Formulas Flashcards
0
Q
Earned Value (EV)
A
- Value of work performed expressed in terms of the approved budget assigned to that work for an activity or WBS component
- EV = CV + AC
- Progress Indicator
1
Q
Planned Value (PV)
A
- Authorized budget assigned to the work to be accomplished on an activity or WBS component
- PV = EV-SV
- Progress Indicator
2
Q
Schedule Performance Index (SPI)
A
- A measure of schedule efficiency on a project.
- A measure of progress achieved compared to progress planned on a project
- SPI = EV/PV
- Efficiency Indicator
- Predicts the completion date & used with CPI to forecast the project completion estimates
- Value < 1.0 = behind schedule
- Value > 1.0 = ahead of schedule
- Value = 1.0 = right on schedule
3
Q
Cost Performance Index (CPI)
A
- A measure of cost efficiency on a project.
A measure of the value of work completed compared to the actual cost on a project - CPI = EV/AC
- Efficiency Indicator
- Value < 1.0 = Overrun (negative funds)
- Value > 1.0 = Underrun (leftover funds)
- Value = 1.0 = Right on budget
4
Q
Estimate at Completion (EAC)
A
- The expected total cost of completing all work expressed as the sum of the actual cost to date and estimate to complete.
- May be calculated on performance to date or estimated by the project team based on other factors
- EAC = AC + ETC
5
Q
EAC Forecast
for ETC work performed at the budgeted rate
A
- This method accepts the actual project performance to date & predicts that all future ETC work to be accomplished at the budgeted rate
- EAC = AC + BAC - EV
6
Q
EAC Forecast
for ETC work performed at the CPI
A
- Assumes what the project has experienced to date can be expected to continue in the future
- EAC = BAC/[CPI]C
7
Q
EAC Forecast
for ETC work considering both SPI and CPI factors
A
- Assumes a negative cost performance and a need to meet a schedule commitment
- EAC = AC + (BAC-EV)
(CPI<sup>c</sup> x SPI<sup>c</sup>)
8
Q
To Complete based on Performance Index
(TCPI)
A
- The calculated projection of cost performance that must be achieved to meet a goal (BAC or EAC)
- If the BAC is no longer reachable, develop a EAC. When the EAC is approved by sponsor it becomes the BAC
- Based on BAC
- TCPI = (BAC - EV)
(BAC - AC)
- TCPI = (BAC - EV)
- Based on EAC
- TCPI = (BAC - EV)
(EAC - AC)
- TCPI = (BAC - EV)
9
Q
Budget at Completion (BAC)
A
- The sum of all the budgets established for the work to be performed on a project or WBS component or schedule activity.
- Used to measure, monitor, and control overall cost performance on the project.
- The total planned value for the project.
- BAC = PVc
10
Q
Lines of Communication
A
- The number of potential communication channels or paths
- Indicates of the project communications complexity
- n(n-1)/2
- n = number of stakeholders
11
Q
Actual Cost (AC)
A
- Total cost actually incurred and recorded in accomplishing work performed for an activity or WBS component.
- This AC must correspond in definition and coverage to whatever was budgeted for the PV and the EV.
- AC = EV - CV
- Progress Indicator
12
Q
Cost Variance (CV)
A
- The amount of budget deficit or surplus at a given time
- relationship between physical work and costs spent
- CV = EV - AC
13
Q
Schedule Variance (SV)
A
- A measure of schedule perfomance on a project
- The amount of time a schedule is ahead or behind scheduled delivery date
- Efficiency Indicator
- SV = EV - PV
14
Q
Eatimate to Complete (ETC)
A
- Estimate of costs to complete the project from point in time
- ETC = EAC - AC