M2Q1 A Project Manager wants to estimate the duration of an activity. He asks a few team members. One member says it can be done in 5 days. The other member in 15 days. The third member says in 35 days.
Using the triangular estimating technique, what is the duration of the activity?
18 days
15 days
13 days
21 days
Correct answer
18 days
Feedback
Using the Triangular formula: [Pessimistic estimate + Most likely estimate + Optimistic estimate]/3 = Therefore, [5 + 15 + 35]/3 = 18.
M2Q2 An organization has moved from traditional to agile methods and is now conducting its first agile project. The newly appointed product owner would like the team to prioritize the features as soon as possible so they can start the sprints immediately.
What should the project manager do in this scenario?
Inform the team to prioritize the features and store them in the product backlog
Educate the product owner on the benefits of having him prioritize the features
Work with the team to prioritize the features and store them in the product backlog
Inform the product owner that prioritizing the feature is not needed
Correct answer
Educate the product owner on the benefits of having him prioritize the features
Feedback
On an agile project, it is important for the product owner to prioritize the features and store them in the product backlog. If the product owner refuses, then the project manager should educate them on the benefits of doing this.
M2Q3 A smartphone company reports that customers are complaining that a new phone is very slow to boot, while others are saying it boots times are okay. A Project Manager needs to determine if something needs to be changed during the production of the smartphone.
Which tool or technique can the Project Manager use for this?
Cost of Quality
Affinity diagram
Control chart
Histogram
Correct answer
Control chart
Feedback
Control charts are used to determine whether or not a process is stable or has predictable performance.
M2Q4 A product deliverable has failed acceptance testing. The sponsor says the deliverable was not created as per the original scope.
What should the project manager do to avoid this in the future?
Have the team create the scope statement
Review the change management plan
Ensure a scope management plan is created
Have the team demo the finished product
Correct answer
Ensure a scope management plan is created
Feedback
A scope management plan documents how the project and product scope will be defined, validated and controlled.
M2Q5 A customer is unwilling to accept the deliverable since it was not functioning the way they expected it. A Project Manager is evaluating what could have been done differently to avoid this.
What should the Project Manager have done?
Assess and evaluate the scope management plan
Create the work breakdown structure (WBS) dictionary
Ensure that the quality metrics are defined
Review the requirements documentation
Correct answer
Ensure that the quality metrics are defined
Feedback
Quality metrics are a description of a project or product attribute and how to measure it.
M2Q6 A team working on a hybrid project is frustrated with the customers due to the constant changing of the project scope. When the team completes a release, the customers will then ask for the work to be redone. This has led to major delays in the project schedule.
What can the project manager do to prevent this from happening while the project is progressing?
Have the team invite the customers to the daily standup meetings and take feedback from them
Ensure customers are invited to the sprint review meeting to give feedback
Inform the project sponsor about this issue
Inform the customers that changes should not be made after the work has been completed
Correct answer
Ensure customers are invited to the sprint review meeting to give feedback
Feedback
If their constant changes to a deliverable, it would be best to invite the customers or have them participate more in the Sprint review meetings to give more feedback as it is being built.
M2Q7 The project manager created a charter for a new software project. A senior stakeholder feels this project will have a negative impact on her employees.
What should the project manager do first?
Request for the project sponsor to speak with this stakeholder
Have the stakeholder meet with the team for a better explanation of the project
Document as a risk in the risk register
Have a meeting with the stakeholder to review the project objectives
Correct answer
Have a meeting with the stakeholder to review the project objectives
Feedback
The first thing the PM needs to do is to make sure the project objectives are well understood before taking any action.
M2Q8 A project manager has been assigned to an ongoing project in the planning phase. The WBS has already been decomposed, but the project manager feels that more information will be needed in order to complete the project.
What will the project manager use to further decomposed the work?
Scope statement
WBS dictionary
Requirements management plan
Requirements documentation
Correct answer
WBS dictionary
Feedback
The best document for the user would be to WBS dictionary since it has detailed information about some of the work. After reviewing the WBS, the project manager can then determine what additional detailed meeting is needed.
M2Q9 A company is creating a new technology product. The project manager has verified that the component work packages have been well-defined.
