Contract Practice Flashcards
Contract formation
- consideration, each side must promise to give or do something for the other.
- intent, the parties must intend the agreement to be legally binding.
- offer, an offer is willingly made by an offeror with the intention that it will become binding as soon as the offeree accepts.
- acceptance, a final and unqualified acceptance of the terms of an offer. To make a binding contract the offeree must accept all the terms of the offer (mirror image)
HGCRA 1996
The Housing Grants, Construction and Regeneration Act 1996 aims for
- payments to be made promptly throughout the supply chain
- disputes to be resolved swiftly.
It applies to all construction contracts which means an agreement with a person for any of the following;
(a) the carrying out of construction operations;
(b) arranging for the carrying out of construction operations by others, whether under sub-contract to him or otherwise;
(c) providing his own labour, or the labour of others, for the carrying out of construction operations.
Insurances
Insurances are required within construction to protect individuals/ companies against claims which due to the nature of the works can be costly. It also ensures anyone owed money from a claim receives what they are rightfully owed.
Construction all risk insurance
The Employer gets this and it covers damage or injury to the works themselves and the cost of reinstating them. E.g. if there was a fire at the worksite which damaged the works under construction, or if cabling was being installed and was stolen from site. The insurers will pay up to the value specified each time there is a separate event to cover the cost of repair/reinstatement.
Public liability insurance
The Employer gets this and it provides cover in the event that TfL/our contractors are negligent and cause damage to third party property or cause injury to a third party. This might be because they didn’t make a site safe and a customer trips over a discarded piece of building material that should have been cleared away.
Employer’s liability insurance
The contractor gets this and it covers claims where any employee suffers an injury during the course of their work as a result of their employer’s negligence. E.g. it must provide a safe place and system of work under the various H&S Acts. If they told me to visit a construction site, but without providing PPE or appropriate briefing, and I broke my foot because something heavy was dropped on it, I could make a claim against TfL. The EL policy would settle that claim.
Contractor’s Equipment loss insurance
The contractor gets this and it covers the Contractor’s tools and plant. We aren’t insuring them; they aren’t our property, and we’re not responsible for the security of the site. If tools/kit disappear or get damaged, the contractor should use their own insurances to cover that loss.
Professional Indemnity insurance
The contractor gets this and it covers losses we might suffer as a result of negligent professional advice or services from the contractor. A typical textbook example is if an architect designs a new house but messes up the calculation for the foundations – they’re not deep enough. The builder construct the foundations and house exactly in accordance with the architect’s design. But the walls start to crack because the foundations aren’t deep enough. It’s the architect’s error (not the builder). The house owner would pursue a claim against the architect for the cost of fixing the defect, the loss of use of the house, cost of temporary accommodation. And that typically would be covered by the architect’s PI insurance.
Standard Forms of Contract
NEC Options A-F
JCT Traditional lump sums (SBC with & without quantities, minor works)
JCT Traditional measurement (SBC with approximate quantities)
JCT Traditional cost reimbursement (prime cost building contract)
JCT D&B
JCT Management
JCT Partnering
ACA Form of Building Agreement
ACA Form of Subcontract
ACA Framework Alliance Contract
NEC A Priced Contract with Activity Schedule
The activity schedule is the key fundamental when using NEC Contract Option A. For a developer it’s beneficial as the contractor cannot claim monies for a work element not satisfactorily complete. Careful consideration is required during tender to ensure the schedule is structured in such way as to best manage cash flow. The programme and activity schedule are to be regularly updated taking allowance of any CE’s. Greater financial risk on the contractor but requires scope certainty.
NEC B Priced Contract with Bill of Quantities
the main difference with NEC Option B is the use of a bill of quantities – similar to that of a JCT. Unlike Option A where specific elements of work within an activity schedule are certified for payment upon full completion, when using Option B the Contractor is entitled to be paid interim payments based on Percentage of Completion of each BoQ Item. Greater financial risk on the contractor but requires scope certainty.
NEC C Target Contract with Activity Schedule
Target price agreed based on an activity schedule. If the Contractor overspends and exceeds the target price of the contract then the Contractor and Employer will share this overspend. This is called the ‘pain share’. Equally, if the Contractor delivers the final cost within the target price then this benefit is called the ‘gain share’ or, formally known as the ‘share ranges’. Shared financial risk but still requires scope certainty to set an accurate target cost.
