Student Syndrome. What does this syndrome imply?
People who proceed with their studies during their professional careers but are unable to balance both
People who begin to apply themselves only at the last possible moment before the deadline
People who experience a learning curve whenever they are working on a project
Professional project managers who consider themselves continuous learners
People who proceed with their studies during their professional careers but are unable to balance bothCorrect answerPeople who begin to apply themselves only at the last possible moment before the deadlinePeople who experience a learning curve whenever they are working on a projectProfessional project managers who consider themselves continuous learnersOverall explanationStudent Syndrome is a term used in project management to highlight the ever-increasing habit of putting off work till the last minute, while initially working at a very relaxed pace.
Question 20:
A project manager is managing a project using the Scrum framework. The project manager receives a call from the product owner asking for a meeting with the team to discuss the possible approaches to implement user stories and make some initial size estimations. What type of meeting is the product owner referring to?
Sprint planning
Story mapping
Backlog refinement
Brainstorming
Sprint planningStory mappingCorrect answerBacklog refinementBrainstormingOverall explanationBacklog refinement provides a chance for the product owner to discuss and address stories’ requirements with the team. This can involve discussing requirements, potential approaches, and even estimations in order to end up with a clear vision of how to approach stories (PMBOK 7th edition, page 179).
Question 21:
Constraints and assumptions are important for projects. They should be identified, controlled, and monitored continuously. Wrong assumptions or constraints can impact the project. For instance, when a constraint turns out to be wrong, it affects the project:
Positively
Negatively
Depends on the constraint
Depends on the project
Correct answerPositivelyNegativelyDepends on the constraintDepends on the projectOverall explanationConstraints are limitations imposed on a project, such as the scope, schedule, quality, budget, risks, or resources. If assumptions end up being false, it is bad news for the project. However, if constraints turn out to be false, it is a good thing, as it means that the project will be positively affected because constraints are limitations imposed on the project.
Question 22:
Three manufacturing lines are producing 5 mm diameter cylindrical steel bars. In order to perform a quality inspection, the project manager takes 10 random bars from each line. The following are the inspection results in mm measurements.
The results of Line 1 can be described as:
Accurate
Precise
Both accurate and precise
Neither accurate nor precise
AccurateCorrect answerPreciseBoth accurate and preciseNeither accurate nor preciseOverall explanationThe results are precise because all measurements are close to 4.45mm (+ or - 5mm). Precision entails delivering end-products with similar dimensions, which may or may not be close to the required dimensions. Precise measurements are not necessarily close to the target value; they’re just close to one another. Accuracy, however, implies creating products with close dimensions to requirements.
Question 23:
A project manager works for a big matrix-structured organization where communication channels are complex and cross-functional. On a daily basis, the project manager communicates with the executive team and reports back to the manager. What type of communication does this describe?
Horizontal communication
Vertical communication
Parallel communication
Triangular communication
Horizontal communicationCorrect answerVertical communicationParallel communicationTriangular communicationOverall explanationBased on the direction of the hierarchies within the organization, there are two basic types of communication: Horizontal and Vertical. In horizontal communication, the project manager communicates with their peers or people on their organizational and hierarchical level. However, in vertical communication, communication flows from a lower level to a higher level and vice versa, as described in the question. “Parallel” and “triangular” communication are made-up terms.
Question 24:
A project manager is having trouble getting one of the team members to complete his assigned tasks. The project manager invites the concerned member over to watch a football game. After the game, the project manager talks with the team member about his performance issues. What type of communication is the project manager using?
Para-lingual
Visual
Formal verbal
Informal verbal
Para-lingualVisualFormal verbalCorrect answerInformal verbalOverall explanationThe project manager is having an informal discussion with the team member. Hallway conversations, cubicle chatting, networking, and all other types of informal communication do not hold any official significance.
Question 25:
When the execution of a rebranding project was completed, several key stakeholders, including the sponsor, were reluctant to accept deliverables and close the project. What should the project manager do in this situation? (Select three)
Identify and resolve any open issues. Then, be firm on formal closure.
Formally close the project. Stakeholders will get well-acquainted with the new brand by that time.
Identify and openly discuss the reasons for reluctance.
