Project Managment Process Groups - trouble processes 1 Flashcards
1
Q
Manage, evaluate, and close procurements
A
M & C
2
Q
Continuously improve; perform progressive elaboration
A
Executing
3
Q
Handoff completed product
A
Closing
4
Q
Define and prioritize requirements
A
Planning
5
Q
Evaluate use of physical resources
A
M & C
6
Q
Perform quality audits and issue quality report
A
Executing
7
Q
Report on project performance
A
Executing
8
Q
Determine whether quality plan processes are correct and effective.
A
Executing
9
Q
Gain customer’s acceptance of interim deliverables
A
M & C
10
Q
Solicit Customer’s feedback about the project
A
Closing
11
Q
Inform stakeholders of all change requests
A
M & C
12
Q
Facilitate stakeholder engagement and manage expectations
A
Executing