Which estimating technique should the project manager use to obtain an accurate cost estimate of the deliverables?
Analogous
Three-point
Bottom-up
Parametric
Correct answer
Bottom-up
Feedback
Bottom-up estimating is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS.
M2Q10 A key stakeholder is giving the team a hard time and is always arguing with team members. The stakeholder feels like no one understands him and knows how to communicate. If the issue is not resolved immediately, it could lead to the termination of the project.
What should the project manager do in this situation in regards to the team?
Inform them not to communicate with the stakeholder going forward
Have the stakeholder communicate with them through email only
Train the team on emotional intelligence
Inform the team to try to communicate with the stakeholder as the project is nearing completion
Correct answer
Train the team on emotional intelligence
Feedback
This solution would be to train the team on emotional intelligence so they can better communicate with the stakeholder and hopefully resolve this issue.
M2Q11 A project is completing the deliverable and a key stakeholder will be unavailable for a few weeks during the project. This stakeholder will be the person to approve the deliverable.
What should the project manager do first?
Ensure that the issue log is updated
Request a replacement during the stakeholder’s absence
Setup a meeting with the sponsor to evaluate the situation
Finish the project and have another stakeholder approve the deliverable
Correct answer
Ensure that the issue log is updated
Feedback
The first thing the PM needs to do is to update the issue log and communicate this to the other stakeholders.
M2Q12 A small team is working virtually on a hybrid project and is having a difficult time being committed to the project. This has led to work being incomplete and defects in completed work.
What should the project manager do first in this situation?
Speak with each team member individually to determine the root cause of this issue
Meet with the team as a whole and inform them of this issue and have them resolve it immediately
Meet with the project sponsor and inform him of this issue
Remove the team members that are having issues and replace them with more motivated members
Correct answer
Speak with each team member individually to determine the root cause of this issue
Feedback
The best solution would be to meet with each member individually since it is a small team to better understand what is causing this. Then work with the team to find a resolution.
M2Q13 A hybrid project has been executed and a new regulatory law has been passed that mandates immediate compliance. This law will increase the project’s scope and cost schedule.
What should the project manager do first?
Update the risk register
Ensure the project management plan is up to date
Escalate this to the senior company management
Implement a change request
Correct answer
Implement a change request
Feedback
Since compliance is mandatory and it impacts the scope, and cost, a change request needs to be submitted.
M2Q14 A deliverable on the project’s critical path is behind schedule. The cost performance index (CPI) is 1.3. The project manager wants it back on schedule.
What is the most likely outcome for this deliverable?
There will be activities performed in parallel
There will be a revised scope
There will be an increase in costs and risks
There will be rework
Correct answer
There will be an increase in costs and risks
Feedback
The Cost Performance Index (CPI) is above 1. Therefore the project is spending money at a rate lower than planned. It would be best to crash this deliverable to complete it sooner. This will generally increase cost and risk.
M2Q15 A scrum team is having a difficult time staying on schedule. The PMO is concerned that this delay can cause the project to lose value. The project manager realizes that this is caused by team members not having the correct skills.
What should the project manager do in this situation?
Meet with the team and inform them of the deadlines they have to meet
Increase the project schedule to account for the delays
Find the correct training for the team members that needs it
Inform the PMO this is normal on a project
Correct answer
Find the correct training for the team members that needs it
Feedback
The project manager should ensure the team members are adequately trained while working on a project.
M2Q16 The project manager discovers that a senior stakeholder is asking a team member for project information. This is causing an issue with the team completing their work.
Which should the project manager do first?
Review the stakeholder register
Refer to the project management information system (PMIS)
Send the stakeholder the information yourself
Review the communications management plan
Correct answer
Review the communications management plan
Feedback
A communications management plan is established to ensure that the appropriate messages are communicated to stakeholders in various formats and various means as defined by the communication strategy.
M2Q17 The agile project team has complained that the product owner has prioritized the product backlog with everything as being critical. The team is not sure what to work on next.
What should the project manager do in this situation?
