Technical - Design Economics and Cost Planning Flashcards
(128 cards)
What are the New Rules of Measurement?
A coordinated suite of measurement rules that give a consistent approach and is best practise to us.
Name the three NRM documents?
NRM1 – cost estimating and planning.
NRM2 – Detailed measurement for building works.
NRM3 – Cost estimating and planning for maintenance.
What NRM document would I use for cost planning?
NRM 1.
What does NRM2 do?
A guide and template to produce bills of quantities and schedule of works for capital projects.
How does NRM deal with risk?
By not allocating a standard percentage as a lump, but by trying to assess in four different categories.
1. Employer change.
2. Employer other.
3. Design development.
4. Construction.
What are the four levels of elements in NRM?
Group element.
Element.
Sub-element.
Component.
Name some of the standard preliminaries in NRM2?
Employer’s requirements.
Site accommodation.
Management and staff.
Temporary services.
Security.
Records and manuals.
Insurances/ bonds/ guarantees.
What is an Order of Cost Estimate?
High level cost based on m2 or per functional unit. Applies to RIBA 0 and 1.
What is the purpose of an Order of Cost Estimate?
To help work out if the project is financially viable by providing an initial estimate using appropriate data. Avoid the client wasting their time on design and legal fees if it’s not affordable.
How do you include professional fees in an Order of Cost Estimate?
As a percentage.
What is the difference between a cost estimate and a cost plan?
An estimate is a high level cost based on the employer’s requirements and is calculated on a m2 basis. Used at RIBA 0 or 1.
A plan is more detailed and provides an elemental breakdown of costs. Used at RIBA 2 and 3.
What is a pre-tender estimate?
A costed BoQ or SoW from RIBA 4 information and using costed data. To provide the client with an idea of what the contractors will tender.
How would I prepare an estimate for M&E works?
Either ask our M&E QS to assist for that section, use historic data for simpler items. Consult with the M&E Engineers for more specialist items.
What is a provisional sum?
An allowance included in the tender documents or contract for a specific element of work that does not have enough detail for tenderers to accurately price.
How can a provisional sum be expended?
Via an instruction from the Contract Administrator for JCT contracts.
How are provisional sums dealt with in the final account?
By omitting the provisional and adding the actual cost.
What are the risks of using provisional sums?
You include an insufficient amount and the cost is higher.
The nature of the work changes as more information becomes available and it takes longer than allowed for at tender stage.
Name the two types of provisional sums.
Defined and undefined.
What is a defined provisional sum?
A specific piece of work that the contractor has accounted for in their price and programme. The contractor takes the risk that their estimate will be sufficient.
What is an undefined provisional sum?
The client takes the risk and the contractor does not account for them in their price and programme. The client may have to grant an extension of time or additional payment.
Can the contractor claim an extension of time or prelims costs for a defined provisional sum?
No. It should already be factored into their programme and tendered prelims.
What are the RIBA stages of work?
0 – Strategic
1 – Preparation & Brief
2 – Concept Design
3 – Spatial Coordination
4 – Technical Design
5 – Manufacture & Construction
6 – Handover and Close Out
7 – In Use
What are the main tasks of the cost manager?
Prepare initial cost advice.
Produce cost estimates and cost plans.
Prepare pricing documents for tender.
Evaluate and adjudicate tenders.
Prepare interim valuations.
Value instructions.
Analyse and comment on contractor’s claims.
Manage expenditure of the risk allowance.
Review ongoing costs and take action to avoid budget overspend.
Negotiate final account.
Issue financial reports.
What is the purpose of cost planning?
To ensure employers are provided with value for money on their proposed projects.
Help designers and clients arrive at a practical and balanced design to suit their budget.
Provide information that helps the client make informed decisions.