Cases Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Twintec Ltd v Volkerfitzpatrick Ltd 2014

Adjudication

A

Injunction granted to a SC to restrain the contractor from pursuing a reference to adjudication after the appointment of an adjudicator

In the absence of agreement by the parties as to the appointment, any decision made by the adjudicator would be a nullity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Wates Construction Ltd v Franthom Properties Ltd 1991

Retention in separate bank account

A

F engaged W to construct hotel

W requested F place retention monies in a separate and identifiable account, to which they refused

Judge found for W, stating F had a duty to protect the fund in the interest of the beneficiaries

Immediate obligation to set aside the fund in a separate account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Rayack Construction v Lampeter Meat Co Ltd 1979

Retention in separate bank account

A

Retention to be held at 50% for 5 years

R requested L set aside the retention monies in a separate bank account (citing clause 34(4)), seeking this through injunction when ignored

Judge found for R - purpose of the provision is to protect both parties from insolvency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Hadley v Baxendale 1854

Unliquidated damages

A

Hadley was denied recovery of lost profit for late delivery of a crankshaft

Baxendale could only be held liable for losses that were reasonably foreseeable, of which lost profit in this case was not

Gave rise to the two limbs:
Arising naturally
Such as may have been in reasonable contemplation of the parties at the time the contract was made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Trentham (G Percy) Ltd v Archital Luxfer Ltd 1993

Is a contract in place

A

No written contract in place, but there were oral and written exchanges and transactions were fully executed

Judge found for T, stating there was evidence to justify the finding that there were contracts concluded partly by conduct, which were capable of coming into existence after part of the work had been carried out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Blyth & Blyth Ltd v Carillion Construction Ltd 2001

Novation of design liability

A

Novation produces a tripartite relationship between the parties

A party cannot claim against a party they only have a novated relationship with for something prior to the date of the novation agreement’s execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Lindenberg v Canning and Others 1992

Duty to warn & contributory negligence

A

A demolition of walls in a project was incorrectly completed

C was in breach of contract because they ought to have raised doubts over the unclear drawing, thus not having exercised the required skill and care

L was owed no duty of care from C in negligence

L had been contributorily negligent by its agent (the designer) wrongly showing the walls as non-load bearing so we’re apportioned 25% of the liability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners 1975

Duty level dependent on circumstances

A

Floor not fit for purpose due to methodology and insufficiently strong design

B owed a higher duty of care by virtue of the special circumstances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

MT Højgaard A/S v E On Climate and Renewables UK Robin Rigg East Ltd 2017

Fitness for purpose

A

Contract stipulated 20 year life span of foundations of which the product did not meet

Contract provisions should almost always be given their natural meaning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

John Mowlem & Co v British Insulated Callenders Pension Trusts Ltd and ors 1977

Limits on Contractor’s liability for design of others

A

B engaged J to build a warehouse and J engaged XP for structural engineering services

XP had failed to exercise sufficient skill and care in their design so were negligent

The bills did not impose a design obligation on J so they were not liable for XP’s design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Ascon Contracting Ltd v Alfred McAlpine Construction Isle of Man Ltd 1999

Ownership of programme float

A

Established that a contractor cannot claim against subcontractors where they have claimed benefit of the float from the Employer as if the float did not exist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Robinson v Harman 1848

Damages must place the injured party in the same position had the other party performed

A

Established the objective of common contract law being to put the parties in the same position as if the contract had been performed (restitution)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd 1915

Should damages be punitive

A

Damages must be a genuine pre-estimate of the loss incurred - anything else is punitive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Balfour Beatty Construction (Scotland) Ltd v Scottish Power Plc 1994

Applicability of remoteness test to construction confirmed

A

Power went off during concrete pour

£10,000-£15,000 awarded in damages but major demolition damages not awarded as it would be unreasonable to expect Scottish Power to understand the technical construction operations’ implications of power dropping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Blue Circle Industries Plc v Holland Dredging Company (UK) Ltd 1987

Scope & validity of variations

A

If works are wholly outside the scope of the original contract, they cannot be ordered as a variation and must be a separate contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Henry Boot Construction Ltd v Alston Combined Cycles 2000

Using tender rates to price variations

A

The basis for valuation as using tender rates and prices cannot be displaced on the grounds the rates were mistakenly inserted

If variation works are significantly different to the works in the BOQ, the engineer could carry out a valuation of their own

17
Q

Costain Ltd v Bechtel Ltd 2005

Whose interests should the PM act in

A

Confirmed PM should act impartially between contractor and employer

18
Q

MacJordan Construction v Brookmount Erostin Ltd 1991

Retention and order of precedence in insolvency

A

Bank floating charges take precedence over unsecured claims (in this case retention) in the case of insolvency of employer

Emphasises the importance of setting aside the retention fund

19
Q

RGB Plastering Limited v Tawe Drylining and Plastering Limited 2020

Obligation to issue in compliance with contract processes

A

An application for payment was submitted late and not to the email address stipulated in the contract

Application held to be invalid

20
Q

Panamena Europea Navigacion v Leyland 1947

Obligation to issue in compliance with contract processes

A

A surveyor thought his function of certification included the manner in which works were carried out and declined to deal with an issue until information he requested was provided

This information request was based on his erroneous view of the contract, meaning he was insisting on an illegitimate condition precedent to carrying out his certification duty

Respondents thus could recover the amount claimed in action

21
Q

Galliford Try Building Ltd v Estura Ltd 2015

Final account vs final valuation

A

GT attempted to get their final application (higher than Estura’s valuation) approved as the final account

This manoeuvring combined with Estura’s lack of money was considered a manifest injustice and stayed with Estura’s own lower valuation

22
Q

Westminster CC v Jarvis & Sons Ltd 1969

Completion validity

A

There is no delay if the party achieves such apparent completion that the contractor is able to take over, notwithstanding that the work apparently completed may be defective

23
Q

Mersey Steel & Iron Co v Naylor Benzon & Co 1884

Defines repudiation

A

A steel seller assumed non-payment on part-delivery as a breach

This was not the case as the whole service had not been carrying out and there was no provision for payment for part-delivery

Repudiation is in essence one party saying you fulfil your obligations and the other party saying/heavily implying I will not fulfil mine, which is of course not the case here

24
Q

Architectural Installation Services v James v James Gibbons Windows 1989

Notices of termination must relate to each other in time and content

A

A notice must have a sensible connection with those prior

If there is no sensible connection and there is a two-notice process to the termination procedure, the second notice will be invalid

Notices must follow the process and notices must be sensibly connected to whatever their consequences are

25
Q

Tate & Lyle Food Distribution Co Ltd v GLC 1981

Purpose of interest when applied to damages due

A

Interest should reflect the cost to the plaintiff of having the sums owed to them not paid

Correct rate to charge should be ascertained by taking the rate at which the plaintiffs could borrow money in general

26
Q

199 Knightsbridge Development Ltd v WSP UK Ltd 2014

A

State of the art defence can be used but not necessarily successfully

Opposing party must prove the other foresaw the problem and designed accordingly still resulting in failure