Project Delivery & Bidding Flashcards

1
Q

When does bidding occur in DBB?

A

After design docs are complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When does bidding occur in multiple prime/fast track?

A
  • bidding for each portion of work, once design docs are complete
  • may be required for publicly funded projects
  • used to accelerate construction schedule
  • required increased owner involvement or CM
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When does bidding occur in D-negotiate-bid?

A

-owner requests proposals (not bids) once design docs are complete
- owner chooses 1+ GC, then decides upon cost
- generally on private projects
- can allow owner to pre-qual a GC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When does bidding occur in CMc?

A
  • Cmc brought on during design phase as advisor, then becomes constructor
  • advises on $, schedule, constructibility
  • no bidding
  • CMc negotiates with owner for GMP
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When does bidding occur in DB?

A
  • no bids
  • price determined upfront, based on owner’s program requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When does bidding occur in Bridging?

A
  • designer prepares schematic plans
  • owner uses schematic plans to solicit bid from DB entity
  • then same process as DB
  • improves owners control & understanding of cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When does bidding occur in IPD?

A
  • no bid or negotiation
  • team agrees on cost early on
  • all one entity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What’s in the procurement docs?

A
  • project manual
  • contract drawings
  • addenda
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What’s in the project manual?

A
  • sup conditions
  • A701 instructions to bidders
  • bid bond
    -bid security
  • A305 con’s qual statement
  • bid form
    -specs
    -geotech survey & other site conditions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

QBS? (quality based selection)

A

TOP PRIORITIES are quality, speed of work, subjective criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VBS? (value based selection)

A

select GC for any reason besides cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is a stipulated sum bid provided?

A

best for when scope is clear

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When is a GMP bid provided?

A

construction documents not complete (like fast track)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is a Cost+ (t&m) bid provided?

A

small projects, renovations, change order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When is a unit fee bid provided?

A

undefined scope of work or repetitive work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

when is a large price bid provided?

A

Design Build projects