Test Questions Review Flashcards

1
Q

What is last day contractor can submit questions to design team ahead of bid date?

A

7 days prior to the bid date (calendar days)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does a bidding contingency cover?

A

provisions for uncertainty of the marketplace and fluctuating prices
meant to offset actual costs if prices rise due to market forces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What to do when mold is discovered?

A

if over 10sf, involve a mold professional. recommended by EPA. once mold professional clears the area, fix the underlying issue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are engineering assessments that can happen in the field to satisfy a structural concern raised by an AHJ?

A

In situ load testing (simulates anticipated loads)
structural analysis (determine if current structure is inadequate and in need of additional structural members)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is G716, RFI, used for?

A
  • to obtain info that the requesting party cannot obtain through research, document review, or other reasonable means
  • architect/owner/contractor/or other party to request further info from each other during construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is G710, ASI, used for?

A

used by arch to issue additional instructions or interpretations, or to order minor changes in the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is AIA A305, Contractor’s Qual statement, used for?

A

for owner to verify the background, references, and financial stability of any contractor being considered during the bidding or award phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is AIA G701, Change Order, used for?

A

for implementing changes in the work agreed to by the owner, contractor, architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does a slump test help quantify?

A

workability of mixture. a collapsed slump means the mixture is too wet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does a cylinder test help quantify?

A

used to test the compressive strength of hardened concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In order to receive restitution, what can a contractor claim?

A

Unjust enrichment - when a party unfairly benefits at the expense of the other part

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is force majeure?

A

when unforeseeable circumstances prevent someone from fulfilling a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

For what reasons would a performance mock up (PMU) be performed?

A
  • to ensure safety and welfare of future occupants by checking for structural integrity
  • to pinpoint any ares of weakness as they pertain to water penetration
  • to validate design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is true of a stipulated sum contract?

A
  • unit prices are permitted
  • actual construction costs and bid diff are absorbed as profit/loss by contractor
  • competitively bid projects most often use this type of contract delivery
  • owner compensates the contractor a fixed price for providing work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What costs are included in a LCA?

A

operation costs
financing cost
maintenance cost
initial cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

At what time is a building considered ‘enclosed’ ?

A

When the openings are installed and thermal/moisture protection is complete

17
Q

What would a design build project delivery method help streamline?

A

submittals
(not permits, subcontractors, or pay applications)

18
Q

Per AIA A701, Instructions to bidders, what must a bidder do?

A
  • bid is based upon materials, equipment, systems required by bidding documents without exception
  • bidder has read and understands the provisions for liquidated damages
  • bidder must visit the site
19
Q

What does NRC, Noise Reduction coefficient, measure?

A

measures amount of energy absorbed by a material when the sound waves reach a surface

20
Q

What does sound transmission class, STC, measure?

A

represents a material’s ability to block airborne sound

21
Q

What does impact isolation class, ICC, measure?

A

measures an assembly’s ability to absorb noise caused by impact to floor/ceiling assembly

22
Q

What type of building would require an electrical power commissioning plan?

A
  • any building that has a critical operations power systems (COPS), meaning it needs to maintain its ability to operate during an emergency
  • ie. bank, hospital
23
Q

If a supplier/subcontractor messes up, who is responsible to cover the cost of the error?

A

the contractor