Project Finance Flashcards

1
Q

What are project costs?

A

plant, labour, materials, risk, overheads (offices, computing systems)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are project costs monitored & managed

A

Cost report should be used to monitor and manage project costs. This along with comparing it against budget and assessing what has caused periodic changes will help with identifying risk items.

Cost report is updated as the project progresses through the stages from feasibility to construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How can cost be used as a measure of progress

A

Cost can be used as a measure of progress by comparing costs incurred against total estimated cost. This is known as the cost-to-cost measure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost control techniques

A

Budget setting and developing the cost plan with a more accurate and comprehensive breakdown once construction phase commences splitting out all individual labour, plant, materials etc,

Monitoring costs, periodic update of cost plan assessing against budget and actuals, comparing to the programme and identify any cost increases (CE’s) or cost movement (due to delays). Contract Administration system such as Asite can be used to assist with monitoring costs. Analysis of variance on actuals against estimate should be used to identify risk items/ causes of cost overrun so mitigations can be put in place. Clear communication and sound reporting/ record keeping should be undertaken to assist with monitoring the costs and comparing client and contractor reported EFCs

Managing time effectively ensuring programme is met to prevent prolongation which leads to additional costs

Implementing change control systems to allow all change to be clearly implemented cost effectively and with the most suitable solution and with the correct process in place to approve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What were the PAS project costs

A

The PAS project costs were the main contractor which covered prelims (PM & CM), design, materials, plant and labour for the install of the platform end barriers and steps

The TfL project staff PM, Engineers, Commercial
TfL internal services such as cable relocator

The PAS cost report also included the internal risk contingency that was allocated to the project and used to cover any variations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a risk contingency, how it is calculated, why is it useful and how is it managed

A

Risk contingency allows for flexibility and effective responses to change orders and unforeseen risks arising at the construction phase of projects.

A lack of contingency can lead to cost and time overrun whilst appropriate procedures are undertaken to obtain additional authorities/ money.

The contingency is usually calculated based on the value on the contract (usually between 5-15% of contract value), perceived risks to the contract (is there high potential for unforeseen ground conditions), and the contract type (option E will place greater risk on Employer so more contingency usually requested)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What was the change process on PAS

A

Project variations/ CE’s that were assessed as a CE as per the conditions of the contract would be priced using the rates in the schedule of cost components. Internal change notice would be implemented setting out the reason for the CE and the value and revised contract value. A contingency (risk value) was allocated to the project so all CE’s were able to be locally implemented by the project with sign off from the contractor and PM. As we could close to our contingency limit I started the internal governance procedure to request further contingency to allow he project to continue to implement CE’s at project level and prevent project delays by waiting for internal governance procedures to be completed. The contingency was request based on an assessment of the value of CE’s to date and known risks to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What was the portfolio workbank periodic forecast

A

The workbank periodic forecast was the cost report for the whole power portfolio detailing actuals to date and forecast for the remaining costs to completion. Each project was allocated a project code within the portfolio, an individual forecast was complete for each project with detailed breakdown of all PO’s internal labour, risk, etc. and each are summarised as a single line item to show to portfolio costs. One of the project codes was for the project risk (this split out the individual project risk allocations and the pan portfolio risk line)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was the power workbank forecast used for

A

The forecast was used to monitor the portfolio costs and assist with budget setting. The forecast was reported on each period where I would detail the changes per project in periodic cost, YE, and EFC against the last periods forecast and the budget. I would detail the causes of these and then do a portfolio roll up advising the project on the impact of these changes in regard to budget and Project Authority.

Each period I would undertake meetings with the PM to understand changes in the project e.g. prolongation, additional works, etc. and would use this to update the forecast. I would also ensure the forecast against periods was aligned with the project programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did the forecasting process on power portfolio vary depending on contract type, procurement route & stage of the project

A

The forecasting process was fairly similar across the different contract types in the fact it still was broken down across PO’s, internal labour, risk, etc. However the contract type would often impact the level of risk reported on.

Again the procurement route would not change the way the forecast/ reporting was undertaken or the level of information, however a design and build procurement route may have less PO’s/ internal labour for design engineers compared to a traditional procurement route. There would also be an overlap between the design & construction phases.

