Reactor Trips & SI Initiations Flashcards
- Reactor Trips & SI Initiations*
- *
What is the coincidence of the manual Rx Trip?
1 of 2 switches
- Note:*
- Switches located on CP005 and CP007*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the SR Flux - High Rx Trip?
1x105 cps [1/2]
Manual Block: ≥ P-6 (1x10-10 amps) [1/2]
Auto Block: ≥ P-10 (10%) [2/4]
Auto Unblock: < P-6 (1x10-10 amps) [2/2]
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the IR Flux - High Rx Trip?
25% [1/2]
(IR amps equivalent)
Manual Block: ≥ P-10 (10% PR NIs) [2/4]
Auto Unblock: < P-10 (10% PR NIs) [3/4]
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the PR Flux High - Low Rx Trip?
25% [2/4]
Manual Block: ≥ P-10 (10%) [2/4]
Auto Unblock: < P-10 (10%) [3/4]
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the PR Flux High - High Rx Trip?
109% [2/4]
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the PR Flux Rate - High Rx Trip?
5% RTP / 2 sec [2/4]
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the OT∆T Rx Trip?
- *114% RTP [2/4]**
- (± Penalties)*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the PZR Pressure - Low Rx Trip?
1870 psig [2/4]
- *Auto Blocked**: < P-7
- (< P-10 (10%) [3/4] AND < P-13 (10% Impulse Pressure) [2/2])*
- *Auto Unblocked**: ≥ P-7
- (≥ P-10 (10%) [2/4] OR ≥ P-13 (10% Impulse Pressure) [1/2])*
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the RCS Flow - Low Rx Trip?
- Setpoint:*
- *91.8%**
- Coincidence:*
- *< P-8: [2/3 on 2/4]**
- (< 40% PR NIs) [3/4]*
- *≥ P-8: [2/3 on 1/4]**
- (≥ 40% PR NIs) [2/4]*
- *Auto Blocked**: < P-7
- (< P-10 (10%) [3/4] AND < P-13 (10% Impulse Pressure) [2/2])*
- *Auto Unblocked**: ≥ P-7
- (≥ P-10 (10%) [2/4] OR ≥ P-13 (10% Impulse Pressure) [1/2])*
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the RCP UV (15 kV cubicle) Rx Trip?
- *72.6% for 1.5 sec [2/4]**
- (10,014 VAC)*
- *Auto Blocked**: < P-7
- (< P-10 (10%) [3/4] AND < P-13 (10% Impulse Pressure) [2/2])*
- *Auto Unblocked**: ≥ P-7
- (≥ P-10 (10%) [2/4] OR ≥ P-13 (10% Impulse Pressure) [1/2])*
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the RCP 15 kV cubicle UF Rx Trip?
57.2 Hz [2/4]
Will also trip ALL RCPs (DNB Protection)
- *Auto Blocked**: < P-7
- (< P-10 (10%) [3/4] AND < P-13 (10% Impulse Pressure) [2/2])*
- *Auto Unblocked**: ≥ P-7
- (≥ P-10 (10%) [2/4] OR ≥ P-13 (10% Impulse Pressure) [1/2])*
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the OP∆T Rx Trip?
- *108% RTP [2/4]**
- (- Penalties)*
Note:
Unlike OT∆T which has ± Penalties, OP∆T only has - Penalties.
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the PZR Pressure - High Rx Trip?
2380 psig [2/4]
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the PZR Level - High Rx Trip?
92% [2/4]
- *Auto Blocked**: < P-7
- (< P-10 (10%) [3/4] AND < P-13 (10% Impulse Pressure) [2/2])*
- *Auto Unblocked**: ≥ P-7
- (≥ P-10 (10%) [2/4] OR ≥ P-13 (10% Impulse Pressure) [1/2])*
- Note:*
- P-10 driven off PR NIs and NOT RTP*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the S/G Level - Low 2 Rx Trip?
20% [2/4 on 1/4]
- Reactor Trips & SI Initiations*
- *
What will cause a SI Initiation?
- ≥ P-11:*
- *PZR Pressure - Low [2/4]**
- 1857 psig*
- *Steam Pressure - Low [2/3 on 1/4]**
- 735 psig*
- No Permissives:*
- *Containment Pressure - High [2/3]**
- 3.0 psig*
- *Manual [1/2]**
Manual Blocked: < P-11: PZR Pressure < 1985 psig [2/3]
Auto Unblocked: ≥ P-11: PZR Pressure ≥ 1985 psig [2/3]
- Note:*
- P-11 Block switches located on CP005
- SI Manual Switches are located on CP001 and CP005
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the PZR Pressure - Low SI Initiation Signal?
1857 psig [2/4]

Manual Blocked: < P-11: PZR Pressure < 1985 psig [2/3]
Auto Unblocked: ≥ P-11: PZR Pressure ≥ 1985 psig [2/3]
- Note:*
- Block switches located on CP005*
- Reactor Trips & SI Initiations*
- *
What is the setpoint of the Steam Pressure - Low SI Initiation Signal?
735 psig [2/3 on 1/4]

Manual Blocked: < P-11: PZR Pressure < 1985 psig [2/3]
Auto Unblocked: ≥ P-11: PZR Pressure ≥ 1985 psig [2/3]
- Note:*
- Block switches located on CP005*
- Reactor Trips & SI Initiations*
- *
What will cause a logic cabinet urgent alarm Rx trip?
- *Loose / removed circuit card**
- (any except isolation boards)*
- *Respective actuation train urgent alarm**
- Actuation Cabinet “A” → Logic Cabinet “R”*
- Actuation Cabinet “B” → Logic Cabinet “S”*
Associated bypass breaker closed AND Racked-In
Input Error Inhibit Sw. in “Inhibit”
- *Switches NOT in “OFF”**
- Logic Test Sw. ‘A’*
- Permissive Test Sw.*
- Memory Test Sw.*
Coincidence required is [2/2].
- Note:*
- Do not confuse input error inhibit sw. with multiplexer test sw. Both have an inhibit position.*

- Reactor Trips & SI Initiations*
- *
What is the setpoint of the Containment Pressure - High SI Initiation Signal?
3.0 psig [2/3]
- Note:*
- Unlike PZR Pressure - Low and Steam Pressure - Low which can be blocked on P-11, Containment Pressure - High is active at all times.*
- Reactor Trips & SI Initiations*
- *
What will cause an actuation train urgent alarm Rx trip?
Loss of AC power to safeguards actuation train
Actuation train in test
Safeguards test cabinet in test
Coincidence required is [2/3].
- Reactor Trips & SI Initiations*
- *
What are the SSPS Rx trips?
- *Logic Cabinet Urgent Alarm [2/2]**
- Actuation Cabinet “A” → Logic Cabinet “R”*
- Actuation Cabinet “B” → Logic Cabinet “S”*
Actuation Train Urgent Alarm [2/3]
Master Relay Defeat Sw.
Loss of both 15 VDC OR both 48 VDC in a logic train