Formulas Flashcards

0
Q

Earned Value (EV)

A
  • Value of work performed expressed in terms of the approved budget assigned to that work for an activity or WBS component
  • EV = CV + AC
  • Progress Indicator
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Planned Value (PV)

A
  • Authorized budget assigned to the work to be accomplished on an activity or WBS component
  • PV = EV-SV
  • Progress Indicator
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Performance Index (SPI)

A
  • A measure of schedule efficiency on a project.
  • A measure of progress achieved compared to progress planned on a project
  • SPI = EV/PV
  • Efficiency Indicator
  • Predicts the completion date & used with CPI to forecast the project completion estimates
  • Value < 1.0 = behind schedule
  • Value > 1.0 = ahead of schedule
  • Value = 1.0 = right on schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Performance Index (CPI)

A
  • A measure of cost efficiency on a project.
    A measure of the value of work completed compared to the actual cost on a project
  • CPI = EV/AC
  • Efficiency Indicator
  • Value < 1.0 = Overrun (negative funds)
  • Value > 1.0 = Underrun (leftover funds)
  • Value = 1.0 = Right on budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimate at Completion (EAC)

A
  • The expected total cost of completing all work expressed as the sum of the actual cost to date and estimate to complete.
  • May be calculated on performance to date or estimated by the project team based on other factors
  • EAC = AC + ETC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

EAC Forecast

for ETC work performed at the budgeted rate

A
  • This method accepts the actual project performance to date & predicts that all future ETC work to be accomplished at the budgeted rate
  • EAC = AC + BAC - EV
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

EAC Forecast

for ETC work performed at the CPI

A
  • Assumes what the project has experienced to date can be expected to continue in the future
  • EAC = BAC/[CPI]C
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EAC Forecast

for ETC work considering both SPI and CPI factors

A
  • Assumes a negative cost performance and a need to meet a schedule commitment
  • EAC = AC + (BAC-EV)
                           (CPI<sup>c</sup> x SPI<sup>c</sup>)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

To Complete based on Performance Index

(TCPI)

A
  • The calculated projection of cost performance that must be achieved to meet a goal (BAC or EAC)
  • If the BAC is no longer reachable, develop a EAC. When the EAC is approved by sponsor it becomes the BAC
  • Based on BAC
    • TCPI = (BAC - EV)
                         (BAC - AC)
  • Based on EAC
    • TCPI = (BAC - EV)
                         (EAC - AC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Budget at Completion (BAC)

A
  • The sum of all the budgets established for the work to be performed on a project or WBS component or schedule activity.
  • Used to measure, monitor, and control overall cost performance on the project.
  • The total planned value for the project.
  • BAC = PVc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lines of Communication

A
  • The number of potential communication channels or paths
  • Indicates of the project communications complexity
  • n(n-1)/2
  • n = number of stakeholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Actual Cost (AC)

A
  • Total cost actually incurred and recorded in accomplishing work performed for an activity or WBS component.
  • This AC must correspond in definition and coverage to whatever was budgeted for the PV and the EV.
  • AC = EV - CV
  • Progress Indicator
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Variance (CV)

A
  • The amount of budget deficit or surplus at a given time
  • relationship between physical work and costs spent
  • CV = EV - AC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Schedule Variance (SV)

A
  • A measure of schedule perfomance on a project
  • The amount of time a schedule is ahead or behind scheduled delivery date
  • Efficiency Indicator
  • SV = EV - PV
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Eatimate to Complete (ETC)

A
  • Estimate of costs to complete the project from point in time
  • ETC = EAC - AC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly