Risk Management SoE Q's Flashcards

1
Q

What is the definition of risk in NRM 1?

A

The likelihood of an event or failure occurring and its consequences or impact.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the risk categories in NRM 1?

A
  • Design development risk
  • Construction risk
  • Employer change risk
  • Employer other risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a risk assessment?

A

An assessment of the risk to identify the likelihood and severity of the hazard occurring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you create a risk register for a new project?

A

Project team engages in workshop and brainstorms as many elements of project risk as possible
Project Manager usually collates this and issues to the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you use the risk register?

A

Continually monitor risk items identified in the initial risk register and make it a working document to identify project risks for the remainder of the project.

Assign ‘likelihood’ and ‘impact’ scores to each risk to give an overall risk score.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is simple method of risk assessment?

A

Most basic quantitative method for calculating a risk allowance on a project.

A likely cost is assigned to all risks in the register along with a, usually subjective, probability or occurrence.

The cost is then multiplied by the probability to give an expected value. The expected value for each risk is then totalled for an overall risk allowance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is included within the guidance note on Management of Risk?

A

This details the types of risk under NRM1, and the ways in which risk can be apportioned/response/mitigation measures.

It further looks at procurement strategy and the cost, time and quality risks associated with the differing routes.

It also looks at risk quantification, including probability trees and the monte carlo method.

It further looks at qualitative and quantitative assessment, with examples shown on draft risk registers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you identify risks on a project?

A

I would identify risks on a project by participating in a risk workshop with other member of design team.

We would discuss potential risks on a project and include them within the risk register.

I would look at the probability of these risks occurring and price them accordingly to get the expected monetary value (EMV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you elaborate on how risk allocation differs between different procurement routes?

A

With design and build, the client relinquishes all design and construction risk, and this is absorbed by the contractor for a premium.

With traditional, the client takes the design risk, whilst the contractor takes the pricing risk and construction quality risk. If using a BoQ, the client takes the measurement risk.

With construction management, the client takes the risk in terms of management of trade agreements, the construction manager, as well as the pricing and design risk.

With management contracting, the management contractor takes the risk associated with trade contracts, programme and quality. The client takes the pricing and design risk, as well as risk associated with the management contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can you name the NRM risk categories for me and provide an example of one?

A
  • Design development risk (planning requirements, environmental issues)
  • Construction risk (ground obstructions, adverse weather, existing services)
  • Employer change risk (change in scope of works, change in quality/time)
  • Employer other risk (acceleration costs, funding)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a probability Tree?

A

Tree diagrams are a way of showing combinations of two or more events. Each branch is labelled at the end with its outcome and the probability is written alongside the line.

A technique for determining the overall risk associated with a series of related risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the Monte Carlo method?

A

A computer generated simulation used to model outcomes.

A random-number generator is used to run enough simulations to produce different outcomes that mimic real-life results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is risk allocation?

A

Risks should be allocated to those best able to manage it, therefore risks are allocated to an ‘owner’ and recorded on the risk register.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the risk management strategies?

A
  • Avoidance (action to ensure risk does not occur)
  • Reduction (if it does occur, impact reduced as much as possible)
  • Transfer (risk transferred to another party)
  • Share (shared between parties)
  • Retention (kept by client)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the benefits of risk management?

A
  • Reduced cost / time overruns
  • Increased confidence in achieving project objectives and success
  • Risk workshops encourage communication between the team
  • Enable informed decision making on assessment of known variables
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why is risk management needed in construction?

A

Projects are typically complex and have time, cost and quality targets that must be met

Risk is present in all projects and surveyors are routinely involved in making decisions which have a major impact on risk

Used to reduce the impact of events that may cause failure to reach desired targets

17
Q

Can you name a risk that was present on the Project Zeta risk register?

A

A risk that was present was in relation to the LUX levels of the external lighting.

The architect was unsure whether the proposed levels would be satisfactory for planning approval and therefore an allowance was made within the register to account for any potential uplifts.

18
Q

How is risk captured within the various stages of cost planning?

A

Risk is captured during the various stages of cost planning as a % of the works. This % will be predicted using past project data as a reference point.

The risk % will be reduced as the works progress to account for a more detailed design and cost plan.

19
Q

How did you assess the time and cost impact for the ground risk on St Wilfrids? Could anything be done to reduce the risk?

A

The time and cost impact of the ground risk was determined by reviewing the allowances that were made during the prior development. The prior development had encountered ground issues and it was therefore thought that this project would be a good reference point. Appropriate uplifts were applied in respect of time and inflation.

In order to reduce the risk, I could have looked at instructing further surveys to firm up the nature of the ground conditions and in turn firm up the cost.

In addition, I could have estimated the price of the ground risk by looking at the contractors labour, material, plant and any associated profit they would apply.

20
Q

What surveys were completed to ascertain the extent of ground risk at St Wilfrids? How did you establish the extent of risk and how did you determine the value of the P.Sum?

A

A soil investigation was completed on St Wilfrids. This provided us with a breakdown of the varying ground strata.

The extent of the risk was established through discussions with the design team. A probability % was applied to the risk.

The value of the provisional sum was established by looking at the allowances that were made during the prior project for a similar ground risk. This was uplifted for time and inflation as this project was completed a few years prior.

21
Q

What are the main categories on a risk register?

A
  • Description of risk
  • Category of risk
  • Risk owner
  • Risk probability
  • Risk impact
  • Expected Monetary Value of Risk
  • Mitigation measures
  • Review date
  • Status
22
Q

On a construction project, asbestos is identified which wasn’t identified pre contract? Who owns this risk?

A

The person that owns the risk will be the person that is best placed to deal with the risk.

This being the contractor in most instances.

For example, on one of my Toby Carvery projects, we encountered asbestos following the work starting. As the contractor was on site completing the works, they dealt with the encapsulation, management and removal of the asbestos.

23
Q

How were risks identified and priced on Project Zeta?

A

Risks were identified by setting up a risk workshop with members of the design team.

Potential risks on the project were identified and included within the risk register.

The risks were assigned a probability and priced to give an expected monetary value (EMV)

24
Q

What risks were identified on Project Zeta?

A

As mentioned within key issue 2 of my case study, the cost of the welfare unit was raised as a risk. The price of materials had increased, and the contractor had provided critical dates for ordering of materials to ensure there were no further increases or delay to programme.

25
Q

How did you manage the level of contingency on Project Zeta once a risk had passed?

A

Once a risk had passed, this was drawn down proportionally.

For example, there was a concern that the current lux levels of the proposed external lighting may not have been appropriate for local authority requirements.

I made an allowance for increasing these, but it was confirmed that the lux levels were appropriate and therefore the cost was drawn down appropriately.

26
Q

How much of the contingency was used to deal with risks that were detailed within the risk register?

A

In the end, none of the client’s contingency was required to be used and the project was delivered under budget.