Have the team choose what is the most important to start with first
Have the team reprioritize the entire product backlog
Have the team prioritize the work based on what can be finished the fastest
Meet with the product owner and educated him on why the product backlog should be reprioritize based on value
Correct answer
Meet with the product owner and educated him on why the product backlog should be reprioritize based on value
Feedback
Prioritization of the product backlog should be done by the product owner, not the product team. It would be best for the project manager to educate the product owner on the values of doing this.
M2Q18 An organization has signed a fixed price contract with the vendor to upgrade its current network. The project manager thinks that due to certain network components, the project might be delayed by more than two months. The vendor has stated this will not happen.
What should the project manager do in this situation?
Update the procurement management plan with this potential issue
Update the risk register and risk responses
Implement a change request to extend the project schedule by two months
Hire a new vendor on standby in case the vendor delays the project
Correct answer
Update the risk register and risk responses
Feedback
Since this is a risk that can affect the project schedule, the project manager should add the risk to the risk register with a corresponding response.
M2Q19 A project manager is working with a customer who submitted over 10 new scope changes for an existing software development project. The project manager feels this is unnecessary due to the type of software being made.
What should the project manager do next?
Hold a meeting with the customer to request that the number of new requests is reduced
Define the number of changes with the sponsor
Organize a meeting with the team to set expectations
Analyze the scope management plan
Correct answer
Analyze the scope management plan
Feedback
The scope management plan documents how the project and product scope will be defined, developed, monitored, controlled and validated. The document provides guidance and direction on how the scope will be managed throughout the project.
M2Q20 A project manager is working on a large project for a global corporation. After conducting a stakeholder analysis, the project manager decides the best way to communicate would be through virtual meetings. The sponsor would prefer emails since it is what the organization uses the most.
What should the project manager do in this situation?
Inform the team they should use emails going forward
Meet with the project sponsor and educate him on the benefits of virtual meetings over emails
Change the communication management plan to reflect emails
Ask the PMO what would be best for this project
Correct answer
Meet with the project sponsor and educate him on the benefits of virtual meetings over emails
Feedback
The project manager should always be willing to educate stakeholders on the benefits of using communication methods that are better suited to the project.
M2Q21 A project is 9 months into execution. The Project Manager computes that the schedule performance index (SPI) is .60. The SPI was .9 in month 1, .8 in month 4 and .7 in month 8.
What should the project do in this situation?
Issue a change request
Hire new team members to complete the work faster
Crash the project schedule
Utilize the management reserve
Correct answer
Issue a change request
Feedback
Since the project is behind schedule and the trend analysis shows that this will continue, the best course of action is to update the project management plan with a new realistic schedule.
M2Q22 As a project is being implemented. A key stakeholder communicates to the project manager that the requirements of the project may have changed. These changes may significantly impact the project scope.
What should the project manager do in this situation?
Update the risk register and identify risk responses
Redo the scope statement
Use the contingency reserve and update the risk mitigation plan
Compute the current earned value management (EVM)
Correct answer
Update the risk register and identify risk responses
Feedback
These new requirements may pose additional risks. These risks need to be documented and appropriate responses need to be identified.
M2Q23 The agile project has just released a minimum viable product (MVP) to the customers and the company. A few of the customers have complained that it is lacking a large number of features and is not very useful.
What should the project manager do first in this scenario?
Pullback the release until it has the right amount of features
Inform the team to add the required features immediately
Educate the customers on the value of an MVP
Ask the product owner to meet with the customers to discuss this issue
Correct answer
Educate the customers on the value of an MVP
Feedback
The best-case scenario would be to educate the customers on the usage and value of an MVP and why it lacks certain features.
M2Q24 A project has the following characteristics:
-US$5 million budget
-Planned value of US$635,000
-Actual cost of US$655,000
-Earned value of US$545,000
Which statement is true about the current status of the project?
The project is ahead of schedule and under budget
The project is behind schedule and over budget
The project is ahead of schedule and over budget
The project is behind schedule and under budget
Correct answer
The project is behind schedule and over budget
Feedback
CV = EV - AC: 545 - 655 = -110, SV = EV - PV: 545 - 635 = -90, Negative cost variance means the project is over budget, Negative schedule variance means the project is behind schedule.
