Payment Flashcards
Fundamental elements of payment
The Prices (how much are the works supposed to cost)
Defined cost (how much the works are currently projected to cost)
PWDD (what the contractor should be paid for the works in their partially complete state)
Disallowed cost (what the contractor requested but the PM has decided he are not entitled to receive)
Schedule of cost components (a way to recalculate the costs when things change) - not applicable to main option F as contractor is reimbursed for all payments to SC’s
How does an activity schedule differ from a BOQ
Activity schedules have lump sums for items
BOQ’s have quantity, unit and rate info for items (more detailed)
How do the prices, defined cost and the fee interact
The prices = defined cost + the fee
This does not apply to priced contracts (main options A and B)
Basis for cost dependent on main option
A & B - the Prices
C - F - defined cost + fee
What is the fee
Single % given in CD part 2
Covers overheads, profit, tax, insurance etc.
What is the schedule of cost components
Submitted by contractor in CD part 2
Used to calculate the cost parts of works changed from the original intent in all main options excluding main option F
Example content:
People, equipment, plant and materials, design, insurance
What is defined cost
The original intended costs (the Prices) and those incurred through CE’s
The contractor’s actual incurred cost
What is PWDD
Represents expenditure on the partially complete structure, determined differently dependent on the basis of payment (the Prices or defined cost + fee)
What is disallowed cost
Costs that the contractor has asked to be paid, but the PM believes are unsupported by the contract
Deductions from contractor’s application for payment
Key payment term in Construction Act (payment cycle)
Part II payment cycle
Payment due within 7 days of relevant period
Payment notice within 5 days (becomes notified sum)
Payless notice no later than 7 days before final date for payment
Final date for payment is 17 days after due date
NEC4 payment process
Contractor submits payment application before each assessment date detailing amount due and basis for calculation
PM certifies payment within 1 week of application
Client pays contractor within 3 weeks of certification
What if payment requires correction in later period
PWDD is altered accordingly in subsequent payment period
Interest is to be paid to the underpaid party
How does NEC4 address client non-payment
Contractor has right to terminate
If they do not, they must continue as their obligations remain
When is the first payment assessment
Within one assessment interval after the starting date
How do final assessment intervals differ
Within 4 weeks of issuance of defects certificate from supervisor
Within 13 weeks of issuance of termination certificate from PM