Construction Technology Flashcards
Types of Structural frames
- Concrete
- Timber
- Steel
Types of foundation
Strip foundations- A concrete base that is poured to a minimum depth of 225mm, upon which the walls of the foundation are built up to the level of the ground floor. Used when setting a building on firm, level ground that has been properly prepared.
Trench fill foundations- Similar to strip foundations, but with the trench filled with concrete. Typically used on sites with clay soils or where tree roots are a problem.
Raft foundations- Large, flat slab of concrete used to spread the weight of a building over a larger area. Raft foundations are typically used on soft, weak or waterlogged ground.
Pile foundations: Used on sites where the soil is unstable, or where the building is particularly heavy. Pile foundations involve the use of long, steel or concrete columns that are driven deep into the ground to support the weight of the building.
Pad foundations: Similar to strip foundations but consists of isolated footings that support individual columns or stanchions. Typically used on lightweight structures or on sites with a shallow layer of topsoil.
What is off-site manufacturing/ construction
Off-site construction is a construction procedure that involves the planning, designing, fabrication, transportation of fabricated building items and its assembling on the site.
Panelised (2D) construction- flat panel units used in the form of walls, floors or roof panes in order to create a complete structural shell. Built in the factory and transported to the site for assembling as a three-dimensional structure or to fit into an already on-site constructed structure. panel units can be made out of timber, insulated panels or light gauge steel or concrete.
Volumetric/ modular (3D) construction- three-dimensional units are produced in the factory and brought to the site and bolted together. The frames constructed can be either steel, timber or concrete. The modules can bought in different forms e.g. basic structural shell or with internal and external finishes and services.
Benefits of OSM
Speed, high degree of precision, cost savings, greater quality control
When is OSM suitable
Project has to meet tight deadlines, involves the construction of repetitive structures, space limitations on site, safety concerns.
RIBA Plan of Work 2020
RIBA is a framework explaining how a construction project should be organised.
Split into 8 stages from 0-7:
RIBA Stage 0
Strategic definition- Determining the best means of achieving the clients requirements, including undertaking early cost appraisals (which could be not build something new). QS involvement in reviewing budget as part of business case.
RIBA Stage 1
Preparation and brief- Developing detail of the brief to make sure everything needed for the design phases is in place (undertaking feasibility studies). Agree budget and produce initial cost plan/ estimate (e.g. based on unit rate)
RIBA Stage 2
Concept design- Getting a design concept that makes sure the look and feel for the building is in line with the clients requirements and budget. Cost plan update, e.g. ratio analysis.
RIBA Stage 3
Spatial coordination- Spatially coordinate the design before the detail required for construction is added e.g. the spaces required for any building systems – such as structural and building services have been determined. Cost plan can be updated to elemental cost plan.
RIBA Stage 4
Technical design- Developing the information required to manufacture and construct the building. Cost plan continue to be updated, with constant review against budget and analysis of design solution/ value engineering. Cost plan update to initially be updated with approximate quantities and developed to full BoQ with pre-tender estimate also produced. BoQ is then issued to tenderers to populate with rates and pricing document is then produced and negotiated to agree a contract sum.
RIBA Stage 5
Construction and manufacturing- Constructing/ manufacturing the building. The QS main involvement begins in regard to managing the construction contract (undertaking duties detailed in contract administration) monitoring and managing costs (as per project finance/ commercial management duties)
RIBA Stage 6
Handover- Closing out of defects and completing the handover tasks required to conclude the building contract (agree final account, undertaking analysis looking at final cost against initial budget, assessing lessons learnt)
RIBA Stage 7
Use- When the building is in use, this lasts until the building reaches the end of its life
Monitoring of MSE roof for loading
An automatic total station was installed on top of one of the precast concrete columns. Monitoring prisms were then installed throughout the precast structure which would feed information to the total station. Readings were taken automatically every hour to check if there was any movement in the structure.
This was required whilst the loading of the green roof took place due to previous deflection that had occurred on the structure