TIA 2 & 3 Flashcards
M2Q1 A Project Manager wants to estimate the duration of an activity. He asks a few team members. One member says it can be done in 5 days. The other member in 15 days. The third member says in 35 days.
Using the triangular estimating technique, what is the duration of the activity?
18 days
15 days
13 days
21 days
Correct answer
18 days
Feedback
Using the Triangular formula: [Pessimistic estimate + Most likely estimate + Optimistic estimate]/3 = Therefore, [5 + 15 + 35]/3 = 18.
M2Q2 An organization has moved from traditional to agile methods and is now conducting its first agile project. The newly appointed product owner would like the team to prioritize the features as soon as possible so they can start the sprints immediately.
What should the project manager do in this scenario?
Inform the team to prioritize the features and store them in the product backlog
Educate the product owner on the benefits of having him prioritize the features
Work with the team to prioritize the features and store them in the product backlog
Inform the product owner that prioritizing the feature is not needed
Correct answer
Educate the product owner on the benefits of having him prioritize the features
Feedback
On an agile project, it is important for the product owner to prioritize the features and store them in the product backlog. If the product owner refuses, then the project manager should educate them on the benefits of doing this.
M2Q3 A smartphone company reports that customers are complaining that a new phone is very slow to boot, while others are saying it boots times are okay. A Project Manager needs to determine if something needs to be changed during the production of the smartphone.
Which tool or technique can the Project Manager use for this?
Cost of Quality
Affinity diagram
Control chart
Histogram
Correct answer
Control chart
Feedback
Control charts are used to determine whether or not a process is stable or has predictable performance.
M2Q4 A product deliverable has failed acceptance testing. The sponsor says the deliverable was not created as per the original scope.
What should the project manager do to avoid this in the future?
Have the team create the scope statement
Review the change management plan
Ensure a scope management plan is created
Have the team demo the finished product
Correct answer
Ensure a scope management plan is created
Feedback
A scope management plan documents how the project and product scope will be defined, validated and controlled.
M2Q5 A customer is unwilling to accept the deliverable since it was not functioning the way they expected it. A Project Manager is evaluating what could have been done differently to avoid this.
What should the Project Manager have done?
Assess and evaluate the scope management plan
Create the work breakdown structure (WBS) dictionary
Ensure that the quality metrics are defined
Review the requirements documentation
Correct answer
Ensure that the quality metrics are defined
Feedback
Quality metrics are a description of a project or product attribute and how to measure it.
M2Q6 A team working on a hybrid project is frustrated with the customers due to the constant changing of the project scope. When the team completes a release, the customers will then ask for the work to be redone. This has led to major delays in the project schedule.
What can the project manager do to prevent this from happening while the project is progressing?
Have the team invite the customers to the daily standup meetings and take feedback from them
Ensure customers are invited to the sprint review meeting to give feedback
Inform the project sponsor about this issue
Inform the customers that changes should not be made after the work has been completed
Correct answer
Ensure customers are invited to the sprint review meeting to give feedback
Feedback
If their constant changes to a deliverable, it would be best to invite the customers or have them participate more in the Sprint review meetings to give more feedback as it is being built.
M2Q7 The project manager created a charter for a new software project. A senior stakeholder feels this project will have a negative impact on her employees.
What should the project manager do first?
Request for the project sponsor to speak with this stakeholder
Have the stakeholder meet with the team for a better explanation of the project
Document as a risk in the risk register
Have a meeting with the stakeholder to review the project objectives
Correct answer
Have a meeting with the stakeholder to review the project objectives
Feedback
The first thing the PM needs to do is to make sure the project objectives are well understood before taking any action.
M2Q8 A project manager has been assigned to an ongoing project in the planning phase. The WBS has already been decomposed, but the project manager feels that more information will be needed in order to complete the project.
What will the project manager use to further decomposed the work?
Scope statement
WBS dictionary
Requirements management plan
Requirements documentation
Correct answer
WBS dictionary
Feedback
The best document for the user would be to WBS dictionary since it has detailed information about some of the work. After reviewing the WBS, the project manager can then determine what additional detailed meeting is needed.
