Risk Management Flashcards
What is risk
Risk is defined as the uncertainty of outcome, whether positive opportunity or negative threat, of actions and events
Risk Management Process
- Identify risk (initial and continuous)
- Assess risk e.g. non-financial matrix (possibility x severity)
- Address risk- tolerate (accept), treat (manage to acceptable level), transfer (to someone else e.g. insurance, subcontractor), terminate (avoid the risk)
- Monitor- review and report risks e.g. via risk register and update actions as appropriate
How risk is allocated on NEC A Priced Contract with Activity Schedule
Greater financial risk on the contractor but requires scope certainty.
How risk is allocated on NEC B Priced Contract with Bill of Quantities
Greater financial risk on the contractor but requires scope certainty.
How risk is allocated on NEC C Target Contract with Activity Schedule
Shared financial risk but still requires scope certainty to set an accurate target cost.
How risk is allocated on NEC D Target Contract with Bill of Quantities
Shared financial risk but still requires scope certainty to set an accurate target cost.
How is risk allocated on NEC E Cost Reimbursable Contract
the developer/ client will largely take on the financial risk.
How is risk allocated on NEC F Management Contract
the client takes on the financial risk.
How traditional procurement route deals with risk
Clients architect takes design responsibility so greater risk on client
How D&B procurement route deals with risk
D&B contractor takes design risk so greater risk on them
How Management procurement route deals with risk
nearly all risk with the client
RICS risk guidance note
Principles of risk; Definition of risks, issues and types of risk (consequential, political, programme
Mitigation; avoidance (terminate), reduction (treat), transfer, share, retain
Quantification; probability tree’s, monte carlo, probability x severity, sensitivity analysis
How was portfolio risk register managed
Portfolio risk register with portfolio wide risks (inflation, resource shortage, etc.) as well as project specific risks.
Quarterly risk workshops held to identify new risks, with description, cause, effect, probability, min, max, expected cost, EMV (expect x probability) and min, expected and max time impact. Mitigation actions with owners and dates were identified. Existing risks were reviewed at the workshops to monitor actions and update any details as appropriate.
I would chair the meetings, contribute to risk identification, quantification, etc. and then upload to ARM (Active Risk Management System) which would calculate the risk score based on the probability and EMV, and categorise the risk register into high, medium and low risks.
Risk reports could be downloaded from the system and information used to assess level of risk to be attributed to the portfolio.
Quantifying risk using Estimated Monetary Value
Assessment of the max, min, expected costs would be identified with expected cost x probability used to calculate the estimated monetary value.
How to identify successful risk mitigations
Successful risk mitigations would be reviewed during the risk workshops assessing if they have successfully mitigated or reduced the impact of the risks, and new actions identified if the risk has not been completely mitigated