CHANGE ORDERS & PAYMENTS Flashcards
When he change order is agreed to by both owner and contractor, it becomes a…
Contract modification
What happens in the absence of total agreement on the terms of a change order?
A construction change directive
Construction change directive can only be in the general…
Scope of the contract documents
Four ways to agree upon the contract some for a construction change directive adjustment
- Mutual acceptance of a lump sum
- Unit prices stated in the contract documents or subsequently agreed-upon
- Cost TBD in a matter agreed upon by parties at a mutually acceptable fixed or percentage fee
- The architect determines the cost by monitoring the contractors actual expenditures of time, materials, and overhead.
When the contractor discovers a deficiency in the contract documents, the architect is obligated… But not obligated…
YES: to remedy the deficiency at his expense… By revising drawings and processing the change documents
NO: to pay for the cost of construction caused by the deficiency (unless the owner approves the architect was negligent)
A change cannot be so great that it would…
Impede the contractors ability to perform the work of the construction contract
If the owner hires another contractor to perform remedial work, the original construction contract can be…
Adjusted to deduct the amount of the payments made to the second contractor… The owner can also deduct by change order the cost of the architects services required by the original contractors default!!
What is the document used by the architect to outline the work anticipated for a change order?
A proposal request – document G709
Examples of minor modifications that would not involve a change order (change in sum or time)… 3
- Issuance of color schedule
- Revisions to ceiling layout
- Interpretations of the contract documents (how many treads in the stair)
The AIA general conditions require the contractor to claim time extensions within how many days after the event which caused the claim?
21
If the owner chooses to hire a second contractor to complete work that an original contractor refused to do, claiming it was outside the scope of the contract documents, the first contractor may be liable for…
Refusing to perform work that could’ve been done by change order construction change directiv
A change order is a written instrument prepared by the architect and signed by the owner, contractor, and architect, stating their agreement upon what three things…
- Change in the work
- Amount of the adjustment, if any, in the Contract Sum
- Extent of the adjustment, if any, in the Contract Time
Change orders usually have what kind of effect on performance and labor and material payment bonds for the project?
No effect… However the surety must be notified when change orders are issued
What is the number of the change order form? Who prepares it?
G701… The architect, with info from the contractor
Who approves the contractors payments by issuing certificates for payment?
The architect