Invite earnest feedback from all sides and try to identify any misunderstanding.
Correct selectionIdentify and resolve any open issues. Then, be firm on formal closure.Formally close the project. Stakeholders will get well-acquainted with the new brand by that time.Correct selectionIdentify and openly discuss the reasons for reluctance.Correct selectionInvite earnest feedback from all sides and try to identify any misunderstanding.Overall explanationThe project manager should not close the project when key stakeholders are not satisfied. They should try to discuss, identify, and resolve any issues or misunderstandings first.
Question 26:
A project manager believes that being an active listener is not easy. She considers active listening to be more of an art than a skill, so she often encourages her team members to use a checklist of the key elements of active listening before any important meeting with stakeholders. Which of the following are regarded as elements of active listening? (Select three)
Making eye contact
Paraphrasing
Interpreting information
Interrupting when appropriate
Correct selectionMaking eye contactCorrect selectionParaphrasingCorrect selectionInterpreting informationInterrupting when appropriateOverall explanationActive listening is a skill that can be acquired and developed through practice. Instead of passively receiving the speaker’s message, active listening entails paying close attention to what is being said. Active listening involves allowing others to completely express their ideas without interrupting them, asking questions to get a clear understanding of the situation as well as the conveyed ideas, focusing on what is being said by maintaining comfortable eye contact, remaining open-minded about others’ opinions, employing paraphrasing skills and feedback, and keeping an eye on non-verbal signs such as the body language and facial expressions of the speaker.
Question 27:
The final decision on which projects are selected for execution is generally made by the company executives. However, a project manager was always able to use their experience to assist the organization’s decision-makers in choosing the best project through the use of the suitable benefit measurement project selection method. Which of the following is not a benefit measurement method?
5 Whys
Internal Rate of Return
Scoring model
Discounted cash flow
Correct answer5 WhysInternal Rate of ReturnScoring modelDiscounted cash flowOverall explanationThe Five whys is not a benefit measurement method; it’s rather an iterative interrogative technique used to investigate the cause-and-effect relationships in order to resolve a particular problem. The most common Benefit Measurement Methods are the Cost-Benefit Ratio, Economic Model, Payback Period, Discounted Cash Flow, Net Present Value, Scoring Models, Internal Rate of Return, and Opportunity Cost.
Question 28:
A project manager for Steel Foundations has been brought on to the project in the very early stages and has been asked to write its charter. Over the past week, the project manager met with a number of stakeholders, received their input, and is now ready to have the charter signed. Who is responsible for signing the project charter?
Project Sponsor
Senior Management
Project Manager
Project stakeholders
Correct answerProject SponsorSenior ManagementProject ManagerProject stakeholdersOverall explanationProjects get authorized by someone external to the project such as the sponsor, PMO, or portfolio steering committee (PMBOK 6th edition, page 77). Unless the Project sponsor is part of Senior Management, the project charter should be signed by someone with the authority to assign project resources and name the project manager, i.e., the project sponsor. The project manager or stakeholders may under no circumstances sign the charter to authorize the project.
Question 29:
A project manager’s authority and power vary depending on whether they work in a functional, matrix, or projectized organization. Once appointed as a project manager, inherent forms of legitimate power will be conveyed to them. There are three forms of legitimate power:
Absolute, direct, and indirect
Formal, informal, and persuasive
Formal, reward, and direct
Formal, reward, and penalty
Absolute, direct, and indirectFormal, informal, and persuasiveFormal, reward, and directCorrect answerFormal, reward, and penaltyOverall explanationThe three types of legitimate power are formal power, reward power, and penalty power.
1) Formal or legitimate power stems from the project manager’s position. The assumption that a person has a formal right to make demands gives rise to this form of power. For instance, a CFO holds legitimate authority over an intern who works for them because they are higher in the organizational hierarchy.
2) Reward power comes from giving rewards and it is attached to the formal authority of the project manager. This type of power originates from the ability to compensate another person as it is known that rewards are desirable, and team members tend to show their support since they think that they will be rewarded if they perform well. Non-monetary rewards such as recognition, training recommendations, or valuable assignments are also common. Criteria for reward should be fair, transparent, and possible for all.
