What Is AIA D200?

A

Standard project checklist, lists items that are typically required at each stage of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In what ways can bid documents be made available to bidders?

A
  • keep bid docs on file in central plan room
  • sending bid docs directly to contractors
  • make bid docs available in printing companies and plan rooms
  • make digital versions of bid documents available through a project website
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which party submits the certificate of payment, G702?

A

Arch
- contractors submits an application of payment to arch
- architect reviews and approves/denies
- arch submits certificate of payment to owner
- owner releases payment to contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In a DB project, which cost control functions are responsibility of an arch?

A
  • cost estimate of architect’s segment of work in the project
  • provide evaluations of design-builder’s budget for the work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

After receiving and approving the app for payment, how long does arch have to issue owner a cert of payment?

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is included in Design phase of commissioning?

A
  1. assisting with development of specific owner’s project requirements
  2. perform independent design review of plans and specs to help meet owner’s goals
  3. create comm specs for inclusion in bid docs
  4. assist design team with develop comprehensive training program
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is included in construction phase of commissioning

A
  1. create construction phase commish schedule
  2. review submittals for commissioned systems
  3. conduct commissioning meetings to coordinate with contractors and discuss schedule, open items, etc.
  4. perform site visits to review systems installation
  5. attend equip start ups
  6. monitor all issues and deficiencies and assist with resolution
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is included in acceptance phase of commissioning?

A
  1. functionally test systems and document compliance with drawings and specs
  2. review operations and maintenance manuals
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is included in post-acceptance phase of commissioning?

A
  1. assist with and help owner coordinate owner training
  2. provide owner with all commissioning related documentation and disposition of all issues and deficiencies
  3. conduct seasonal testing with assistance of installing contractors and provide end of warranty review of new building
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what are 4 phases of commissioning?

A
  1. design
  2. construction
  3. acceptance
  4. post acceptance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the correct order of steps for the bid process in a public project?

A
  1. prep of bid docs
  2. advertise of bids
  3. contractor receiving bid docs
  4. pre-bid meeting
  5. submission of bids
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where does an arch note nonconforming work?

A

certificate of substantial completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

who is responsible for paying for a test required by a local jurisdiction?

A

owner (even if arch missed calling out the test in their specs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what will a final change order resolve?

A

allowances
completion bonus or penalty assessments
contingencies
outstanding arch add services
outstanding changes
owner rebates or credits
unit prices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what are 3 approaches when realizing a project through IPD?

A

multi-party agreement
transitional forms
single-purpose entity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what is it called when the contractor decides to speed up the construction schedule to get a bonus?

A

voluntary acceleration

17
Q

how long does the GC have to notify the owner/arch of conditions that differ from the contract documents?

A

14 days

18
Q

who does the commissioning agent usually work for?

A

owner

19
Q

what is directed acceleration?

A

when contractor is requested to speed up the construction by the owner

20
Q

what must GC do before owner is required to issue final payment?

A

obtain consent from surety for final payment
submit to arch an affidavit that payrolls, bills for materials, equip have been paid for
submit data establishing payment of satisfaction of obligations, such as receipts, releases, waivers of liens

21
Q

when should you consider rejecting a bid?

A

bids made without a required bid bond
bids with irregularities
bids that have not taken into account the required specs