Site Work DD Flashcards

1
Q

runoff

A

stormwater that accumulates on site in excess of what can be absorbed by ground

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

above ground drainage system

A

porous paving, sheet flows, gutters, swales, channels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

underground drainage system

A

drains, enclosed storm sewers to carry runoff off site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

capacity of drainage system

A

based on size of area, runoff coefficient (fraction of water not absorbed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

minimum slope of sewer pipe

A

0.5%-2%, depends on size of pipe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

road slope

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

crown

A

gradual cross slope on road for runoff

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

typical lane road dimension

A

12’w

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

typical double road dimension

A

24’w

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

typical radius of cul de sac

A

40’r

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

pedestrian circulation walkway dimension & rules of thumb

A

5’ MIN, 6’-8’ better
provide lighting
don’t make cross busy roads
8% max slope, 6% is beter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

typical slope of parking lot

A

1.5%-2%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

ideal pitch away from building

A

2%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

recreation area slope

A

3% max

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

building site slope

A

10%MAX, 4% preferred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

ramp max slope

A

8%, 1:12

17
Q

slope of site to be planted with grass

A

less than 25%

18
Q

slope of site that must be terraced

A

25%-50%

19
Q
A