Sec 5- Capacity Management and Production Activity Control Flashcards

1
Q

Define Capacity Requirements Planning (CRP)

A

The process of determining in detail the amount of labor and machine resources required to accomplish the tasks of production. Provides a validity check of the priority plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Capacity Management

A

The function of establishing, measuring, monitoring, and adjusting limits or levels of capacity in order to execute all manufacturing schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is capacity management called at each of these levels?

1) S&OP
2) master scheduling
3) MRP
4) PAC

A

1) resource planning
2) RCCP
3) CRP
4) input/output control and operations sequencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List the 4 steps of the Capacity Planning Process

A

1) determine available capacity
2) use priority plan to determine amount of capacity required for each time period
3) Sum up the capacities for each time period required for each resource and compare to available capacity for that resource
4) Resolve differences between available and required capacities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define Capacity Available

A

the capability of a system or resource to produce a quantity of output in a particular time period. Can be “rated” or “demonstrated”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is demonstrated capacity determined?

A

From historical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is rated capacity calculated?

A

available time X utilization X efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is available time calculated?

A

number of machines X hours a day X days a week

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is utilization calculated?

A

hours actually worked / available hours X 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is efficiency calculated?

A

standard hours of work / hours actually worked X 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the 5 key inputs into the Capacity Requirements Plan (CRP)

A
Available capacity
load
data requirements
shop calendar
lead-time elements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define Load

A

the amount of planned work scheduled for and actual work released to a facility, work center, or operation for a specific span of tie. Usually expressed in standard hours of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How is operation times calculated?

A

number of pieces x run time per piece + setup time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What sort of data is required to do the Capacity Requirements Plan (CRP)?

A
open shop orders
planned order releases
where work is done
time needed (standard hours)
lead times
work center capacity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the Manufacturing Calendar?

A

provides information on the actual number of working days available in each week or month

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the 5 components of Manufacturing Lead Time?

A

1) Queue- time spent waiting before an operation begins
2) Setup - time spent getting ready for an operation
3) Run - time spent performing an operation
4) Wait- time spend waiting after operation ends
5) Move - time spent physically moving materials between operations

17
Q

Define Load Profile

A

a graphical comparison of each work center’s available capacity and the load established by the planned and released orders for each time period of the plan

18
Q

What are the 4 objective of the Production Activity Control (PAC)?

A

1) Execute the MPS and MRP
2) Optimize use of resources
3) Minimize WIP
4) Maintain customer service

19
Q

What are the 3 functions of the PAC?

A

1) Plan/Replan - ensure resources are available, schedule start and completion dates, replan if necessary
2) Implement- release shop orders to manufacturing and prepare “shop packet”
3) Control - establish/maintain priority list, monitor control WIP/lead times/queues, track and report production status, report work center performance data

20
Q

What are the 4 basic scheduling and loading techniques?

A

Forward scheduling
Backward scheduling
Infinite loading
Finite loading

21
Q

Define Forward Scheduling

A

Activities are scheduled form a known start date through a finished date

22
Q

Define Backward Scheduling

A

Activities are schedule back from the due date

23
Q

Define Infinite Loading

A

Assumes that capacity is infinite at any work center

24
Q

Define Finite Loading

A

Assumes there is a definite limit to capacity at any work center

25
Q

Define Priority Control

A

Communicating start and completion dates for orders that are to be run at each workstation

26
Q

Define Critical Ratio (CR)

A

A dispatching rule that calculates a priority index number by dividing the time to due date remaining by the expected elapsed time to finish the job

27
Q

Define Input/output Control (I/O)

A

Technique for capacity control. Monitors both planned/actual inputs and planned/actual outputs.

28
Q

Define Flow Control

A

Used in a continuous manufacturing system where materials flow through production at a established rate using fixed routing and dedicated machinery.