Cost Management Flashcards
Cost Attributed directly to the project work and cannot be shared among projects.
Direct Costs
Shared to more than one project. Facilities, project management software, licenses.
Indirect Costs
Costs vary based on conditions in the project. Number of meeting participants, supply and demand of materials.
Variable Costs
Costs constant throughout the project. Rented equipment, consultant, etc.
Fixed Costs
Rough Order of Magnitude
Rough estimate, -25% to +75%
Budget Estimate
Based on scope, -10% to +25%
Definitive Estimate
Based on WBS -5% to +10%
Money set aside for known risk events
Contingency Reserve
Parametric Estimating
Uses a statistical relationship between relevant historical data and other variables to calculate a cost estimate for project work.
Regression Analysis
Statistical approach predicts what future values may be, based on variables from historical values
Learning Curve
The cost per unit decreases the more units workers complete
Bottom Up Estimating
A method of estimating a component of work. The cost of individual work packages or activities is estimated to the greatest level of specified detail. Detailed cost is then summarized or rolled up to higher levels for subsequent reporting and tracking purposes.
Three Point Cost Estimate
Finds an average of Optimistic, Most Likely, and Pessimistic. (O+ML+P)/3
Alternative Analysis
A technique used to evaluate identified options in order to select which options or approaches to use to execute and perform the work of a project.
Reserve Analysis
Cost estimates may include contingency reserves to account for cost uncertainty. The budget within the cost baseline that is allocated for identified risks.