THE BIDDING PROCESS Flashcards

1
Q

When an owner contracts with a builder on the basis of qualifications instead of a bid, the agreement is usually based on…

A

Cost of the work plus fee (with a guaranteed maximum price) such as AIA Document A111

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What three things can result in higher bid prices from all contractors?

A
  1. An extremely short bid period
  2. Short construction time
  3. Ambiguous requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Minimum time necessary to prepare a bid

A

2 weeks usually

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Doubling the number of workers does not…

A

Double the amount of work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What kind of contract is used in the normal design/award/build project?

A

AIA Document A101 Owner-Contractor agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are acts of God?

A

Natural or other events beyond the control of owner and contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A contractor familiar with AIA document A201 will expect a project’s special circumstances and specific project requirements to be included in which portion?

A

Supplementary conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

12 items that may be locally required in a public advertisement for bids

A
  1. Project name and location
  2. Name and address of the owner and architect
  3. Date, time, and location that bids are due
  4. Nature and scope of project
  5. Description of project
  6. Will bids be opened and read publicly?
  7. How to obtain bid documents and whether a bid deposit is required to obtain them.
  8. Names and locations of places where bidding documents may be inspected by interested bidders.
  9. Details about proper procedures for submitting bids.
  10. Type and amount of bid security if any
  11. Whether and not an owner can wave in formalities or except a bid other than the lowest
  12. Date the advertisement was first published
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the AIA instructions for bidders document called?

A

A701 .. Designed for use with AIA Document A201 (General conditions)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What comprises the bid documents (5)?

A
  1. Advertisement/invitation to bid
  2. Instructions to bidders
  3. The bid form
  4. Sample bidding and contract forms
  5. The proposed contract documents, including addenda, if they are issued prior to receipt of bids
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

By submitting a bid you implicitly state that…

A

You understand the bidding documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When do you propose substitutions?

A

10 days before bid submittal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If a substitution is approved what does the architect do?

A

Provide addendum including it at least 4 days before bid date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does it mean to be pre-qualified?

A

You’re on a list by a company or agency. Sometime only pre-qualified can bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It’s have to be submitted on time but…

A

A slightly late bid would probably be considered legitimate by a court if the other bids had not yet been opened.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

It’s for private work can be opened publicly or privately, but bids for public work must be opened…

A

Publicly

17
Q

Additives may be either additive or deductive, but which is favorable?

A

Additive, because credit to the contract some for deleted work is usually let me additional cost for the installation of the same work.

18
Q

If it be resubmitted?

A

If retracted and resubmitted before the bid date

19
Q

Can unit can’t be used to determine the low bid?

A

No, only to adjust cost once the contract is awarded, according to changes in the scope

20
Q

In public work, can you change or withdraw to bid?

A

You can withdraw, if it was a clerical error an honest mistake, but you cannot change a bid.

21
Q

When do owner and architect review suppliers and subcontractors?

A

After the bidder has selected… and after the suppliers and subcontractors are excepted and they cannot be substituted after the contract award.