RMC Hot Topics 9th Edition Flashcards - Schedule Management - Deck 1

1
Q

What is the process of schedule management?

A

Plan Schedule Management

Define Activities

Sequence Activities

Estimate Activity Durations

Develop Schedule

Control Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the key output of Plan Schedule Management process?

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key outputs of the Define Activities process?

A

Activity list

Activity attributes

Milestone list

Change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the key output of the Sequence Activities process?

A

Project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the key outputs of the Estimate Activity Durations process?

A

Duration estimates

Basis of estimates

Updates to project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Describe the Develop Schedule process.

What are some of its key outputs?

A

An iterative process that creates a project schedule that his bought into, approved, realistic, and formal.

Project schedule

Schedule baseline

Change requests

Schedule data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the key outputs of the Control Schedule process?

A

Work performance information

Schedule forecasts

Change requests

Updates to the schedule management plan, performance measurement baseline, and project documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is triangular distribution?

What is beta distribution?

A

Triangular distribution: A simple average giving equal weight to each of the three point estimates when calculating the expected activity duration or cost; it uses the formula (P+O+M)/3

Beta distribution: a weighted average that gives stronger consideration to the most likely estimate; it uses the formula (P+4M+O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is alternatives analysis?

A

Alternatives analysis involves evaluating the impact of each option on project constraints, including financial investment versus time saved and level of risk.

This process will result in the determination of the best approach to completing project work within the constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the two types of reserves being evaluated in reserve analysis?

A

Contingency reserves and management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is rolling waves planning?

A

Planning at a higher level and developing more detailed plans when the work is to be done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What do network diagrams show?

A

The network diagram shows just dependencies (logical relationships)

If estimates and leads and lags are added to the diagram later in the schedule management process, it can show the critical path.

If plotted out against time (or placed against a calendar-based scale), the network diagram is a time-scaled schedule network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the four types of logical relationships between activities in the precedence diagramming method?

A

Finish-to-start (FS): An activity must finish before the successor can start

Start-to-start (SS): An activity must start before the successor can start

Finish-to-finish (FF): An activity must finish before the successor can finish

Start-to-finish (SF): An activity must start before the successor can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are mandatory dependencies?

What are discretionary dependencies?

A

Mandatory: The order in which activities must be done, due to inherent nature of the work or as required by a contract; also called “hard logic “

Discretionary: the order in which the organization has chosen to have work performed; also called “preferred,” “preferential,” or “soft logic”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are external dependencies?

What are internal dependencies?

A

External: Dependencies based on the needs of a party outside the project

Internal: Dependencies based on the needs of the project; may be under the control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is lag?

What is a lead?

A

Lag: Waiting time inserted between activities.

Lead: How soon an activity can start before it’s predecessor activity has completed.

17
Q

What tool can be used when creating complex project schedule network diagrams that include leads and lags (as well as other dependencies)?

A

An automated scheduling system that is part of the PMIS

18
Q

What are some inputs to Estimate Activity Durations?

A
  • Activity list and activity attributes
  • Assumption log
  • Lessons learned register
  • Resource breakdown structure
  • Resource requirements
  • Project team assignments
  • Resource calendars
  • Risk register
19
Q

What does a resource breakdown structure show?

A

The categories of resources required for the project.