Risk Management Flashcards

1
Q

How do you carry out risk analysis and risk management?

A

Experienced clients may have access to risk registers from previous schemes that can be used as a starting point.
A risk management workshop can also be organised with all members of the design team coming together to identity project specific risk items.
The risk register can be updated during the meeting and will form the basis of risk management for the project.
These risks will be continually monitored as the project progresses.
Identified risks can either be removed or we can aim to reduce their probably of occurring and put in mitigation measures if they do occur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is risk defined as?

A

An uncertain event that will have an effect on the achievement of the project objectives should it occur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the stages of risk management?

A

Identify
Assess
Control/Monitor
Record
Review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the NRM risk categories?

A

Employer Change Risk
Employer Other Risk
Design Development Risk
Construction Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens to risk allowances if the risk does not occur?

A

If it’s a central contingency pot, this should be reduced proportionally as the project progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you give me some examples of risk in a construction project?

A

External risks: Brexit, Covid
Financial risks: exchange rate, inflation
Client risks: lack of experience, likelihood of post-contract changes
Design risks: inappropriate consultant team, incomplete/poor design
Contractor selection: inadequate selection process.
Construction: weather, buildability, H&S, availability of resources, ground conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between qualitative and quantitative risk management?

A

Quantitative quantifies risks numerically 1-5.
Qualitative categorises them in descriptive terms such as low to very high.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is risk management?

A

A process for identifying, assessing and responding to risks associated with the delivery of an objective such as a construction project.
Risk management establishes a set of procedures by which risks are managed.
All time, cost and quality targets must be met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tell me about the importance of risk registers?

A

Help to identify, analyse, monitor, manage and respond to potential hazards and risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the various risk response strategies?

A

Retain
Reduce
Transfer
Avoid
Share

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What current challenges is Covid and/or Brexit bringing to Risk Management?

A

How do you allow for price increases?
Fluctuations in contracts
Who takes risk of covid?
Material delays

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between a hazard and a risk?

A

A hazard is the potentially detrimental event that could occur.
A risk is the probability and impact of that hazard occurring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you expand on the Identify, Assess, Respond approach?

A

Risk identification should be carried out as early as possible.
Assessment can be carried out to determine the probability and impact of each risk item and its effect on cost, time and performance of the project.
Response actions aim to reduce the probability of the risk arising or to mitigate its impact should the risk arise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an uncertain or unforeseen event?

A

A random event that defies prediction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Risk Allocation?

A

Risks should be allocated to those who are best able to manage it, in a manner likely to optimise project performance.
Financial allocation of risk should be achieved through the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe the format of the risk register?

A

A risk register format will typically include:-
A description of the risk.
The risk owner.
A probability of occurrence.
The impact of its occurrence (£/wks).
Risk factors (probability x impact).
Actions required.
Review date.
Status (open or closed).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What role does the QS play in Risk Management?

A

Assist in setting & managing contingency funds appropriately.
Undertake risk analysis to ensure accuracy of funds available & manage their release when no longer required.

18
Q

Can risk be calculated?

A

Risk can be calculated to an extent, but it cannot be calculated exactly otherwise it would not be classified as a risk.
Risk involves the probability of something occurring & its potential impact in the event that it does occur.

19
Q

What is Expected Monetary Value (EMV)?

A

EMV is the probability of the risk occurring multiplied by its impact.
Can be used to establish the overall monetary value of risks
within the project.
The probability is usually expressed as a fraction or percentage while the impact is usually a positive or negative monetary value.

20
Q

What is monte carlo simulation?

A

Uses computer software to predict the risk.

21
Q

What is a risk register?

A

A document listing all the risks identified for the project, explaining the risk qualitatively and quantitatively.

22
Q

How do you create a risk register?

A

All members of the project team come together and brainstorm elements of project risk.
All risks will be collated by the PM.

23
Q

How do you use the risk register?

A

Continually monitor risk items and assign likelihood and impact scores to each risk. Will give it an overall risk score.

24
Q

What is risk allowance?

A

A sum included to cover unknown expenses or unmitigated risks during the project.

25
Q

L1 - What methods are there to assess the value of a risk?

A

Probability trees and monte carlo simulation.

26
Q

L1 - How do you decide if a risk has passed?

A

It would be discussed within a risk workshop between the project team. For example, if asbestos had been identified on the risk register it would be removed following investigation and confirmation that there was none present.

27
Q

L1 - Have you participated in a risk workshop?

A

No, I have not participated in a risk workshop. I have been involved in progress meetings where the contractor has highlighted certain risks.

28
Q

L1 - How do you identify a risk?

A

Work collaboratively with stakeholders to identify everything that could go wrong with a project.

29
Q

L1 - How do you mitigate a risk?

A

You put appropriate actions in place to reduce the likelihood of the risk occurring.

30
Q

L1 - How would you score or weight a risk?

A

You apply a percentage to the risk, this is dependent on the likelihood of it occurring.

31
Q

L1 - What are the NRM1 measurement rules for risk and risk allowance?

A

Under NRM1 a risk allowance is calculated by estimating the risk allowance for:
design development risks
construction risks
employer change risks
employer other risks
These are calculated by multiplying the base cost estimate by a % probability.

32
Q

L1 - What current challenges is Covid and/or Brexit bringing to Risk Management?

A

How do you allow for price increases?
Fluctuations in contracts
Who takes risk of covid?
Material delays

33
Q

L1 - What is a Monte Carlo simulation?

A

A computer based software used for predicting risk.

34
Q

L2 - St Wilfrid’s – when the ground problems identified how was the value of the PS determined?

A

I reviewed the time and cost implications of removing the ground obstructions and priced them appropriately.

35
Q

L2 - Why and on what basis was the risk split between contractor and client?

A

Typically risk allocation would fall to those that are best placed to manage it.
With the ground risk on St Wilfrid’s the contractor would have been best placed to manage it, although the client had experienced a similar situation previously and it was therefore thought that the risk would be best split between the parties.

36
Q

L2 - Project ZETA – what part did you play in the risk meetings?

A

The contractor advised on the potential impact of the risks and queried whether the project team agreed or disagreed. My involvement was as simple as this. I did not disagree with any of the risks that the contractor had identified.

37
Q

L2 - Project Zeta - How were the risks evaluated?

A

The project team assessed the risks and applied a probability percentage to them. This was multiplied by a rate to give a total risk allowance.

38
Q

What contractual mechanisms protect the client or contractor?

A

Performance Bond/PCG
Variations
LD’s

39
Q

How do probability trees work?

A

Tree diagrams are a way of showing combinations of two or more events. Each branch is labelled at the end with its outcome and the probability is written alongside the line.

40
Q

How does the monte carlo method work?

A

A random-number generator is used to run enough simulations to produce different outcomes that mimic real-life results.

41
Q

Can you provide some examples that relate to the NRM1 risk categories?

A

Design development risk - use during the design process to provide for the risks associated with design development i.e. planning requirements, environmental issues, tender delays etc.
Construction risk - allowance for use during the construction process to provide for the risks associated with site conditions i.e. ground conditions, existing services etc.
Employer change risk - allowance for use during both the design process and the construction process to provide for the risks of employer driven changes i.e. changes to scope of works, change in quality etc.
Employer other risk - an allowance for other employer risks i.e. acceleration, funding issues etc.