3) Penalty or coercive power is the ability to penalize team members. The project manager gains support because they are capable of directly or indirectly subjecting their personnel to penalties. Penalty power is usually derived from the same sources as reward power, with one being a necessary condition for the other.
Other forms of power include Expert power, Referent power, etc.
Question 30:
Fabrice is an organization operating in the Oil and Gas industry. They had signed a subcontracting agreement with SPM Inc. to get provided with experts, technical know-how, and mechanical spare parts. Since Fabrice’s projects consist of building innovative high-tech machines, the exact description of the work involved is not clear. In this scenario, what kind of contract should they sign with SPM Inc.?
Fixed Price Incentive Fee (FPIF)
Cost Plus Award Fee (CPAF)
Time & Materials (T&M)
Firm Fixed Price (FFP)
Fixed Price Incentive Fee (FPIF)Cost Plus Award Fee (CPAF)Correct answerTime & Materials (T&M)Firm Fixed Price (FFP)Overall explanationWhen you need to hire technical experts, you should use a Time & Materials contract. A T&M contract is a hybrid of fixed price and cost-reimbursable contracts. This type of contract is suitable for projects with no precise scope of work, or when it’s hard to determine the required duration and material to get the job done (PMBOK 7th edition, page 191).
Question 31:
A project manager was assigned to lead a big project. Since this project is really important for their organization, management does not want any delay in completion. After getting the project charter signed, the project manager started identifying and categorizing stakeholders using different data representation tools. Which of the following tools can the project manager use? (Select three)
Brainwriting
Stakeholder cube
Direction of influence
Salience model
BrainwritingCorrect selectionStakeholder cubeCorrect selectionDirection of influenceCorrect selectionSalience modelOverall explanationData representation techniques include the stakeholder cube, direction of influence, and salience model. The stakeholder cube adds a third analysis dimension to the impact/influence grid. The salience model is used to assess stakeholders’ power, urgency, and legitimacy (PMBOK 7th edition, page 171). The direction of influence, on the other hand, is used to categorize and classify stakeholders on the basis of their influence on the project. Brainwriting is a brainstorming technique for stimulating creativity.
Question 32:
A project manager decides to obtain her PMP certification in two months. She creates the following exam preparation plan: she will study for 4 weeks, take mock practice tests in weeks 5 and 6, and then take the 7th week off before sitting for the exam in week 8. At the end of week 5, the project manager gets caught in an accident that keeps her hospitalized for one week. To make up for the lost time, the project manager had to cancel her week off, and work on mock tests during weeks 6 and 7 instead of weeks 5 and 6. This is an example of:
Adaptability
Risk mitigation
Workaround
Corrective action
AdaptabilityRisk mitigationCorrect answerWorkaroundCorrective actionOverall explanationWhen an unidentified risk occurs, it is addressed through a workaround. A workaround is an unplanned risk response to deal with unexpected risks as well as passively accepted risks during project execution (i.e. when there is no predetermined risk response plan put in place).
Question 33:
In agile, what is the planning poker technique used for?
Estimating how much effort is needed to complete tasks
Estimating how much work is left in the sprint
Testing the project and identifying blockers
Measuring the sprint velocity
Correct answerEstimating how much effort is needed to complete tasksEstimating how much work is left in the sprintTesting the project and identifying blockersMeasuring the sprint velocityOverall explanationPlanning poker is a card-based technique that is mostly used for estimating project activities. It is a consensus-based estimating technique (PMBOK 7th edition, page 58). It can be used with story points, ideal days, or any other estimation unit. The estimation is done using poker cards. Team members discuss the feature, asking the product owner any questions they might have. Then, privately, each team member picks out one card that presents their estimate. All cards should be then revealed at once. If all team members select the same value, it’s set as the final estimate. Otherwise, a discussion of the different opinions and estimates will take place again before re-estimating the feature or task again.
Question 34:
You are simultaneously managing six projects in the company. Two projects are of a similar type, while the other four are entirely different. You work as a ______________.
Portfolio manager
Program manager
Project manager
Program coordinator
Correct answerPortfolio managerProgram managerProject managerProgram coordinatorOverall explanationIn portfolio management, a group of related or non-related programs and projects are managed in coordination (PMBOK 7th edition, page 244). Portfolio management is intended to reduce the gap between strategy and implementation by aligning projects to attain business objectives.
