Test Review Flashcards
Who can authorize a change to the contract sum or time?
owner only
What code/standard lists information on Type A + Type B dwelling units?
ICC A117.1 - accessibility standard referenced by the International building code
What are examples of items a contractor’s overhead includes?
anything that cannot be directly attributed to constructing an individual project
- project binders and file folders
- business licensing fees
- leased copy machine at the home office
- salaries for the contractor’s marketing team
Where would information on how to process a field report be found?
specs, div 1
What is a processes that uses a backing bar?
welding steel
- backing bar is placed on backside of a weld to support the molten material during the weld
Per IBC, what % of total units must be type a units?
2%
What does a contractor’s application for payment indicate?
- shows amount of retainage
- shows the value of materials purchased but not installed
- standardizes the payment process
NOT - signify acceptance of work or start the warranty period
Who prepares change orders and construction change directives?
architect
Who would pay for an issue with ADA in the documents?
Architect (their prof liability insurer) it is an error and omission, did not meet the standard of care
Per b101, who is responsible to coordinate the services of the owners consultants?
owner
What are some things contractors review in submittals before passing on to arch?
dimensions
materials
quantities
What is the difference between total project commissioning and traditional comissioing?
- total project validates all systems
- traditional validates one system
How should meetings be conducted in order to monitor the construction process?
regular meetings with regular attendees
(not necessarily an OAC weekly)
What is the basis for the contractor’s pay applications?
schedule of values
If a hazardous material is found on site by the contractor - who are they required to notify first?
owner
architect
(need to provide a written notice)