Sec 5- Capacity Management and Production Activity Control Flashcards
Define Capacity Requirements Planning (CRP)
The process of determining in detail the amount of labor and machine resources required to accomplish the tasks of production. Provides a validity check of the priority plan.
Define Capacity Management
The function of establishing, measuring, monitoring, and adjusting limits or levels of capacity in order to execute all manufacturing schedules
What is capacity management called at each of these levels?
1) S&OP
2) master scheduling
3) MRP
4) PAC
1) resource planning
2) RCCP
3) CRP
4) input/output control and operations sequencing
List the 4 steps of the Capacity Planning Process
1) determine available capacity
2) use priority plan to determine amount of capacity required for each time period
3) Sum up the capacities for each time period required for each resource and compare to available capacity for that resource
4) Resolve differences between available and required capacities.
Define Capacity Available
the capability of a system or resource to produce a quantity of output in a particular time period. Can be “rated” or “demonstrated”
How is demonstrated capacity determined?
From historical data
How is rated capacity calculated?
available time X utilization X efficiency
How is available time calculated?
number of machines X hours a day X days a week
How is utilization calculated?
hours actually worked / available hours X 100
How is efficiency calculated?
standard hours of work / hours actually worked X 100
What are the 5 key inputs into the Capacity Requirements Plan (CRP)
Available capacity load data requirements shop calendar lead-time elements
Define Load
the amount of planned work scheduled for and actual work released to a facility, work center, or operation for a specific span of tie. Usually expressed in standard hours of work
How is operation times calculated?
number of pieces x run time per piece + setup time
What sort of data is required to do the Capacity Requirements Plan (CRP)?
open shop orders planned order releases where work is done time needed (standard hours) lead times work center capacity
What is the Manufacturing Calendar?
provides information on the actual number of working days available in each week or month