Question 35:
During the iteration review, the project team was demonstrating new features to the Product Owner. The product owner was resting his hands on the table with a relaxed and open posture, while occasionally fiddling with his pen or coffee mug without looking directly at the speaker. What kind of communication is the product owner using? (Select two)
Paralingual communication
Active listening
Implicit message
Non-verbal communication
Paralingual communicationActive listeningCorrect selectionImplicit messageCorrect selectionNon-verbal communicationOverall explanationNon-verbal communication is used to convey implicit messages. It includes gestures, facial expressions, and paralinguistics such as voice tone or volume, body language, personal space, eye contact, touch, and appearance. These non-verbal signals can provide additional information and meaning to verbal communication. Paralingual communication is non-verbal, but it’s not the right answer because the product owner didn’t communicate any vocal messages. The scenario doesn’t describe active listening either, since the product owner is not interacting or paying attention to the demonstration.
Question 36:
While traditional project management follows predefined phases and sticks to the predetermined scope, Agile project management approaches:
Encapsulate analysis, design, implementation, and test within an iteration
Involve documenting, estimating, and sequencing each planned activity in detail
Use Gantt charts along with well-defined activities, responsibilities, and time frames
Map the iteration backlog into a Work Breakdown Structure (WBS)
Correct answerEncapsulate analysis, design, implementation, and test within an iterationInvolve documenting, estimating, and sequencing each planned activity in detailUse Gantt charts along with well-defined activities, responsibilities, and time framesMap the iteration backlog into a Work Breakdown Structure (WBS)Overall explanationThe iterative method is the heart of the Agile development process. Each iteration generates a piece of the product until the final product is fully completed and delivered.
Question 37:
The burnup and burndown charts are tools used by Scrum teams to get an overview of a sprint’s work development. Both charts are primarily used for:
Identifying technical issues
Tracking project progress
Project retrospective
Sprint planning
Identifying technical issuesCorrect answerTracking project progressProject retrospectiveSprint planningOverall explanationThe burnup and burndown charts are created to identify the amount of workload achieved and how much remains to be completed (PMBOK 7th edition, page 188). In a burndown chart, the line goes downwards, while in a burnup chart, the line goes upwards, which in both cases illustrates the team’s progress. When burndown or burnup charts reveal issues related to sprint progress, which can be due to both technical or non-technical reasons, a self-organizing team should take corrective actions. In their next retrospective meeting, the team needs to reflect on what happened and how to better handle issues in the future.
Question 38:
A project manager is implementing an internal design project. She needs a driller with a rental cost of $25 per day, which she finds quite high. Since she will be using it for a long duration, a team member suggests buying a driller for $500. What is the minimum number of rental days before it becomes more advantageous to buy a driller?
2
5
10
20
2510Correct answer20Overall explanationAfter 20 days, the total cost of rent will be equal to the equipment’s price, i.e., $500 = 20 days x $25.
Question 39:
A project manager is assigned to lead a new project that requires applying a hybrid development approach. Therefore, management enrolled the project manager in a training to help them learn how to combine agile principles with predictive techniques. Which aspect of the PMI talent triangle does this training target?
Business Acumen
Power Skills
Working Methods
Ways of thinking
Business AcumenPower SkillsCorrect answerWorking MethodsWays of thinkingOverall explanationWorking Methods (also known as Ways of Working) are the skills that the project manager is developing through the training. The other two aspects of the PMI talent triangle are Power Skills and Business Acumen. Ways of Thinking is a made-up term.
Question 40:
In order to predict the project’s future performance based on its current performance, the project manager can use all of the following methods for forecasting purposes: (Select three)
Scenario building
Simulation
Time series method
Variance analysis
Correct selectionScenario buildingCorrect selectionSimulationCorrect selectionTime series methodVariance analysisOverall explanationExamples of forecasting methods are time series, scenario building, and simulation, as well as regression analysis, expert opinion, and causal/econometric methods. Variance analysis is not a forecasting method. It is the quantitative measurement of the difference between planned and actual behavior.