M2Q25 A recent change to safety regulations will be implemented soon across the entire country. After analyzing the project management plan, the project manager realizes the project will not be in compliance.
What should the project manager do next?
Meet with the legal department and implement a change request to update the project plan
Add safety regulations as a risk to the risk register
Meet with the legal department and seek guidance
Update the project management plan and continue working
Correct answer
Meet with the legal department and implement a change request to update the project plan
Feedback
Since this is a regulation, the project manager should meet with the legal department and determine how to implement this across the project and then implement the change request.
M2Q26 A project has been executed. The project must be completed fast. The project manager needs to quickly assign resources to meet project requirements.
What should the project manager do next?
Create the resource management plan
Conduct workshops
Acquire and train a team
Host a webinar
Correct answer
Acquire and train a team
Feedback
Once the project team is established, the project manager can then start developing them.
M2Q27A new project manager is assigned to a new hybrid project and wants to start guiding the team toward project success. This project has been ongoing for the last three months.
What should the new project manager do first?
Review the project charter to understand the goals and deliverables
Review the lesson learned register by the former project manager
Stop the project until he understands all the project objectives
Review the project schedule to determine if extra time is required
Correct answer
Review the project charter to understand the goals and deliverables
Feedback
The Project Charter defines many aspects of the project which are critical to the new project manager’s understanding of the project strategy, as well as the tactical execution.
M2Q28 The project manager working on an agile project has received many emails from team members complaining that other members are interrupting them and causing them to delay their work. This is happening on a daily basis and may affect the project schedule.
What can the project manager do to resolve this?
Have the team conduct the daily standup meeting more than once per day
Meet with all team members and find out the root cause of this issue and work with the team for a solution
Meet with each member individually and inform them not to interrupt each other
Coach the team on the benefits of solving problems on their own
Correct answer
Meet with all team members and find out the root cause of this issue and work with the team for a solution
Feedback
Once there is an issue on a project with team members, it is best for the project manager to meet with the team and facilitate them to find the main cause of an issue and to resolve that issue.
M2Q29 A Project Manager receives a list of assumptions, a few restrictions from the PMO and a preliminary scope from the sponsor.
What should the project manager do next?
Review or create the business case
Build the project team
Build the project schedule
Ensure project charter approval
Correct answer
Review or create the business case
Feedback
The business case should be done before a charter can be written.
M2Q30 A project manager wants to estimate the duration for the creation of a complex function. A subject matter expert says the function can be done as early as 20 days, as late as 70 days and will most likely take 30 days.
What is the estimated development duration for this function?
20 Days
30 Days
70 Days
35 Days
Correct answer
35 Days
Feedback
Using 3 point estimating: Beta Estimate = (Optimistic + (4 X Most Likely) + Pessimistic)/6 = (20 + (4*30) + 70)/6 = 35 days.
M2Q31 A project manager joins a project with a worldwide distributed virtual team and a budget that is fixed and a scope that is driven by certain regulations.
What should the Project Manager do to avoid any scope creep?
Ask that all team members report all work to the project manager only
Have teams do weekly meetings
Put any changes to scope through a formal approval process
Don’t allow stakeholders to directly interact with the members
Correct answer
Put any changes to scope through a formal approval process
Feedback
Scope creep can be avoided by adherence to the agreed upon change management process.
M2Q32 The project manager and the team are currently reviewing the risk register and the corresponding responses. They have determined that most of the severe risks are no longer a threat to the project.
What should the project manager and the team do with the other less severe risks?
Remove them from the risk register since they will not have much impact
Remove contingency reserves from the project plan
Inform the project sponsor of this accomplishment
Reevaluate the risks and reprioritize the risk register
Correct answer
Reevaluate the risks and reprioritize the risk register
Feedback
The best course of action would be to reevaluate the risk and then reprioritize the risk register. Risk consistently changes on a daily basis and reevaluation should be done consistently throughout the project.
M2Q33 A project manager has updated the work performance information of a hybrid project with an SPI of 1.2 and CPI of .78.
What should the project manager review on this project?
