Time Management Flashcards
Project Schedule Network Diagram
a graphical depiction of dependencies among project activities.
Precedence Diagramming Method
a network diagramming method that uses rectangles (nodes) to represent activities and arrows to show logical relationships between the activities; also knows as Activity-On-Node (AON)
Types of Dependencies
Mandatory (hard logic), Discretionary (preferred, arbitrary, soft logic), External and Internal
Logical Relationships
dependencies between two activities where one activity must be started or finished before the other can be started or finished; Four Types: FInish to start (FS), Finish-to-Finish (FF), Start-to-start (SS), Start-t0-finish (SF)
Lead
starting an activity prior to the completion of the preceding activity; getting a head start on an activity
Lag
delaying the start of an activity after the completion of a preceding activity; delaying an activity
Bottom-Up Estimating
breaking a project or activity down into smaller components that are easier to estimate, then aggregating (rolling-up) those costs or durations
Analogous Estimating
using a previous project (historical information) as a starting point to estimate activity costs or activity durations; also known as top-down estimating
Parametric Estimating
using a statistical relationship to calculate cost or duration; typically involves multiplying the number of units by a cost or duration per unit; time example: 4 hours per server x 20 servers = duration of 80 hours; cost example: $100 cost per square foot x 2,000 square feet = $200,000 construction cost
Three-Point Estimating
a weighted average method used to increase estimation accuracy; uses Optimistic, Pessimistic, and most likely estimates to calculate the estimated activity cost or duration; Beta Distribution Formula (PERT): (O + 4xML +P) / 6; Triangle Distribution Formula: (O + M + P) / 3
Reserve Analysis
contingency reserves (buffers) used to account for schedule or cost uncertainty (risks)
Critical Path
the path of activities along which any delays will cause the project to be delayed; the longest duration path through the schedule network diagram; the chain of tasks which all have 0 float.
Total Float (Slack)
the amount of time an activity can be delayed without delaying the project completion date
Free Float
the amount of time an activity can be delayed without delaying the following (successor) activity
Critical Path Method
a schedule analysis method that calculates the critical path for the project, float for each activity, and possible start and finishes dates for each activity