Quiz Review Flashcards
What Is AIA D200?
Standard project checklist, lists items that are typically required at each stage of a project
In what ways can bid documents be made available to bidders?
- keep bid docs on file in central plan room
- sending bid docs directly to contractors
- make bid docs available in printing companies and plan rooms
- make digital versions of bid documents available through a project website
Which party submits the certificate of payment, G702?
Arch
- contractors submits an application of payment to arch
- architect reviews and approves/denies
- arch submits certificate of payment to owner
- owner releases payment to contractor
In a DB project, which cost control functions are responsibility of an arch?
- cost estimate of architect’s segment of work in the project
- provide evaluations of design-builder’s budget for the work
After receiving and approving the app for payment, how long does arch have to issue owner a cert of payment?
7 days
What is included in Design phase of commissioning?
- assisting with development of specific owner’s project requirements
- perform independent design review of plans and specs to help meet owner’s goals
- create comm specs for inclusion in bid docs
- assist design team with develop comprehensive training program
What is included in construction phase of commissioning
- create construction phase commish schedule
- review submittals for commissioned systems
- conduct commissioning meetings to coordinate with contractors and discuss schedule, open items, etc.
- perform site visits to review systems installation
- attend equip start ups
- monitor all issues and deficiencies and assist with resolution
what is included in acceptance phase of commissioning?
- functionally test systems and document compliance with drawings and specs
- review operations and maintenance manuals
what is included in post-acceptance phase of commissioning?
- assist with and help owner coordinate owner training
- provide owner with all commissioning related documentation and disposition of all issues and deficiencies
- conduct seasonal testing with assistance of installing contractors and provide end of warranty review of new building
what are 4 phases of commissioning?
- design
- construction
- acceptance
- post acceptance
What is the correct order of steps for the bid process in a public project?
- prep of bid docs
- advertise of bids
- contractor receiving bid docs
- pre-bid meeting
- submission of bids
Where does an arch note nonconforming work?
certificate of substantial completion
who is responsible for paying for a test required by a local jurisdiction?
owner (even if arch missed calling out the test in their specs)
what will a final change order resolve?
allowances
completion bonus or penalty assessments
contingencies
outstanding arch add services
outstanding changes
owner rebates or credits
unit prices
what are 3 approaches when realizing a project through IPD?
multi-party agreement
transitional forms
single-purpose entity