Review the budget since the project is over budget and ahead of schedule
Review the schedule since the project is behind schedule and under budget
Review both the budget and schedule since both are not as planned
Informed the sponsor the project is progressing as planned
Correct answer
Review the budget since the project is over budget and ahead of schedule
Feedback
CPI and SPI should both be 1 and over. Any value under 1 would indicate the project is over budget or behind schedule.
M2Q34 A project is behind schedule by 20% due to an issue with a stakeholder giving wrong requirements. The project manager issued a change request, but the stakeholder claims he didn’t know about this change request.
What should the project manager do next?
Review the communications management and stakeholder engagement plans
Approve the change request
Meet with the project sponsor to better understand stakeholders communication needs
Update the communications management plan
Correct answer
Review the communications management and stakeholder engagement plans
Feedback
There is a communication issue on this project. The PM should first review the communication management plan and the engagement plan.
M2Q35 A project sponsor requests the Project Manager to change a component to increase the customer likeability of the product.
What should the project manager do first?
Follow the perform integrated change control process
Immediately implement the change
Stop the project and enact the change
Reject the change since it is outside the scope
Correct answer
Follow the perform integrated change control process
Feedback
The perform integrated change control process is done to analyze a change and get it approved.
M2Q36 A project manager has been managing an agile project for several months when an unexpected component of the project fails. The team thinks they can fix this without any impact on the project. If the team cannot fix it, it may delay the project significantly.
What should the project manager do?
Delay the project by a few weeks to have the team address the issue
Immediately inform the sponsor of this issue
Meet with the team to discuss how they will fix it and agree on a solution
Have the team work on the issue and hope to finish it on time
Correct answer
Meet with the team to discuss how they will fix it and agree on a solution
Feedback
The best course of action would be to meet with the team and determine how the conflict is said that if it’s possible.
M2Q37 A key stakeholder on the project is very upset that they have not been included in the regular project communications. This has led to the stakeholder missing vital reports on the project performance.
What should the project manager do first to resolve this communications issue?
Meet with the stakeholder to understand why he wants the report
Review the project management plan
Implement a change request to fix the communications management plan
Meet with the team to understand why the stakeholder was not updated
Correct answer
Review the project management plan
Feedback
The best course of action would be to first review the project management plan which will include the communication and stakeholder engagement plan to better understand what communications should have taken place before trying to resolve this issue.
M2Q38 One of the sprints on an agile project has become very complex. The product owner would like the work to be completed within four weeks, but the project manager thinks this may take longer.
What should the project manager do in this situation?
Inform the product owner that it will take a few more weeks to complete
Have the agile team work together to complete the work as fast as possible
Facilitate the team and push them to complete the work within four weeks
Hire an outside consultant to help the team
Correct answer
Have the agile team work together to complete the work as fast as possible
Feedback
It would be best to let this self-organized and cross-functional team work on the sprint as fast as they could while facilitating and coaching them to complete the work.
M2Q39 A team is having a difficult time determining how long it should take to finish a particular feature. One senior programmer says the feature can be done in as little as 7 days but could take as long as 32 days. The other programmer said it would most likely take 14 days to complete.
What is the estimated development duration for the new product using the Beta estimation technique?
7 Days
16 Days
32 Days
18 Days
Correct answer
16 Days
Feedback
Using the Beta Estimate = (Optimistic + (4 X Most Likely) + Pessimistic)/6 = (7 + (4*14) + 32)/6 = 96/6 = 16 days.
M2Q40 A project was just executed when the team noticed they would need to implement changes to the scope statement. The team cannot come to an agreement on how to implement these changes.
What should the Project Manager do first?
Hold a meeting with the project sponsor to address the issue
Ensure all team members understand the change management plan
Organize a meeting with team members and sponsor to review the impact of this change
Ensure all requested changes are applied to the project
Correct answer
Ensure all team members understand the change management plan
Feedback
The team and Project Manager must follow the agreed upon change management processes.
M2Q41 After the project work is finished, the project team members are still being asked to do the following:
-Make minor modifications
-Solve technical and non-technical issues
The project manager wants to ensure the product now has operational support.
What should the Project Manager do?
