Cost Management Flashcards

1
Q

Cost Attributed directly to the project work and cannot be shared among projects.

A

Direct Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Shared to more than one project. Facilities, project management software, licenses.

A

Indirect Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Costs vary based on conditions in the project. Number of meeting participants, supply and demand of materials.

A

Variable Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Costs constant throughout the project. Rented equipment, consultant, etc.

A

Fixed Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Rough Order of Magnitude

A

Rough estimate, -25% to +75%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Budget Estimate

A

Based on scope, -10% to +25%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Definitive Estimate

A

Based on WBS -5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Money set aside for known risk events

A

Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Parametric Estimating

A

Uses a statistical relationship between relevant historical data and other variables to calculate a cost estimate for project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Regression Analysis

A

Statistical approach predicts what future values may be, based on variables from historical values

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Learning Curve

A

The cost per unit decreases the more units workers complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Bottom Up Estimating

A

A method of estimating a component of work. The cost of individual work packages or activities is estimated to the greatest level of specified detail. Detailed cost is then summarized or rolled up to higher levels for subsequent reporting and tracking purposes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Three Point Cost Estimate

A

Finds an average of Optimistic, Most Likely, and Pessimistic. (O+ML+P)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Alternative Analysis

A

A technique used to evaluate identified options in order to select which options or approaches to use to execute and perform the work of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Reserve Analysis

A

Cost estimates may include contingency reserves to account for cost uncertainty. The budget within the cost baseline that is allocated for identified risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Cost of Quality

A

Assumptions about costs of quality may be used to prepare the estimates. This includes evaluating the cost impact of additional investment in conformance versus the cost of nonconformance.

17
Q

The approved version of the tie phased project budget, excluding any management reserves, which can only be changed through formal change control procedures

A

Cost Baseline

18
Q

Compares the performance measurement baseline to the actual schedule and cost performance. Integrates the scope baseline with the cost baseline and schedule baseline to form the performance measurement baseline

A

Earned Value Analysis

19
Q

The authorized budget assigned to scheduled work. It is the authorized budget planned for the work to be accomplished for an activity or WBS component, not including management reserve.

A

Planned Value

20
Q

Measure of work performed expressed in terms of the budget authorized for that work. It is the budget associated with the authorized work that has been completed

A

Earned Value

21
Q

The realized cost incurred for the work performed on an activity during a specific time period.

A

Actual Cost

22
Q

Measure of schedule performance expressed as the difference between the earned value and the planned value. It is the amount by which the project is ahead or behind the planned delivery date. Earned Value minus Planned Value.

A

Schedule Variance SV = EV - PV

23
Q

The amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost.

A

Cost Variance CV = EV - AC

24
Q

A measure of schedule efficiency expressed as the ratio of earned value to planned value. Measure how efficiently the project team is accomplishing the work.

A

Schedule Performance Index (SPI) SPI = EV /PV

25
Q

A measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost. A value of less than 1.0 indicates a cost overrun for work completed.

A

Cost Performance Index (CPI) CPI = EV / AC

26
Q

Examines project performance over time to determine if performance is improving or deteriorating.

A

Trend Analysis

27
Q

EAC forecast for ETC work performed at the budgeted rate

A

Accepts the actual project performance to date as represented by the actual costs and predicts that all future ETC work will be accomplished at the budgeted rate. EAC = AC + (BAC - EV)

28
Q

EAC forecast for ETC work performed at the present CPI

A

This method assumes that what the project has experienced to date can be expected to continue in the future. EAC = BAC / CPI

29
Q

EAC forecast for ETC work considering both SPI and CPI factors

A

In this forecast, the ETC work will be performed at an efficiency rate that considers both the cost and schedule performance indices. This method is most useful when the project schedule is a factor impacting the ETC effort. EAC = AC + [(BAC - EV) / (CPI x SPI)]

30
Q

To Complete Performance Index (TCPI)

A

Measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget. TCPI = (BAC - EV) / (BAC - AC)

31
Q

Estimate at Completion (EAC)

A

EAC = BAC / CPI

32
Q

Estimate to Complete (ETC)

A

ETC = EAC - AC

33
Q

Present Value Formula

A

FV / (1 + i)^n - FV is the future value, i is the interest rate, and n is the number of time periods.

34
Q

Straight-line Depreciation

A

Takes the purchase value of the item, minus the salvage price of the item, divided by the number of time periods.