PROJECT FILES, COMPLETION, PROBLEMS Flashcards

1
Q

What is AIA document G807?

A

Project Directory - Basic information about the architects staff and consultants, and the contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is AIA document G805? Who fills it out?

A

List of subcontractors – filled out by the contractor and sent to the architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is AIA document G804?

A

Register of bid documents – basic information about the bid (big deposit, costs for sets of drawings, etc).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does an architect do with the contract between the owner and the contractor?

A

Gets a copy of it and updates it as per change orders, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does a full-time project representative for the architect do?

A

For large and/or complex projects, sometimes a change services, this is a person who monitors the site at all times.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is AIA document B352?

A

Outlines limitations on the project representative’s duties, i.e. making decisions or not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between an architect’s project representative and a “clerk of the works”?

A

The clerk of the works is employed by the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is AIA document G810? What is it for?

A

Transmittal Letter. Written record of what was sent to whom and when.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In which AIA document is the phrase “the Owner and Contractor shall endeavor to communicate with each other through the Architect…”

A

General conditions of AIA document A201

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What a record drawings?

A

They show field changes that occurred during construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Does every project of record drawings?

A

The owner decides

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Transferring the contractors notations of minor changes in the field would be a…

A

Changing services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In addition to the broad warranty on the construction in AIA document A201, specific warrantees on equipment are included in the…

A

Technical specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Move forwards warranties to the owner for review?

A

Cording to AIA document B141, the architect forwards warranties to the owner, who can check for any discrepancies between the terms of the warranty required by the specs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

According to the general conditions, who fills out the punch list (though this varies by location)?

A

Contractor… But the architect can add items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The only two inspections and architect makes of the construction site happen…

A

At substantial completion and final completion

17
Q

If the owner occupies the work before substantial completion, the contractor may claim…

A

It cost/delays because of owner interference

18
Q

What are forms AIA document G706? And AIA document G706A?

A

Contractors Affidavit of Payment of Debts and Claims… And Contractors Affidavit of Release of Liens

19
Q

The owner doesn’t require the contractor to furnish a performance bond or a labor and material payment bond, it is even more important to make sure that…

A

Releases of lien are in order before issuing final certificate for payment

20
Q

How many days does the architect have to resolve disputes between the contractor and owner before that dispute can go into arbitration or mediation?

A

30 days

21
Q

What is AIA document G809?

A

Project Data… Records basic information about the project (owner + team contact, location, etc)

22
Q

Services post completion of the project are considered…

A

Additional services… Unless they relate to a design-related problem, for which an architect might not seek additional compensation

23
Q

When an architect is requested to investigate problems on a project designed by another architect, they are playing the role of…

A

Expert witness