Schedule Management Flashcards
Theory of Constraints
Examine the most limiting factor in our process and improve it so that it’s no longer a constraint.
To decompose project activities you need these three things:
Scope baseline, EEFs, OPAs
Rolling Wave Planning
An iterative planning technique in which the work to be accomplished in the near term is planned in detail while work further in the future is planned at a high level
Activity List includes:
scheduled activities required on the project and an activity identifier and a scope of work description in sufficient detail to ensure the project team members understand what work is required to be completed
Lead
The amount of time a successor activity can be advanced with respect to a predecessor activity.
Lag
The amount of time a successor activity will be delayed with respect to a predecessor activity
Law of diminishing returns
When one factor used to determine the effort required to produce a unit of work is increased while all other factors remain fixed, a point will eventually be reached at which additions of that one factor start to yield progressively smaller or diminishing increases in output
Level of Effort
Needed to manage scope but are not required to complete scope
Discrete Effort Activities
Activities required to complete project scope
Apportioned Effort Activities
The project management work, QA, Integrated Change Control, and Communications
Activity on Node Diagram
designed to show which activities must be completed in order for other activities to commence. This is referred to as “finish-to-start” precedence – meaning one activity must be finished before the next one can start.
Precedence Diagramming Method
Arrows used to represent the relationship and the dependencies of the work packages
Analogous Estimating
Using historical information / previous similar projects to estimate a projects duration
Critical Path Method
used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model
Schedule Network Analysis
a graphical representation of a schedule showing each sequenced activity and the time it takes to finish each one