M2Q9 A company is creating a new technology product. The project manager has verified that the component work packages have been well-defined.
Which estimating technique should the project manager use to obtain an accurate cost estimate of the deliverables?
Analogous
Three-point
Bottom-up
Parametric
Correct answer
Bottom-up
Feedback
Bottom-up estimating is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS.
M2Q10 A key stakeholder is giving the team a hard time and is always arguing with team members. The stakeholder feels like no one understands him and knows how to communicate. If the issue is not resolved immediately, it could lead to the termination of the project.
What should the project manager do in this situation in regards to the team?
Inform them not to communicate with the stakeholder going forward
Have the stakeholder communicate with them through email only
Train the team on emotional intelligence
Inform the team to try to communicate with the stakeholder as the project is nearing completion
Correct answer
Train the team on emotional intelligence
Feedback
This solution would be to train the team on emotional intelligence so they can better communicate with the stakeholder and hopefully resolve this issue.
M2Q11 A project is completing the deliverable and a key stakeholder will be unavailable for a few weeks during the project. This stakeholder will be the person to approve the deliverable.
What should the project manager do first?
Ensure that the issue log is updated
Request a replacement during the stakeholder’s absence
Setup a meeting with the sponsor to evaluate the situation
Finish the project and have another stakeholder approve the deliverable
Correct answer
Ensure that the issue log is updated
Feedback
The first thing the PM needs to do is to update the issue log and communicate this to the other stakeholders.
M2Q12 A small team is working virtually on a hybrid project and is having a difficult time being committed to the project. This has led to work being incomplete and defects in completed work.
What should the project manager do first in this situation?
Speak with each team member individually to determine the root cause of this issue
Meet with the team as a whole and inform them of this issue and have them resolve it immediately
Meet with the project sponsor and inform him of this issue
Remove the team members that are having issues and replace them with more motivated members
Correct answer
Speak with each team member individually to determine the root cause of this issue
Feedback
The best solution would be to meet with each member individually since it is a small team to better understand what is causing this. Then work with the team to find a resolution.
M2Q13 A hybrid project has been executed and a new regulatory law has been passed that mandates immediate compliance. This law will increase the project’s scope and cost schedule.
What should the project manager do first?
Update the risk register
Ensure the project management plan is up to date
Escalate this to the senior company management
Implement a change request
Correct answer
Implement a change request
Feedback
Since compliance is mandatory and it impacts the scope, and cost, a change request needs to be submitted.
M2Q14 A deliverable on the project’s critical path is behind schedule. The cost performance index (CPI) is 1.3. The project manager wants it back on schedule.
What is the most likely outcome for this deliverable?
There will be activities performed in parallel
There will be a revised scope
There will be an increase in costs and risks
There will be rework
Correct answer
There will be an increase in costs and risks
Feedback
The Cost Performance Index (CPI) is above 1. Therefore the project is spending money at a rate lower than planned. It would be best to crash this deliverable to complete it sooner. This will generally increase cost and risk.
M2Q15 A scrum team is having a difficult time staying on schedule. The PMO is concerned that this delay can cause the project to lose value. The project manager realizes that this is caused by team members not having the correct skills.
What should the project manager do in this situation?
Meet with the team and inform them of the deadlines they have to meet
Increase the project schedule to account for the delays
Find the correct training for the team members that needs it
Inform the PMO this is normal on a project
Correct answer
Find the correct training for the team members that needs it
Feedback
The project manager should ensure the team members are adequately trained while working on a project.
M2Q16 The project manager discovers that a senior stakeholder is asking a team member for project information. This is causing an issue with the team completing their work.
Which should the project manager do first?
Review the stakeholder register
Refer to the project management information system (PMIS)
Send the stakeholder the information yourself
Review the communications management plan
Correct answer
Review the communications management plan
Feedback
A communications management plan is established to ensure that the appropriate messages are communicated to stakeholders in various formats and various means as defined by the communication strategy.
M2Q17 The agile project team has complained that the product owner has prioritized the product backlog with everything as being critical. The team is not sure what to work on next.
What should the project manager do in this situation?
