Sec 4: Material Requirements Planning Flashcards

1
Q

Define Material Requirements Planning

A

A set of techniques that uses bill of material data, inventory data, and the master production schedule to calculate requirements for materials. Will make suggestions on when to replenish and when/if to adjust current replenishment plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Capacity Requirements Planning (CRP)

A

The process of determining in detail the amount of labor and machine resources required to accomplish the tasks of production.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define Production Activity Control (PAC)

A

The function of routing and dispatching the work to be accomplished through the production facility and performing supplier control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define Planning Bill

A

Plans material requirements for a family of end products for which there are several variations based on options for one or more components. I.E. a bicycle would have multiple paint color options, wheel sizes, etc. Would show how much blue, red, green paint to order based on forecast total for bikes and historical order percentages for each color.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define Pegging Report

A

Similar to a where-used report but shows only those parent items for which there is an existing requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Lead-time Offset

A

a technique used in MRP where a planned order receipt in one time period requires the release of that order in an earlier time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define MRP Planned Orders

A

Created by the computer, exists only within the computer, and may be changed or deleted by the computer during subsequent processing if conditions change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define MRP Firm Planned Order (FPO)

A

A planned order that has been frozen in quantity and time. Computer is not allowed to change it automatically. Computer requests change via exception messages and then planner must decide whether to change the order or not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define MRP Released Orders

A

Once released a planned order becomes an open order to the factory floor or supplier. Authorizes purchasing to buy materials and manufacturing to make the component

How well did you know this?
1
Not at all
2
3
4
5
Perfectly