Crowe Cost Flashcards

1
Q

Cost Management

A

Knowledge area with 3 processes that focus on creating the cost estimates, creating a budget, and controlling that budget.

Processes:

  1. Estimate Costs (Planning)
  2. Determine Budget (Planning)
  3. Control Costs (Monitoring & Controlling)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Estimate Costs

A

Planning process within cost management concerned with creating the activity cost estimates.

Key Inputs
• (none)

Key Tools
• Analogous Estimating
• Parametric Estimating
• Botton-Up Estimating
• Three-Point Estimates
• Reserve Analysis

Key Outputs
• Activity Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Determine Budget

A

Planning process within cost management concerned with creating the cost performance baseline (also known as the budget).

Key Inputs
• (none)

Key Tools
• Cost Aggregation
• Reserve Analysis
• Funding Limit Reconciliation

Key Outputs
• Cost Performance Baseline
• Project Funding Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Control Costs

A

Monitoring and Controlling process within cost management concerned with controlling the changes to the budget according to the cost management plan.

Key Inputs
• Project Management Plan
• Project Funding Requirements

Key Tools
• Earned Value Measurement
• Forecasting
• TCPI
• Variance Analysis

Key Outputs
• Work Performance Measurements
• Budget Forecasts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Life-cycle Costing

A

A way of considering cost not only based on purchase price or development cost but also factoring in anticipated operating costs. Life-cycle costing looks beyond the project itself.

Project costs that are initially higher but have a lower overall life-cycle cost should be viewed favorably.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Value Engineering

A

A method of improving the value of a product, service, or result by increasing the functionality or reducing the overall cost.

Value engineering seeks to optimize costs to achieve the highest possible value for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

BAC

A

Budgeted At Completion

Calculation used in earned value management representing the total budgeted cost for this project. The BAC is usually specified in the cae or question. No one formula exists to calculate the BAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PV

A

Planned Value, also known as BCWS (Budgeted Cost of Work Scheduled).

A calculation used in earned value management representing the work that should have been completed at a point in the schedule.

PV = planned % complete × BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EV

A

Earned Value, also known as BCWP (Budgeted Cost of Work Performed).

A calculation used in earned value management representing the work that actually was completed at a point in time.

EV = actual % complete × BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

AC

A

Actual Cost, also known as ACWP (Actual Cost of Work Performed).

Calculation used in earned value management representing the sum of the costs for a given period of time.

AC = sum of costs for a given period of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

CV

A

Cost Variance

A calculation used in earned value management representing the difference between what expenditures were planned and what was actually spent.

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Schedule Variance

A

Schedule Variance

A calculation used in earned value management representing the difference between what as planned to be completed and the work that was actually completed for a scheduled period of time.

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CPI

A

Cost Performance Index

The rate at which the project’s performance is meeting cost expectations during a given period of time.

CPI = EV ÷ AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CPIc

A

Cumulative CPI

The rate at which the project’s performance is meeting cost expectations from the beginning of the project to a point in time. CPIc is also used to forecast the project’s cost at completion.

CPIc = EVc ÷ ACc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

SPI

A

Schedule Performance Index

the rate at which the project’s performance is meeting schedule expectations up to a point in time.

SPI = EV ÷ PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

EAC

A

Estimate At Completion

the total projected cost of the project adjusted for past performance.

EAC = BAC ÷ CPIc

17
Q

ETC

A

Estimate To Complete

the projected amount of how much more will need to be spent to finish the project from this point forward, based on past performance.

ETC = EAC - AC

18
Q

Variance At Complete

A

The difference between what was bufgeted and what is projected to be spent.

VAC = BAC - EAC

19
Q

TCPIc

A

To-Complete Performance Index

Performance that must be achieved in order to meet financial or schedule goals.

TCPIc = (BAC-EV) ÷ Remaining Funds

(If the BAC is the goal, the Remaining Funds = BAC - AC)