Complete the delivery of the project
Examine the acceptance criteria
Formally release the project team
Fulfill the requests
Correct answer
Complete the delivery of the project
Feedback
Project closure happens once the project is complete. The PM should formally close the project and deliver the final product, service, or result.
M2Q42 An organization has moved from traditional project management methods to agile methods. This was done so the project can output deliverables faster.
What two things should the project manager implement to ensure faster delivery on an agile project? (Choose 2)
Have the team work with the customers to prioritize the product backlog
Work with the product owner and educate him about prioritizing the product backlog
Delegate work to the project team based on their skill set to accomplish the work faster
Have the team delegate work to each other based on their skill set
Speak with the product owner to determine who should be delegating the work to the team
Correct answers
Work with the product owner and educate him about prioritizing the product backlog
Have the team delegate work to each other based on their skill set
Feedback
On an agile project, is important to have a product owner prioritize the product backlog. The team should be a self-organizing self-directed team. This means they will determine what work to do and who does the work.
M2Q43 A draft of a project management plan is completed and needs to be sent to sponsors around the world. There is limited time and needs to get approved fast.
What should the project manager do in this situation?
Send the plan for the sponsors for review, and then meet with them all individually
Have each sponsor review the plan individually, adding any recommendation, and then hold a virtual meeting
Ask select sponsors to review particular sections of the plan
Organize individual meetings with only a few sponsors to walk them through the plan
Correct answer
Have each sponsor review the plan individually, adding any recommendation, and then hold a virtual meeting
Feedback
By sending the project management plan to the sponsors in advance, the PM can ensure that the virtual meeting is most productive.
M2Q44 A project team on an agile project is having a difficult time getting along with each other. The constant conflict has led to the project being severely delayed.
What should the project manager do in this situation?
Meet with the project sponsor to discuss changing team members
Meet with each team member individually and give them solutions on the issues
Meet with the team and demonstrate how the conflict is affecting the project
Organize meetings in different face-to-face activities with the team to resolve these conflicts
Correct answer
Organize meetings in different face-to-face activities with the team to resolve these conflicts
Feedback
The best way to resolve team conflicts would be to have the team discuss these conflicts in a face-to-face session.
M2Q45 A new agile virtual team is having difficulty communicating due to the complexities of the technology being used. They complain that the technology is very difficult to use and it leads to delays in communication.
What should the project manager do first in this situation?
Replace technology with a simpler technology
Review the training requirements for the technology and ensure the project team is trained
Request from the product owner additional funding for the team to work in the same environment
Inform the team to use the self-help feature in the software to learn
Correct answer
Review the training requirements for the technology and ensure the project team is trained
Feedback
It is up to the project manager to ensure the team is well trained in the development of the deliverables and the usage of technology on the project.
M2Q46 An organization has transitioned from traditional project methods to agile methods. Many team members feel that the daily standup meetings are a waste of time.
What should the project manager do to handle this situation?
Inform them that the standup is optional
Educate them on the benefits of the daily standup
Inform the product owner of the noncompliance by the team
Inform them it is okay to have the standup just once a week
Correct answer
Educate them on the benefits of the daily standup
Feedback
When an organization moves from one method to the next, it is important for a project manager to educate the team on the benefits and processes within that method.
M2Q47 An organization has been authorized to conduct a hybrid project that includes toxic materials. If the team is not trained on how to handle the materials, it will be a safety risk.
What should the project manager do in this situation?
Build the team with only resources who know how to handle the materials
Alert the sponsor and product owner of this risk
Update the risk register and risk management
Include mandatory training for the team in the project budget when planning the project
Correct answer
Include mandatory training for the team in the project budget when planning the project
Feedback
Since this is a safety risk and will happen if there are not trained, the best action would be to ensure the team is trained to handle the materials.
M2Q48 A Project Manager is working on an agile team. The Project Manager realized that two members are having a very serious disagreement about an approach to fix a technical issue. They are not allowing each other to speak and raising their voices at each other.
In what phase of development is the team now?
Confronting
Attacking
Performing
Storming
Correct answer
Storming
Feedback
Storming is when the team is having issues and conflicts about getting the work done.