Technical - Contract Administration Flashcards
What is the role of the Contract Administrator under the JCT contract?
The person responsible for administering the contract.
Has to act honestly and reasonably as their decisions can be questioned under the dispute resolution procedure.
Issues timely information and pre-agreed information.
Issues instructions, variations and extensions of time.
Assesses delays and claims.
Works with the QS to review and approve monthly valuations, variations and loss and expense.
Issues the payment certificate.
What if a contractor does not comply with an instruction issued under a JCT contract?
The contract states that ‘The contractor shall forthwith comply…’ so if they don’t the CA must issue a notice requesting compliance with their previously issued construction.
Failure to comply within 7 days of the instruction means that the CA can get another firm to carry out the work and deduct the amount from the contract sum.
Ongoing failures can lead to the termination of the contract.
A contractor is not obligated to carry out a variation if it is dangerous or such work that is materially different from the agreed contract works. If that is the case then the contractor must notify the CA of their decision in writing.
What is an Employer’s Agent role?
Usually for Design & Build contracts and they are appointed by the client to manage the project on their behalf. They act as Project Manager and Cost Manager. They are the lead consultant on the project but appoint other consultants under them. Their duties include:
Develop the client’s brief.
Carry out a pre-tender estimate.
Develop and monitor the programme.
Lead the professional team.
Compile the tender docs.
Manage the tender process and award the contract.
Sign off the contractor’s detailed design.
Chair and record meetings.
Monitor the quality of a project.
Manage the budget.
Carry out valuations and instruct variations.
Organise handover/ soft landings.
What is the difference between an Employer’s Agent and a Contract Administrator?
The EA is the client’s advisor and is required to protect the client’s interests whereas the CA must act impartially, making decisions even if they are detrimental to the client.
What status does the programme have in a JCT contract?
None.
What is practical completion?
The point at which the contractor has completed the project and hands it over to the client.
The building is fit for use although there may be some outstanding defects and small works that need to be completed.
But it must be used for its intended purpose and be safe to occupy. I usually include a list of requirements in the tender and contract documentation that the contractor must complete to achieve practical completion.
Can the Practical Completion certificate be rescinded once issued?
No.
What happens when Practical Completion is issued?
Usually 50% of the retention is released.
The 12-month defect period starts.
The client must take over responsibility for insuring the building.
The ability to impose liquidate damages stops.
What is a non-completion certificate?
Issued by the Contract Administrator to certify that the works, or section of works, have not been completed by the contractual completion date.
What are the consequences of a non-completion certificate?
The employer has the right to withhold liquidated damages if they follow the process of:
1. Issuing a non-completion certificate.
2. Write to the contractor to state their intention of withholding LADs.
3. Issue a pay-less notice.
What are LADs (Liquidated and Ascertained Damages)?
Allow the client to recover losses as the result of the contractor not fulfilling their duties. They cannot be punitive and must be an accurate assessment of the loss experience by the client because of the delay.
What happens if the Contract Administrator thinks the construction work has been carried out incorrectly or that there is a defect?
They can issue an instruction for the contractor to open-up the area in question to inspect the area or carry out further tests.
Who bears the costs of these opening-up works?
The client unless the contractor is found to have no carried out the works in accordance with the contract documents. Then the contractor must pay for the opening works and rectification of the defect.
What is an extension of time?
The Contract Administrator is able to extend the completion date so that the client postpones their ability to claim liquidated damages, and the contractor is not worrying that their completion date is at large.
What is the procedure for claiming an extension of time?
The contractor should write to the Contract Administrator to inform them of a likely delay as soon as they think one will occur.
They should identify the cause of the delay, stipulate the relevant event and propose a revised completion date.
The Contract Administrator must reply to the contractor in writing with their decision.
The contractor must take all efforts to mitigate the effect of the delay.