TIME AND SCHEDULE Flashcards

1
Q

Name for factors affecting the time required for schematic design.

A
  1. Size and complexity
  2. Quality and completeness of the program information supplied by the client
  3. Decision-making ability of the client
  4. The nature of the design team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the main factor determining the length of time it takes to complete design development and construction document phases?

A

Complexity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Typical time for schematic design on a simple project

A

1-2 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Typical time for design development on a typical project

A

2-4 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Typical time for construction documents on a typical project

A

3-7 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Typical time for bidding or negotiation on a typical project

A

3-6 weeks… Regardless of the size of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In what phase can financing lags have the greatest effect?

A

Usually in the client approval. Between schematic design and design development and between design development of construction documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When do you file for a building permit?

A

Near the conclusion of the construction phase… So that the building permit can be obtained about the same time as the construction contract is let

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The five phases of design

A

Schematic design, design development, construction documents, bidding or negotiation, construction administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Three ways to shorten the design schedule

A
  1. Architects work overtime (more expensive)
  2. More people on the job (less efficient = more expensive)
  3. Reduce man-hours spent (lower quality work)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What do the arrows indicate I the CPM method?

A

Activities resulting in events/milestones (no indication of time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a completed CPM diagram referred to as?

A

Network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When two portions of a project are planned in separate CPM diagrams, but have events common to both networks, these events are called…

A

Interface events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

After the CPM network diagram is created, time is added to the equation to create… And to ascertain the…

A

CPM scheduling… The critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the unit of time in CPM scheduling?

A

One normal working day

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the critical path?

A

This is the procedural path in a CPM network diagram with the longest total required time

17
Q

What are activities along the critical path called?

A

Critical activities

18
Q

If critical activities are delayed…

A

They will delay overall construction time

19
Q

What are float paths?

A

All other path in the network diagram other than the critical path.

20
Q

How do you determine the float of the path?

A

This is the difference, and days, between the path in question and the critical path.

21
Q

Why would a contractor multiply working days by 7/5?

A

That gives him the number of calendar days

22
Q

For reasons a client might want to shorten the construction schedule.

A
  1. Interest on borrowed funds
  2. Pressures of business
  3. To minimize effects of inflation
  4. Inclement weather
23
Q

Though shortening the durations of the critical path likely result in increased direct cost through inefficiency of added overtime work and inefficiency’s from coordination and supervision, the contractors overhead _______

A

Actually decreases as the scheduled time is shortened.

24
Q

Fast track scheduling often the gates the possibility of…

A

Fixed price for construction… Because it usually has to be bid in stages

25
Q

Who can help you with fast-track construction?

A

Construction manager

26
Q

Shop fabrication reduces the impact of…

A

Inclement weather on construction time

27
Q

Prefabricated items reduce design time because…

A

It is easier to select from a catalog then to design new pieces

28
Q

The only party responsible for scheduling construction trades

A

Contractor