CHANGE ORDERS & PAYMENTS Flashcards

1
Q

When he change order is agreed to by both owner and contractor, it becomes a…

A

Contract modification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What happens in the absence of total agreement on the terms of a change order?

A

A construction change directive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Construction change directive can only be in the general…

A

Scope of the contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Four ways to agree upon the contract some for a construction change directive adjustment

A
  1. Mutual acceptance of a lump sum
  2. Unit prices stated in the contract documents or subsequently agreed-upon
  3. Cost TBD in a matter agreed upon by parties at a mutually acceptable fixed or percentage fee
  4. The architect determines the cost by monitoring the contractors actual expenditures of time, materials, and overhead.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When the contractor discovers a deficiency in the contract documents, the architect is obligated… But not obligated…

A

YES: to remedy the deficiency at his expense… By revising drawings and processing the change documents

NO: to pay for the cost of construction caused by the deficiency (unless the owner approves the architect was negligent)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A change cannot be so great that it would…

A

Impede the contractors ability to perform the work of the construction contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If the owner hires another contractor to perform remedial work, the original construction contract can be…

A

Adjusted to deduct the amount of the payments made to the second contractor… The owner can also deduct by change order the cost of the architects services required by the original contractors default!!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the document used by the architect to outline the work anticipated for a change order?

A

A proposal request – document G709

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Examples of minor modifications that would not involve a change order (change in sum or time)… 3

A
  1. Issuance of color schedule
  2. Revisions to ceiling layout
  3. Interpretations of the contract documents (how many treads in the stair)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The AIA general conditions require the contractor to claim time extensions within how many days after the event which caused the claim?

A

21

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If the owner chooses to hire a second contractor to complete work that an original contractor refused to do, claiming it was outside the scope of the contract documents, the first contractor may be liable for…

A

Refusing to perform work that could’ve been done by change order construction change directiv

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A change order is a written instrument prepared by the architect and signed by the owner, contractor, and architect, stating their agreement upon what three things…

A
  1. Change in the work
  2. Amount of the adjustment, if any, in the Contract Sum
  3. Extent of the adjustment, if any, in the Contract Time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Change orders usually have what kind of effect on performance and labor and material payment bonds for the project?

A

No effect… However the surety must be notified when change orders are issued

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the number of the change order form? Who prepares it?

A

G701… The architect, with info from the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who approves the contractors payments by issuing certificates for payment?

A

The architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which is more common: stipulated sum contracts or cost plus fee contract?

A

Stipulated sum

17
Q

Why is it the architect that issues a contractors certificates of payment?

A

He is unbiased

18
Q

What is the incentive for the contractor to do the work for less than the guaranteed maximum price?

A

Usually the owner will incentivize that by sharing the savings, for instance 25%, with the contractor

19
Q

What is different for the architects with a cost plus fee arrangement for the contractor?

A

The architect has to verify actual labor and material invoices… And is therefore usually entitled to more compensation for added time and liability.

20
Q

Document a 101 assumes the contractor will apply for and receive payment how often?

A

Monthly basis

21
Q

Prior to substantial completion, the architect ______ the work, but at substantial completion, the architect must ____ the work.

A

Observes…. Inspect

22
Q

The certificate of substantial completion, document G704, establishes the time limit for…

A

Final completion

23
Q

What are three reasons the owner would like to delay the date of substantial completion? Why does the contractor want the soonest possible date of substantial completion?

A
  1. The owner loses the retainage and the use of those funds
  2. Incomplete work will appear on the punch list
  3. The owner will have to assume responsibility for security, maintenance, and utilities

The contractor one substantial completion to receive retainage friends and understand there is a finite period of future liability for deficient work.

24
Q

How many days does the owner have to pay the contractor after the architect makes a final certificate for payment?

A

30 days

25
Q

What do you call a draft of the application for payment for the architects review? And why do you make it?

A

A “pencil copy” is used to resolve disagreements to prevent an architect from rejecting the application

26
Q

7 reasons and architect can decline to certify payment in whole or in part.

A
  1. Defective work not remedied
  2. Third-party claims filed or reasonable evidence
  3. Failure of the contractor to pay his subs
  4. Reasonable evidence that the work can’t be completed for the unpaid balance of the contract sum
  5. Damage to the owner or other contractor
  6. Reasonable evidence the work cannot be completed within the contract time (and that the unpaid sum would not cover actual or liquidated damages for anticipated delay)
  7. Persistent failure to carry out the work in accordance with the contract documents
    6.
27
Q

Two reasons why it can be good for an owner to pay a contractor for material stored on site.

A
  1. It can be cheaper because the contractor doesn’t have to add the cost of financing materials
  2. It can benefit the owner if the contractor can purchase materials before prices increase because of inflation
28
Q

What is the process by which the owner withhold money from the contractor is protection against the contractors potential failure to complete the work according to contract.

A

Retainage

29
Q

Who prepares the punch list?

A

The contractor

30
Q

When the owner and contractor cannot agree on the additional cost resulting from a change in the work, who decides?

A

The architect