Earned Value Management Formulas & Meanings Flashcards
CV =
Cost Variance | Formula: EV - AC | Negative is bad, positive is good
SV =
Schedule Variance | Forumla: EV - PV | Negative is bad, positive is good
CPI =
Cost Performance Index | Formula: EV/AC | Under 1 is bad, Over 1 is good
SPI =
Schedule Performance Index | Formula: AC + (BAC - EV) | AC plus work remaining. use budget rate (atypical)
EAC =
Estimate at Completion | Formula: AC + (BAC - EV) or BAC/CPI or AC + [BAC - EV]/[CPI *SPI] | Assumes poor cost performance & schedule performance will continue
ETC =
Estimate to Completeion | Formula: EAC - AC | Value of work remaining
VAC =
Variance at Completion | BAC - EAC | Negative is bad, Positive is good
TCPI =
To Complete Performance Index | Formula: (BAC - EV) /(BAC - AC) | Optimal rate to complete within budget or (BAC - EV)/(EAC - AC) | Assumes original budget cannot be achieved.