Risk Flashcards

1
Q

Risk categories

A

A way to group individual project risks for the project team, to ensure we consider the full range of sources of risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where are risk categories described?

A

The risk management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PESTEL

A

Political, economic, social, technological, environmental, and legal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

TECOP

A

Technical, environmental, commercial, operational, and political

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

VUCA

A

Volatility, uncertainty, complexity, ambiguity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk breakdown structure

A

A hierarchical representation of potential sources of risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Risk categorization framework

A

A simple list of categories.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List of identified risks

A

Each project risk has a unique identifier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Risk owner

A

This person is accountable for the risk and its outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Risk responses

A

The controls, mitigations, or other responses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Probability and impact matrix

A

Grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs. Giving a rating helps prioritize the risks. (numbers or words like very high, high, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Decision tree

A

Used to support the selection of the best of several alternative courses of action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Monte Carlo simulation

A

Calculates thousands of different outcomes (end date or end budgets) using various activity assumptions, constraints, risks, issues, and other scenarios to give a probability distribution of the outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sensitivity analysis and tornado charts

A

Helps determine which individual project risks could have the most impact on project outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Strategies for opportunities

A

When an opportunity is outside the scope of the project or would exceed the project manager’s authority to take advantage of it, it is managed at the program level or above. (Escalate, exploit, share, enhance, or accept)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Strategies for threats

A

When the risk or its response is outside the project manager’s authority, or it’s appropriate to escalate to a higher level that is affected by the risk. (Escalate, avoid, transfer, mitigate, or accept)

17
Q

Reserve analysis

A

Compares the remaining contingency reserves to the amount of risk remaining at any time in the project to determine if the remaining reserve is adequate. One way to represent this is with a burndown chat, showing the total risk with the remaining contingency reserve amount. (burndown chart)