Time & Delay Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Main concepts of time and delay in NEC4

A

Time and money contractual definitions must reflect the agreement

Avoid time and money being at large

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Adversarial contracts (JCT SBC/Q) vs collaborative contracts (NEC4)

A

Adv. - contractor claims for loss and expense disputes around time

Collab. - looking ahead to avoid future problems, compensation events and advance payment look to minimise disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a CE

A

Anything that affects the achievement of the completion date, key dates, the scope of works changing, design changing or the cost of the project changing is a CE

Therefore change becomes a CE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the stated dates in NEC4

A

Contract date - when contract is executed

Starting date - when word should start; stated in CD part 1

Access date - when the client gives possession of the site to the contractor

Completion date - date for completion of the whole of the works as stated in CD part 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the completion date

A

The Completion Date is the completion date unless later changed in accordance with the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a key date

A

Date by which work is to meet the condition stated

Similar to sectional completion in JCT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are time risk allowances

A

Allowances made within programmed activity durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is float addressed in NEC4

A

Float can be used by either party to ensure completion before the Completion Date

Float is owned by whichever party uses it first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Different elements of completion

A

Completion date (stated in CD)

Planned completion (stated in the current accepted programme)

Completion (when the PM certifies the works as being complete)

Take over (when the client begins to use the works)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PM actions regarding time management

A

Instruct a change in Scope or key date

Certify date of completion

Instruct the contractor to update the programme

Instruct the contractor to submit an acceleration quotation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Secondary clauses relating to time and delay

A

X6 bonus for early completion

X7 delay damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who owns the programme in NEC4

A

The contractor

The PM certifies or rejects submitted programmes from the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Importance of submitting the first programme

A

If a contractor fails to submit a first programme, they will be deducted 25% of PWDD accrued until they submit a compliant programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is acceleration addressed in NEC4

A

PM or contractor can propose acceleration to the other to achieve completion before the completion date

PM instructs contractor to prepare quotation within three weeks of instruction

PM replies with acceptance or rejection within 3 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are early warnings

A

Contractor or PM can provide early warning of anything that could: (15.1)

Increase the total Prices
Delay completion
Delay a meeting a Key Date
Impair the performance of the works

Underlying principle is to be proactive in addressing risk to identify problems early and jointly find solutions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is early warning register maintained

A

PM prepares first early warning register and issues to contractor

The first early warning meeting must be held within 2 weeks of the starting date

Further meetings then happen at the request of the PM or contractor or at least in the intervals specified in the CD

17
Q

Failure to provide early warning

A

A party will only be compensated from the date they should have notified, not when they did notify

Must warn when an experienced contractor would