Finally the stage of the project would again not necessarily impact how the forecast is produced and the reporting requirements, however projects at the earlier stages will have less of a breakdown on the cost report in regard to the different types of plant, material labour etc. A provisional sum, approximate cost is likely to be used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How was risk provisions managed on power workbank

A

Assessment of risk values by reviewing risk register, calculating target monetary value and allocating a risk value to the project. Each period when forecasting we reviewed the level of risk in the forecast based on the project risks and determine if the risk included is appropriate. All risk would be allocated to an event and forecast based on when that event was to occur. Once the event had passed the risk value would either be reallocated to another risk event or transferred back to the pan portfolio risk to either be handed back or used elsewhere in the portfolio.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Change control processes for project authority and risk

A

2 types of CRFs, 1 is a local CRF which is used to manage the portfolio authority and risk by allowing authority or risk to be transferred between projects within the approved portfolio level. These are approved at the portfolio meeting by SPM & sponsor. If additional authority is required from the business or risk is to be used/ drawn down then a CRF is also to be done at a business level and to be approved at one of the periodic APCD Change meeting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PAS spend reporting

A

The spend report/ cost report was produced periodically splitting out third party cost (contractor PO) and internal costs (e.g. PM, engineers and internal services). This was split out periodically.

Each period I would download the actuals and update the forecast in line with the contractors programme/ activity schedule. I would also update the internal forecast based on any known service relocations, agreed PM/ engineer allocation plus allowance for any additional allocations based on known additional input.

I would then report the revised EFC against the allocated project authority and budget to advise on the expected additional funds to be available for the second phase of the project.

As CE’s came about I would deduct this from the contingency level to keep track of the remaining available contingency and advise when additional contingency was required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Difference between cost plan & cost estimate in early stages of a project

A

In the early stages the cost plan is just a single number and based on a unit rate e.g. per OLBI
whereas the estimate is the rough breakdown to achieve this unit rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why is effective change control important?

A

Assists with accurate monitoring of costs to ensure you stay within the project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are effective change control techniques?

A

Regular monitoring/ review of change and the impacts on cost and time through a change register

17
Q

How to effectively manage project costs

A
  • Regular review and monitor of cost against budget
  • effective change control processes and monitoring
  • effective risk management techniques
  • this can be done via a rolling final account, agreeing project costs (including change) each period
18
Q

Earned Value Management

A

Use of cost and time to measure project performance

  • Cost performance index: how much an activity actually cost vs the planned cost
  • Schedule performance index: How long an activity has taken to complete vs planned completion timescale
19
Q

What is included in a cost report

A

Contract sum
Known variations
Anticipated variations
Risk

20
Q

Purpose of a cost report

A
  • management of project costs
  • set out funding requirements/ budget setting
21
Q

What factors can impact project costs?

A

Factors in our control:
- Client priorities (time/cost/quality)
- Procurement method
- Construction method (complex works/ design preferences)
- Site location (access constraints, flood prone, poor ground conditions)

Factors out of our control:
- Market fluctuations (inflation interest rate hike due to unforeseen events e.g. Covid, Ukraine war)
- Legislation changes

22
Q

How did you establish the PAS reporting regime/ advise on an appropriate reporting regime?

A

The PAS project was a maintenance piece of work and therefore did not fall under our usual periodic cost reporting requirement.

To establish the reporting regime I first off understood the requirements I had for reporting in regards to the quarterly update of the business area cost report, which is just a single line item for the third party costs (actual & forecast)

I then had a meeting with my client (PAS project team) to understand the information they required from the cost report (third party expenditure and how it falls within procurement authority) (total EFC & how it falls within budget & budget remaining for phase 2) simple cost info, not full breakdown.

I then produced a template and set up a session to run the project team through the structure and obtained any feedback on changes to the template to ensure it met their requirements

23
Q

How do you advise on methods to control costs on your projects to stay within budget/ deliver a saving?

A
  • DLR- buy some plant & equipment instead of hiring due to the extensive increase in programme (£62k)
  • PAS- Re-sequencing works so those with cable relocation are pushed back to reduce programme impact. Decision to self-deliver enabling works due to resource capability & removes contractor fee.
  • Power portfolio- Putney earthing, free issue cables due to long lead times which could impact prices & high cable costs. We had cable in stores which mitigated programme impact and reduced cost.
  • Power portfolio- TIS project which was being self delivered. Decision to order materials due to long lead times which would impact programme and also rising material prices.
24
Q

What is the purpose of retention?

A
  • It provides an incentive for the contractor to complete the works promptly
  • It provides some financial cushion to the employer in the event of contractor default
25
Q

Can you explain how you would advise on managing risks through the lifecycle of a project?

A

Risk Register

26
Q

how you manage costs and what you might use to do so?

A

Cost report

27
Q

What are external factors that can affect cost?

A
  • location of the building project
  • State of the construction economy (and general economy) at the point in time when construction cost is established
  • Labour supply
  • Material Supply
  • Legislation changes
28
Q

What would constitute a robust change process?

A
  • early identification of potential change items e.g. EWN
  • Clear tracker of this e.g. EWN register
  • Defined process of implementing change (with timescales, escalation, etc.) e.g. CE process
  • Tracker of change including funding sources e.g. change register/ CE register
29
Q

What is the difference between risk & contingency?

A

Contingencies are for unknown items and based on a %

Risk is for known events with uncertain outcomes/ impacts with a specific value built up and associated with these events