Stakeholder Management Flashcards

1
Q

Primary Project Stakeholder Management Processes

A
  • Identify Stakeholders
  • Plan Stakeholder Management
  • Manage Stakeholder Engagement
  • Control Stakeholder Engagement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Stakeholder Analysis

A
  • Technicque of systematically gasthering ans alayzing qualitative and quantitative information to determoine whose interestes should be taken into account throughout the project
  • Generally follows steps below:
    • identify all potential stakeholders and relevant information
    • analyze the potential impact or support each stakeholder could generate
    • assess how key stakeholders are likely to react
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Classification Models for Stakeholder Analysis

A
  • Power/Interest Grid
  • Power/Influence Grid
  • Influence/Impact Grid
  • Salience Model
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Power/Interest Grid

A
  • grouping based on level of authority (power) and concern (influence)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Power/Influence Grid

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Influence/Impact Grid

A
  • Analysis based on active involvement (influence) and ability to effect changes to the execution (impact)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Salience Model

A
  • Stakeholder analysis based on power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Stakeholder Grid Meanings

A
  • Low Power, Low interest: Monitor
  • Low Power, High Interest: Keep Informed
  • High Power, Low interest: Keep Satisfied
  • High Power, High Interest: Manage Closely
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Stakeholder engagement level

A
  • Unaware: unaware of project and potential impacts
  • Resistant: Aware of proejct and potential impacts and resistant to change
  • Neutral: Aware of project, yet neither supportive nor resistant
  • Supportive: Aware of project and potential impacts and supportive to change
  • Leading: Aware of project potential impacts and actively engaged in ensuring the project is a success
How well did you know this?
1
Not at all
2
3
4
5
Perfectly