RM NumbersGame Flashcards

1
Q

What is parametric estimating?

A

Using mathematical relationships found in historical information to create estimates (e.g., dollars per foot)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the range of accuracy with a definitive estimate?

A

+/-10 percent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A critical path activity will generally have how much float?

A

Zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why would a project manager want to use resource leveling?

A

To smooth the peaks and valleys of monthly resource usage consumed by the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does a benefit cost ratio of 2.5 mean?

A

The benefits are 2½ times the costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the formula for total float?

A

LS - ES, or LF - EF; This is the amount of time an activity can be delayed without delaying the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What schedule network analysis technique uses buffers?

A

Critical chain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What doe present value mean?

A

The value today of future cash flows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost risk is greater for the buyer in what type of contract?

A

Cost reimbursable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a management reserve?

A

An amount of time or money set aside to cover unforeseen risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the cost variance formula?

A

EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is value analysis?

A

Finding a less costly way to complete the work without affecting quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are direct costs?

A

Costs incurred directly by the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the earned value name for “how much have you spent to date?”

A

Actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are fixed costs?

A

Costs that do not change with project activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does a milestone chart show?

A

Dates of significant events on the project

17
Q

What is the duration of a milestone?

A

Zero

18
Q

What is analogous estimating?

A

Top-down estimating

19
Q

Why would you want to crash a project?

A

To shorten the project duration

20
Q

The “what-if” scenario method of schedule network analysis primarily makes use of what technique?

A

Monte Carlo analysis

21
Q

What are sunk costs?

A

Expended costs

22
Q

What schedule network analysis technique involves crashing?

A

Schedule compression

23
Q

What does a finish-to-start relationship mean?

A

One activity must finish before the next can start

24
Q

What does the estimate at completion tell you?

A

What we now expect he total project to cost

25
Q

What is the critical path?

A

The longest duration path in the network;

The shortest time to complete the project

26
Q

The types and quantities of resources required are calculated in what part of time management?

A

Estimate Activity Resources

27
Q

What does the schedule variance tell you?

A

How far you are behind or ahead schedule

28
Q

What is a formula for estimate at completion?

A

BAC/Cumulative CPI

29
Q

What estimating method would use optimistic time estimates?

A

Three-point estimate

30
Q

“How much work should be done” has what earned value name?

A

Planned value