Tendering Flashcards
What are the different forms of procurement?
Design & Build –
Traditional –
Management Contract -
PFI -
What are the different forms of tendering?
Competitive & Non-competitive
Within Competitive tendering you have:
Open Tendering
Selective Tendering (Single Stage & Two stage)
Serial Tendering
Within Non-Competitive tendering you have:
Nominated Negotiated Tendering (Single Stage & Two Stage)
Explain the Selective Tendering Process?
→ Shortlist - Find contractors within the area able suitable to tender for the work
→ Selection Questionnaire - to see if they are suitable/qualified to conduct the works
→ Compile a tender list to of 4-6 tenderers
→ Invite to tender - Send a tender package to the selected tenderers
→ Question period
→ Tenderers return - on the set date
→ Review tender submissions to see for any errors
→ Compile a tender report and send recommendation to client
→ Client makes a decision
→ Notify wining tenderer
→ Stand still period - questions / negotiation
→ Tender becomes contractor and other tenders are notified.
What would you do if there are any errors?
The method for dealing with errors would be stated in tender package; you have two options:
Option 1: Accept or Withdraw
Option 2: Accept of Amend
What is the difference between a Singe Stager & a Two Stage tender?
→ Single stage is conducted once the tender documents have been produced.
→ Two stage tender is to achieve early appointment of the contractor ahead of the completion design, and a potentially quicker start on site.
What is included in an invitation to tender?
→ The form of information to tender → Project description → Drawings listed Specification → BoQ / Schedule of works / Schedule of Rates → The Employers Requirement → Instruction to tenderers → Any additional documents
What is in a Tender Documents?
Illustrative - Drawings
Qualitative - Specification
Quantitative - BoQ / Schedule of works / Schedule of Rates
What is a Specification?
‘It is a written description of the quality of the built product and its component parts.’
Performance Specification - define the characteristics of the final product… clients will state what quality of finish they are after in essence or brief.
Descriptive Method Specification - A written document providing detailed descriptions of the quality required in terms of construction, Workmanship and materials.
What is the Difference between a Bill of Quantities, Schedule of works and Schedule of Rates
→ Bill of Quantities
Only a qualified Quantity Surveyor can produce
In accordance to SMM7 (To be superseded by NRM)
It illustrates the items, quantities, units
Within the Bill of Quantities You have Preliminaries and Measured work
→ Schedule of Work
Is an a document that list the main sections of work for the contractor to price in a lump sum basis
→ Schedule of Rates
Is a list of items and their prices but the work required is not known at the outset A comprehensive Schedule of Rates is the same as a Bill of Quantities, but without the quantities
What is the significance of a Pre-Start meeting?
- Initial meeting before Date of Possession
- To establish contract procedures, administration, standards & quality
- Tool to ensure all parties are aware of duties -Chaired by Contract Administrator
What are Bills of Quantity?
Quantitative product information. Document itemises materials, parts and labour and their costs. Typical headings:
- Preliminaries
- Measured Works
- Prime Costs /Provisional Sums
What are the function of Bills of Quanitities and how are they useful to the design and construction team?
- Forms a list of the works which are quantified for pricing
- Prepared using standardised methods of measurement (NRM 2)
- Used to provide a level playing field for tender responses
- Assists in the preparation of interim and final valuations
What are the preliminaries in a Bills of Quantities?
Items which are cover the specific circumstances to undertake works but which are not included elsewhere in the tender documents.
- Site description
- Access
- Ste security
- Statutory approvals
- Accommodation/equipment requirements
- Site meetings
- Disturbance to 3rd parties
- Warranties and bonds
- Quality checks
- Health and Safety
- Programme
- Valuation and payment dates
- Record drawings
- Guarantees
- Dayworks
What are dayworks?
Items which cannot properly be measured and priced in accordance with the BoQ and therefore have to be dealt with on a labour/materials/plant basis, plus % profit and overheads:
- Labour costs =Current agreed national rates
- Materials =actual cost
- Plant costs =set by RICS and ICE
- Tenderer states his % profit in the dayworks section of BoQ
What is a method of measurement?
→ Standard way of calculating measured works.
→ RICS New Rules of Measurement 2 (NRM2) havereplaced Standard Method of Measurement (SMM7).
→ NRM2 makes BoQ quicker and simpler to prepare.
→ JCT issued a NRM Updaterequiring NRM2 to be used in place of SMM7 in all contract documents
What is a prime cost sum?
NRM2 definition:A sum of money included I a unit rate to be expended on materials or goods from suppliers e.g. ‘door furniture at £75 per door’
Excludes all costs associated with fixing / installation, design fees, prelims etc.
What is a provisional sum?
A sum allowed in BoQ for works/goods which cannot be accurately quantified/detailed at the time of tender
Tenderer allows sum plus profit%
Defined (some info available) e.g. sketch signage proposals
Undefined (no info available) e.g. additional drainage