NEC D Target Contract with Bill of Quantities
Similar to option C a target cost is set at the outset of a project, with cost savings and overruns shared based on a pre-agreed formula. However unlike Option C this target cost is based on a BoQ in the same way as a BoQ is produced for Option B.
NEC E Cost Reimbursable Contract
Often referred to as “cost plus.” Under this option the developer will largely take on the financial risk. The contractor is reimbursed for all of their actual costs plus a pre-agreed overhead and profit percentage. Is useful when works cannot be properly defined at the project outset and/or risks associated with the works are high.
NEC F Management Contract
a cost reimbursable contract wherein the works are designed and/or constructed by multiple subcontractors who are contracted to a management contractor. The management contractor will ultimately be responsible for the procurement, co-ordination and implementation of the works in exchange for a fee i.e. the cost/tendered price of works + an agreed percentage. Often, the client takes on the financial risk.
Key parties/ roles within the NEC contracts and their responsibilities
The project manager – administers the contract, similar to the role of engineer under ICE or architect/contract administrator under JCT.
The supervisor – has responsibility for quality, similar to the role of clerk of the works.
The contractor – responsible for delivering the project in accordance with the works information.
The employer – the paying party.
- only contractor and employer in NEC ECSC
Contract admin responsibilities/ requirements under NEC
Under NEC the contract administration duties fall to the Project Manager, however these responsibilities are often delegated to the commercial manager/ QS.
The contract administrator is responsible for administering the terms of the building contract between the parties. Contract administration duties involve;
a) Ensuring that the works are progressing in accordance with the contract programme and therefore that the completion date is achieved by the parties.
b) Report to the employer on progress of works.
c) Managing the commissioning of works.
d) Supervising works and inspecting works.
e) Providing instructions to the contractor.
f) Managing defects.
g) Determining applications for an extension of time.
h) Managing adjustments to the contract price.
i) Keeping records. This could include keeping records of site visits, correspondence etc.
j) Certifying works and issuing Practical Completion Certificates.
Key clauses & procedures within Option A and E NEC contracts
Most NEC3 contracts have nine core clauses:
1. General terms- details any optional clauses
2. Contractor’s main responsibilities- scope of works, references WI
3. Time- key dates
4. Testing and Defects- defects date/ correction period
5. Payment- for option A it is a periodic assessment of the activities that have been completed to date and all those completed are paid. For option E it is an assessment of the defined costs within the period plus the agreed fee, the defined cost is all cost incurred by the contractor not including disallowed cost.
6. Compensation events
7. Title.
8. Risk and insurance- minimum insurance cover
9. Termination.
NEC payment process
- The Contractor submits an application for payment to the Project Manager in a form prescribed by the Works Information not less than fourteen days prior to each assessment date.
- The Project Manager certifies a payment not later than five days after each payment due date which is the later of
- the assessment date and
- fourteen days after the date of receipt by the Project Manager of the Contractor’s application for payment
- Not later than five days after receipt of the payment certificate the Contractor delivers to the Employer (copied to the Project Manager) a VAT invoice
NEC CE process
- If CE instructed by PM they notify Contractor of CE and instruct them to submit a quotation.
- If Contractor aware of CE must notify within 8 weeks of becoming aware
- PM must respond in 1 week and will assess if it should be a CE as per the list in the contract and if so instruct the contractor to submit a quotation. Must also assess if it is an event that should have been subject to an EWN.
- Once Contractor requested to submit quotation, standard response period is 3 weeks unless longer period specified.
- PM has 2 weeks to respond once quotation submitted. If no response the contractor notifies that if it is not responded to within another 2 weeks it is deemed as accepted. (extensions of time for reply periods can be requested).
- Reply will be one of the following;
- an instruction to submit a revised quotation,
- an acceptance of a quotation,
- a notification that a proposed instruction will not be given or a proposed changed decision will not be made or
- a notification that he will be making his own assessment.
NEC Contract Documentation
- form of agreement
- conditions of contract
- contract data part 1 & 2
- prices/ activity schedule/ BoQ
- Works information
- Site information