Time Management Flashcards

1
Q

Project Schedule Network Diagram

A

a graphical depiction of dependencies among project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Precedence Diagramming Method

A

a network diagramming method that uses rectangles (nodes) to represent activities and arrows to show logical relationships between the activities; also knows as Activity-On-Node (AON)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of Dependencies

A

Mandatory (hard logic), Discretionary (preferred, arbitrary, soft logic), External and Internal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Logical Relationships

A

dependencies between two activities where one activity must be started or finished before the other can be started or finished; Four Types: FInish to start (FS), Finish-to-Finish (FF), Start-to-start (SS), Start-t0-finish (SF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Lead

A

starting an activity prior to the completion of the preceding activity; getting a head start on an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Lag

A

delaying the start of an activity after the completion of a preceding activity; delaying an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Bottom-Up Estimating

A

breaking a project or activity down into smaller components that are easier to estimate, then aggregating (rolling-up) those costs or durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Analogous Estimating

A

using a previous project (historical information) as a starting point to estimate activity costs or activity durations; also known as top-down estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Parametric Estimating

A

using a statistical relationship to calculate cost or duration; typically involves multiplying the number of units by a cost or duration per unit; time example: 4 hours per server x 20 servers = duration of 80 hours; cost example: $100 cost per square foot x 2,000 square feet = $200,000 construction cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Three-Point Estimating

A

a weighted average method used to increase estimation accuracy; uses Optimistic, Pessimistic, and most likely estimates to calculate the estimated activity cost or duration; Beta Distribution Formula (PERT): (O + 4xML +P) / 6; Triangle Distribution Formula: (O + M + P) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Reserve Analysis

A

contingency reserves (buffers) used to account for schedule or cost uncertainty (risks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Critical Path

A

the path of activities along which any delays will cause the project to be delayed; the longest duration path through the schedule network diagram; the chain of tasks which all have 0 float.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Total Float (Slack)

A

the amount of time an activity can be delayed without delaying the project completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Free Float

A

the amount of time an activity can be delayed without delaying the following (successor) activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Critical Path Method

A

a schedule analysis method that calculates the critical path for the project, float for each activity, and possible start and finishes dates for each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Critical Chain Method

A

take the Critical Path Method and factors in resource constraints and schedule buffers

17
Q

Schedule Compression

A

used to shorten the project schedule; two-methods: Crashing (adds extra resources, results in higher costs) or Fast-tracking (doing activities in parallel, which increases risk)

18
Q

Resource leveling

A

used to adjust the resource schedule when resources have been over-allocated; often lets the schedule slip in order to smooth out resource utilization; a histogram (bar chart) is the tool used to do this

19
Q

Resource smoothing

A

used to adjust the activities within the schedule to keep resources from exceeding limits; with resource smoothing, the completion date is not delayed

20
Q

What-if Analysis

A

a statistical analysis method used to predict the schedule based on various possible scenarios; example: Monte Carlo Analysis is a computer software that attempts thousands of random scenarios to predict likely possible outcomes

21
Q

Milestone Schedule

A

a summary schedule which only shows key points in the project

22
Q

Gantt Chart

A

a type of chart used to display the project schedule with bar lengths representing activity durations

23
Q

Schedule Baseline

A

the accepted and approved version of the project schedule