Construction Administration Flashcards

1
Q

Bidding Documents

A

Bound into Project Manual. Not part of Contract Documents
Include:
invitation to bid
instructions to bidders
bid forms
bid security information
performance bond requirements
labor and material payment bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Manual

A

part of Procurement Documents
include:
project manual
contract drawings
any issued addenda

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Performance Bond

A

statement by a surety company that obligates complete construction of the project in the event the contractor defaults and cannot finish the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Labor and Materials Bond

A

protects owners from liens and guarantees payment for sub contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bidding Contingency

A

added to base bid by contractor to account for uncertainty of marketplace, cost of materials, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Bid Bond

A

contractor obtains a bid bond from an insurance company, which asserts that the company will pay the difference between the contractors price and the next lowest bidder if the contractor does not take the job. protects owner from being suck with a high bidder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Bid Security

A

certified check submitted with bid by contractor, forfeited if contractor fails to enter into an agreement with the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bid tampering

A

can be caused by:
failure of owner to read bids aloud
allownance of late bids by owner
collusion of bidders otherwise expected to compete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How many bidders do you want for a project?

A

Invite 5-6 companies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ASI

A

Architect’s Supplemental Instructions
can issue minor changes in the work without having to use a change order (which would involve owner)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Spearin Gap

A

in design-bid-build, spearing gap liability is carried by owner. gap is the difference between defect-free documents and the standard of care

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Substantial completion

A

moment when owner can occupy or utilize the work for its intended purpose
- when statue of limitations begins and contractor’s schedule ends
- CA services provided by the architect after substantial completion are usually an Add service
- however a follow up meeting within 1 year of substantial completion is typically in arch’s contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Final completion

A

contractor notifies arch in writing that punchiest and final cleaning is complete and include final application for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

punch list

A

made by GC, arch adds items to during inspection for substantial completion
once punch list is complete, there is a second inspection held to determine final completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

post occupancy evaluation POE

A

performed 3-6 months after occupancy. not basic service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

building commissioning

A

testing and adjusting building systems after installation, prerequisites for LEED cert to ensure systems are operating as efficiently as intended

17
Q

Cxa (Commissioning agent)

A

participated in project from programming phase to completion