Close Out Flashcards

1
Q

Per B101, what are arch’s duties as pertains to substantial completion?

A
  • conduct sub comp inspection with owner
  • review punch list
  • issue G704, cert of sub comp to owner
  • share warranties, cert of occ to owner
  • inform owner of remaining punch list cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

liquidated damages

A

sum of money if project is not completed on time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How to establish sub comp?

A
  1. expected date noted in A101
  2. Sub comp date can be changed via change order
  3. punch list must be prepared when project is sub comp
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Substantial completion inspection

A

verifies if punch items are complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens when a building is substantially complete?

A

turn over of utilities and security to owner (from GC)
beginning of warranty periods
arch issues G704 - notes date, punch list, list of nonconforming work
final payment issued, retainage is released

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens when a building is deemed ‘final completion’?

A

arch verifies punch list is complete
there is no cert issued
documented by issuing final certificate of paymnet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What documents are submitted prior to final payment?

A
  • cert to maintain liability insurance
  • memorandum for cert of insurance with no reason for nonrenewal
  • outstanding warranties
  • consent of surety to final payment
  • lien waiver
  • final change order (if applicable)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Responsibilities of arch in close out process?

A
  • review project files
  • invoices paid
  • close out consultant contracts
  • meeting in 1 year
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are arch’s role in commissioning?

A
  • assist CXa to identify systems and timing of construction schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly