Contract Compilation & Execution Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What is a contract

A

A legally binding agreement

Needs offer, acceptance and consideration under English law and both parties must be intended to be bound and fit to enter into contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Unilateral vs bilateral contract

A

Unilateral - one promise in exchange for another promise

Bilateral - exchange of mutual promises

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Deeds vs under hand

A

Deeds - solemn promise, signed and witnessed, consideration not required, 12 year limitation period

Under hand - can have any form, simple signature required, 6 year limitation period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is tendering

A

Process of finding and appointing a contractor

Client approaches market (invitation to treat)

Contractors submit bids (offers)

Bids are reviewed and evaluated

Most suitable tenderer becomes contractor (acceptance)

Best value or lowest price award

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a letter of intent

A

A letter from an employer to a contractor (or from contractor to SC) indicating the employer’s intention to enter into a formal written contract for works described in the letter

And asking the contractor to begin those works before the formal contract is executed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is determination

A

A contract being stopped before completion

Usually a result of one party not being able to continue (insolvency, default of payments from client)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is discharge

A

Extinguishing rights and obligations

By performance (normal), agreement or frustration (contract now impossible to perform at no fault of the parties)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Unliquidated damages basis for assessment

A

Assessed on basis of reasonably arising loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are liquidated damages

A

A genuine attempt to pre-estimate loss in the event of specific breaches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the implications of privity of contract

A

No third party can be affected (obligations)

Only the parties can enforce terms (rights)

Third party cannot sue under contract they were not party to

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are collateral warranties

A

Agreements used where the contract creates an obligation from one party to provide a warranty to a third, independent party outside the contract (e.g. residential development extending to tenants)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Key elements of NEC4 contracts

A

Clauses (terms and conditions)

A section for project parameters (Contract Data)

Definition of works (Scope, site information)

Pricing information (the Prices)

Design content (Scope including drawings and specifications)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Composition of NEC4 Contract

A

Core clauses

Main option (provides payment method)

Secondary options (X clauses)

UK specific clauses (Y clauses)

Dispute resolution (W clauses)

Custom options (z clauses)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a compensation event

A

An event which can affect the cost to the client, the time when the works will be completed or both

There are up to 29 potential CE’s under NEC4 dependent on X clauses selected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are early warnings

A

Obligation to notify other party of any event that may:

Increase the prices

Delay completion

Delay meeting a Key Date

Impair the performance of the works once in use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contract Data part 1

A

Completed by client

States contract options

Describes key information (the works, contractor’s responsibilities, important dates, retention percentage if option used etc.)

17
Q

Contract Data part 2

A

Completed by each tendering contractor including:

Key persons

Programme

Completion date

Total of the Prices (main options A-D)

Payment structure

18
Q

What are the Prices

A

If there are no CE’s, the Prices are the amount the contractor will receive for completing the works

19
Q

Priced contract options

A

A - activity schedule

B - bill of quantities

20
Q

Target contract options

A

C - activity schedule

D - bill of quantities

Pain/gain share

21
Q

Reimbursable contract options

A

E - cost reimbursable contract

F - management contract

22
Q

What is Scope and what does it define

A

Work to be done

Defines:

Activity schedule

Client’s liabilities

CE’s

Early warning decisions

23
Q

Core clauses

A

1 General
2 Contractor’s main responsibilities
3 Time
4 Quality Management
5 Payment
6 CE’s
7 Title
8 Liabilities and Insurance
9 Termination

24
Q

Who is the Client

A

Legal entity executing the contract with the contractor

Pays for the works and the process of delivery

Appoints PM and Supervisor

Provides site and Key Dates

25
Q

Who is the Contractor

A

Legal entity executing the contract with the client

“Provides the works in accordance with the scope” (20.1)

Proposes programme

26
Q

Who are the Key Persons

A

Proposed in CD part 2

Specific individuals Contractor proposed as management team

Their presence and skills are part of the offer

27
Q

Who is the PM

A

Appointed by client to administer contract

Oversees works, instructs contractor, accepts Contractor programmes and quotations, assesses CE’s and certifies interim payments

Tells Contractor which “others” to allow onto site

28
Q

Who is the Supervisor

A

Appointed by client to oversee quality of the works

Performs tests and inspections, instructs Contractor to search for defects, issues Defect Certificate when all defects corrected (44.3)

29
Q

Who are named suppliers

A

Suppliers who require access to the Project Bank Account if required

30
Q

Who are the senior representatives

A

Senior members of the client and contractor’s organisations who are not involved in the project

Provide initial dispute resolution method in W1 & W2

31
Q

Who are the dispute avoidance board

A

Independent body of 1 or 3 people (both parties choose one and agree on the 3rd or agree on just 1)

Provided by option W3

32
Q

Who is the adjudicator

A

An experienced, trained, neutral and independent individual with specialist knowledge

Used under options W1 & W2

Investigates and provides a decision

33
Q

What is the tribunal

A

The next level in the hierarchy of dispute resolution

Forms are litigation and arbitration (both binding)

34
Q

Twintec Ltd v Volkerfitzpatrick Ltd 2014

A

Injunction granted to a SC to restrain the contractor from pursuing a reference to adjudication after the appointment of an adjudicator

In the absence of agreement by the parties as to the appointment, any decision made by the adjudicator would be a nullity