Have the team choose what is the most important to start with first
Have the team reprioritize the entire product backlog
Have the team prioritize the work based on what can be finished the fastest
Meet with the product owner and educated him on why the product backlog should be reprioritize based on value
Correct answer
Meet with the product owner and educated him on why the product backlog should be reprioritize based on value
Feedback
Prioritization of the product backlog should be done by the product owner, not the product team. It would be best for the project manager to educate the product owner on the values of doing this.
M2Q18 An organization has signed a fixed price contract with the vendor to upgrade its current network. The project manager thinks that due to certain network components, the project might be delayed by more than two months. The vendor has stated this will not happen.
What should the project manager do in this situation?
Update the procurement management plan with this potential issue
Update the risk register and risk responses
Implement a change request to extend the project schedule by two months
Hire a new vendor on standby in case the vendor delays the project
Correct answer
Update the risk register and risk responses
Feedback
Since this is a risk that can affect the project schedule, the project manager should add the risk to the risk register with a corresponding response.
M2Q19 A project manager is working with a customer who submitted over 10 new scope changes for an existing software development project. The project manager feels this is unnecessary due to the type of software being made.
What should the project manager do next?
Hold a meeting with the customer to request that the number of new requests is reduced
Define the number of changes with the sponsor
Organize a meeting with the team to set expectations
Analyze the scope management plan
Correct answer
Analyze the scope management plan
Feedback
The scope management plan documents how the project and product scope will be defined, developed, monitored, controlled and validated. The document provides guidance and direction on how the scope will be managed throughout the project.
M2Q20 A project manager is working on a large project for a global corporation. After conducting a stakeholder analysis, the project manager decides the best way to communicate would be through virtual meetings. The sponsor would prefer emails since it is what the organization uses the most.
What should the project manager do in this situation?
Inform the team they should use emails going forward
Meet with the project sponsor and educate him on the benefits of virtual meetings over emails
Change the communication management plan to reflect emails
Ask the PMO what would be best for this project
Correct answer
Meet with the project sponsor and educate him on the benefits of virtual meetings over emails
Feedback
The project manager should always be willing to educate stakeholders on the benefits of using communication methods that are better suited to the project.
M2Q21 A project is 9 months into execution. The Project Manager computes that the schedule performance index (SPI) is .60. The SPI was .9 in month 1, .8 in month 4 and .7 in month 8.
What should the project do in this situation?
Issue a change request
Hire new team members to complete the work faster
Crash the project schedule
Utilize the management reserve
Correct answer
Issue a change request
Feedback
Since the project is behind schedule and the trend analysis shows that this will continue, the best course of action is to update the project management plan with a new realistic schedule.
M2Q22 As a project is being implemented. A key stakeholder communicates to the project manager that the requirements of the project may have changed. These changes may significantly impact the project scope.
What should the project manager do in this situation?
Update the risk register and identify risk responses
Redo the scope statement
Use the contingency reserve and update the risk mitigation plan
Compute the current earned value management (EVM)
Correct answer
Update the risk register and identify risk responses
Feedback
These new requirements may pose additional risks. These risks need to be documented and appropriate responses need to be identified.
M2Q23 The agile project has just released a minimum viable product (MVP) to the customers and the company. A few of the customers have complained that it is lacking a large number of features and is not very useful.
What should the project manager do first in this scenario?
Pullback the release until it has the right amount of features
Inform the team to add the required features immediately
Educate the customers on the value of an MVP
Ask the product owner to meet with the customers to discuss this issue
Correct answer
Educate the customers on the value of an MVP
Feedback
The best-case scenario would be to educate the customers on the usage and value of an MVP and why it lacks certain features.
M2Q24 A project has the following characteristics:
-US$5 million budget
-Planned value of US$635,000
-Actual cost of US$655,000
-Earned value of US$545,000
Which statement is true about the current status of the project?
The project is ahead of schedule and under budget
The project is behind schedule and over budget
The project is ahead of schedule and over budget
The project is behind schedule and under budget
Correct answer
The project is behind schedule and over budget
Feedback
CV = EV - AC: 545 - 655 = -110, SV = EV - PV: 545 - 635 = -90, Negative cost variance means the project is over budget, Negative schedule variance means the project is behind schedule.