Time Management Flashcards
Define activities
Taking the work packages created in the WBS and decomposing them into activities that are required to produce the work package deliverables
Plan schedule management
How you will plan manage and control the project schedule
Need to determine in advance what the measures of performance will be how and when you will capture the data you need to measure how you will use the data to keep the project on track and what you will do when variances occur
Rolling wave planning
Planning to a higher level and then waiting until project work has begun and work is clearer to plan at lower levels
Milestones
Significant events within the project schedule. They are not work activities and have no duration
Sequence activities
Taking activities and milestones and sequencing them in the order in which the work will be performed
Result is a network diagram
Precedence diagramming method (PDM)
Activity on node (AON)
Boxes are used to represent activities and arrows show activity
Finish-to-start - an activity must finish before the successor can start
Start to start - an activity must start before the successor can start
Finish to finish - an activity must finish before the successor can finish
Start to finish - an activity must start before the successor can finish
Graphical evaluation and review technique ( GERT )
Allows loops between activities
Ex: design a component and then test it, after testing the component may or may not need to be redesigned
Types of dependencies
Mandatory ( hard logic ) - inherent in the nature of work; you must design before you can construct
Discretionary (preferred soft logic preferential ) - the way an organization has chosen to have work performed; established based on knowledge of best practice within an area of the project
External - needs or desires of a party outside the project
Internal - based on the needs of the project and may be something the project team can control
Leads and lags
Lead may be used to indicate that an activity can start before its predecessor activity is completed
Lag is waiting time inserted between activities such as needing to wait 3 days after pouring concrete for construction can begin
Estimate activity resources
Type and quantity of needed resources are determine
Resources can include equipment materials and people
Estimate activity durations
Estimate how much time each activity will take
Estimators should be the ones who will be doing the work
One-point estimating
Estimator submits one estimate per activity based on expert judgment or historical information
Analogous estimating (top down)
Uses expert judgement and historical information to predict the future; can be done at various times and level of accuracy depends on how closely the project or activity matches past history
Management provides the schedule
Pros:
Quick
Less costly
Cons:
Less accurate
The last 5 projects took this long so this one should as well
The last two times this activity was completed each took 3 days
Parametric estimating
Looks at the relationship between variables on an activity to calculate time or cost estimates
Can come from historical records industry requirements standard metrics
Example estimator may use measures like time per line of code time per linear meter or time per installation
Takes 2 hours to paint 1 square foot of wall so 60 square feet would take 120 hours
Types of parametric estimates
Regression analysis ( scatter diagram ) - tracks two variables to see if they are related and crate a mathematical formula to use in future parametric estimating
Learning curve - the 100th room painted will be less time than the first room because of improved efficiency