Schedule Management Flashcards

1
Q

Theory of Constraints

A

Examine the most limiting factor in our process and improve it so that it’s no longer a constraint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

To decompose project activities you need these three things:

A

Scope baseline, EEFs, OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Rolling Wave Planning

A

An iterative planning technique in which the work to be accomplished in the near term is planned in detail while work further in the future is planned at a high level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity List includes:

A

scheduled activities required on the project and an activity identifier and a scope of work description in sufficient detail to ensure the project team members understand what work is required to be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Lead

A

The amount of time a successor activity can be advanced with respect to a predecessor activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Lag

A

The amount of time a successor activity will be delayed with respect to a predecessor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Law of diminishing returns

A

When one factor used to determine the effort required to produce a unit of work is increased while all other factors remain fixed, a point will eventually be reached at which additions of that one factor start to yield progressively smaller or diminishing increases in output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Level of Effort

A

Needed to manage scope but are not required to complete scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Discrete Effort Activities

A

Activities required to complete project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Apportioned Effort Activities

A

The project management work, QA, Integrated Change Control, and Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity on Node Diagram

A

designed to show which activities must be completed in order for other activities to commence. This is referred to as “finish-to-start” precedence – meaning one activity must be finished before the next one can start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Precedence Diagramming Method

A

Arrows used to represent the relationship and the dependencies of the work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Analogous Estimating

A

Using historical information / previous similar projects to estimate a projects duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Critical Path Method

A

used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Schedule Network Analysis

A

a graphical representation of a schedule showing each sequenced activity and the time it takes to finish each one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Three-Point Estimates

A

Find the average of the optimistic, most likely, and pessimistic (O+ML+P)/3=Estimate

17
Q

PERT Estimates

A

Program evaluation and review technique (beta distribution) (O+(4ML)+P)/6=estimate

18
Q

Free Float

A

An activity can be delayed without delaying the early start of any successor activities

19
Q

Total Float

A

An activity can be delayed without delaying project completion

20
Q

Project Float

A

A project can be delayed without passing the customer expected completion date

21
Q

Forward Pass

A

Early Start + Duration - 1 = Early Finish

22
Q

Backward Pass

A

Late Finish - Duration + 1 = Late Start

23
Q

Monte Carlo Simulation

A

a quantitative risk analysis technique which is used to understand the impact of risk and uncertainty in project management

24
Q

Resource Leveling Heuristic

A

Limits labor in a time period and often extends the project schedule

25
Q

Resource Smoothing

A

Resource smoothing is used when the time constraint takes priority. The objective is to complete the work by the required date while avoiding peaks and troughs of resource demand. Resource leveling is used when limits on the availability of resources are paramount.

26
Q

Allows you to add more labor to effort-driven activities. By adding more labor, or effort, you are reducing the duration of the activity

A

Crashing

27
Q

Score the difficulty of the tasks needed to complete a user story in a sprint

A

Story Points

28
Q

Allows the project manager to make decisions based on conditions outside of the project, best practices, or guidelines

A

Soft Logic

29
Q

States that work will expand to fulfill the time allotted to it. Bloated tasks will take all the time allotted. Management reserve should be used instead

A

Parkinson’s Law

30
Q

A portion of the project schedule allotted for time overruns on activities

A

Contingency Reserve

31
Q

Allows activities to operate in tandem with each other rather than sequentially

A

Fast Tracking

32
Q

A bar chart that represents the duration of activities against a calendar. The length of the bars represents the length of activities, while the order of the bars represents the order of activities in the project.

A

Gantt Chart