Crowe Time Flashcards

1
Q

Time Management

A

Knowledge area with 6 processes that focus on creating an activity list, ordering that list chronologically, estimating resources, estimating time, creating the schedule, and controlling that schedule.

Processes:
• Define Activities (Planning)
• Sequence Activities (Planning)
• Estimate Activity Resources (Planning)
• Estimate Activity Durations (Planning)
• Develop Schedule (Planning)
• Control Schedule (Monitoring & Controlling)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Activities

A

Planning process within time management concerned with creating the activity list.

Key Inputs
• Scope Baseline

Key Tools
• Decomposition
• Rolling Wave Planning

Key Outputs
• Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Sequence Activities

A

Planning process within time management where schedule activities are put into order according to when they should occur.

Key Inputs
• Activity List

Key Tools
• Precedence Diagramming Method
• Dependency Determination
• Applying Leads and Lags

Key Outputs
• Project Schedule Network Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimate Activity Resources

A

Planning process within time management where the resources needed to perform each schedule activity are estimated.

Key Inputs
• Activity List

Key Tools
• Expert Judgement

Key Outputs
• Activity Resource Requirements
• Resource Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimate Activity Durations

A

Planning process within time management where the length of time to perform each schedule activity is estimated.

Key Inputs
• Activity List
• Activity Resource Requirements
• Resource Calendars

Key Tools
• Analogous Estimating
• Three-Point Estimates
• Reserve Analysis

Key Outputs
• Activity Duration Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Develop Schedule

A

Planning process within time managment where the project’s schedule is created.

Key Inputs
• Activity List
• Project Schedule Network Diagrams
• Resource Calendars

Key Tools
• Critical Path Method
• Critical Chain Method
• Resource Leveling
• What-if Scenario Analysis
• Applying Leads and Lags
• Schedule Compression

Key Outputs
• Project Schedule
• Project Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Control Schedule

A

Monitoring and controlling process within time management that manages change requests and unanticipated changes to the project schedule.

Key Inputs
• Project Schedule

Key Tools
• Performance Reviews

Key Outputs
• Work Performance Measurements
• Change Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity Decomposition

A

A tool used in the Define Activities process. It is similar to scope decomposition an is used to break down work packages into schedule activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity On Arrow Diagram

A

A type of network diagram where the activities are on the arrows that connect circular or oval nodes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Activity On Node Diagram

A

A type of network diagram where the schedule activities are represented on the rectangular nodes and the connecting lines represent dependencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Analogous Estimating

A

Also called top-down estimating, it is a form of expert judgment used when there is little information available. Activities, or even entire projects, are estimated by comparing to similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Backward Pass

A

A method for calculating the late start and late finish for activities on a project network diagram.

A backward pass starts at the end of the network diagram and works backward through each activity to the start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Critical Path

A

The path(s) through the network that show which activities, if delayed, will affect the project finish date.

The critical path is the highest risk path through the network.

All activities on the critical path have no float.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Dependencies

A

The relationships that eist between schedule activities. Dependencies may be either:
• Mandatory
• Discretionary
• External

Activities that have dependencies may have any of the following logical relationships:
• Finish-to-Start
• Start-to-Finish
• Finish-to-Finish
• Start-to-Start
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Dummy Activity

A

A way of creating a dependency relationship between two activities on an activity on arrow diagram.

Dummy activities are not real activities, and they have no actual duration. They are represented using a dashed line.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Compression

A

A technique used in the Develop Schedule and Control Schedule proccesses to make the overall schedule shorter. The two techniques most commonly associated with duration compression are crashing and fast tracking.

17
Q

Float

A

Also called “slack,” it is the amount of time an activity may slip before it causes the finish date of the project to change.

18
Q

Forward Pass

A

A technique for calculating the early start and early finish dates for the activities in a project network diagram.

A forward pass begins at the start of the network and progresses linearly to the finish.

19
Q

Lag

A

A waiting period between activities.

If the start of activity B were dependent upon the finish of activity A, and activity B also had a lag of 5 days, then activity B could not begin until 5 days after activity A had finished.

A lag is non-working time, so it is not considered to be part of the activity itself. Lags are essentially the opposites of leads.

20
Q

Lead

A

A jump-start on one activity that has a dependency upon another activity.

if the start of activity B were dependent upon the finish of activity A, and activity B also had a lead of 3 days, then activity B could begin 3 days before activity A finished.

leads are essentially the opposites of lags.

21
Q

Milestone

A

A significant point or event in the life of the project. Milestones are usually tied to deliverables.

22
Q

Precedence Diagramming Method

A

A method of creating project network diagrams that yields activity on node diagrams.

Abbreviated as PDM.

23
Q

Reserve Time

A

Padding added to the schedule to ensure that the schedule is still achievable and manageable if one or more activities take longer than their estimates.

Reserve time may be added to individual schedule activities or as a lump sum buffer.

24
Q

Schedule Baseline

A

A version of the project schedule that has been place under control.

The schedule baseline is created in the develop Schedule process ans eventually becomes a component of the project management plan.

25
Q

Variance Analysis

A
A tool used to understand the difference between what was planned and what was executed.  It is used in the following processes:
• Control Scope
• Control Schedule
• Control Costs
• Report Performance