Contract Practice SoE Q's Flashcards
What Contracts are available under the JCT Suite of Contracts?
- JCT Standard
- JCT Intermediate
- JCT Minor Works
- JCT Design and Build
- JCT Construction Management
- JCT Management Building
- JCT Major Projects
What are some differences between JCT Contracts?
D&B includes for Employers Agent, not included in Standard, Intermediate or Minor Works
D&B and Standard include for third party rights, Intermediate and Minor Works do not
Minor works does not include provisions for collateral warranties
Minor Works unable to include sectional completion
When would you use certain JCT Contracts?
Standard = For larger projects involving complex services installations and specialist work
Intermediate = when proposed works are simple in nature, involving basic recognised trades within the industry, without complex services installations or specialist work.
Minor Works = When works are of a simple nature
Design & Build = When looking to transfer risk to the Contractor
What Contracts are available under the NEC Suite of Contracts?
- Option A: Priced contract with Activity Schedule
- Option B: Priced contract with Bills of Quantities
- Option C: Target contract with Activity Schedule
- Option D: Target contract with Bills of Quantities
- Option E: Cost reimbursable contract
- Option F: Management contract
What is the FIDIC Contract?
International Federation of Consulting Engineers
Geared towards larger engineering projects
What are the timescales of reviewing a CE under the NEC contract?
Notification of Compensation Event – within 8 weeks of becoming aware of the event
Quotation – within three weeks of request
Reply to quotation – within two weeks of receiving quotation
What are the timescales to agree the valuation after receiving the contractors application?
JCT = 5 days after due date
NEC = 7 days, 5 days to issue payment notice
What legislation governs construction contracts?
Housing Grants Construction and Regeneration Act 1996 (Construction Act)
Local Democracy, Economic Development and Construction Act 2009 (changes to payment regimes)
What changes did the LDEDC Act 2009 bring in?
Contracts no longer need to be in writing to commence adjudication.
Contract must have mechanism to determine what payments are due and when
Pay when certified clauses no longer used
Timescales around payment notices and final date for payment
What is the Contracts (Rights of Third Parties) Act 1999?
Allows parties who are not a party to the contract to enforce certain terms as if they were a party to the contract
Must be explicitly named in the contract
What are the advantages of third-party rights?
Saves on time and cost drafting up collateral warranties
Once the rights are negotiated and agreed, there is limited room to revisit the wording, provides certainty
What does JCT stand for?
- Joint Contracts Tribunal
What is included within the guidance note on interim valuations and payment?
The document looks at interim valuations, payment under different forms of JCT and NEC contracts.
It further looks at the payment timelines of JCT and NEC, as well as the components of a valuation and retention.
It further discusses interim applications, certificates and pay less notices
What is a collateral warranty?
It is an contractual agreement between two parties that would usually not have one. For example, on a D&B contract, these would be used between members of the design team that sit beneath the contractor and the client
Please summarise the contractual mechanism of ‘Interim Valuation and Payment’ in JCT contract series?
Interim val date 7 days before the due date – contractor to make application
Due date is 7 days following the interim date
5 days following the due date is the date for the interim cert
14 days following the due date is the final date for payment
5 days prior to the final date for payment is when the payless notice would be due
What is a certificate of non-completion?
A formal notice that the contractor has not completed the works by the date for completion within the contract
Why would you issue a non completion cert?
The contractor has not completed the works by the contract completion date and has not submitted an extension of time claim.
This protects the client in case Liquidated Damages would have to be levied
What are Liquidated Damages?
A genuine pre-estimate of loss suffered by the Employer because of late completion of the works
Not a penalty
What is a loss and expense claim?
Where the Contractor incurs loss due to the failure of the employer (relevant matter)
Should be actual loss incurred by contractor when assessing the claim